JUDGMENT : Item 'A' 1. List on November 26, 1996 Item 'B' 2. Mathura Refinery has placed on record the mile-stone scheduled for Mathura Refinery for 50 beded hospital project. The Project commence on October 1, 1996. It is stated that all the six stages of the hospital indicated in the schedule shall be complete by August 30, 1999. By and large, we agree with the schedule. We direct that the construction of the hospital shall be complete by December 31, 1998 and the hospital shall be commissioned fully thereafter within 3 months. By April 1, 1999 the hospital should be admitting and treating patients of the area. We direct the Mathura Refinery to keep on filing the progress report after every 4 months. Item 'C' 3. Pursuant to this Court's order dated October 29, 1996 regarding brick-kiln operators, Mr. Pradeep Mishra states that the matter is being examined at the level of the U.P. Government. Mr. Mishra further states that all the thermal power stations have been directed to supply fly-ash free of charge to the brick-kiln owners. 4. Pursuant to this Court's order dated November 1, 1996, an affidavit has been filed by R.N. Paliwal, Special Secretary, Department of Urban Development, Government of U.P., Lucknow. It is stated that as desired by this Court, the matter regarding garbage disposal and cleanliness of the city of Agra was considered by the Secretary, Department of Urban Development, Chief Secretary, State of U.P. and the Governor of U.P. In the affidavit, 14 measures adopted in doing the needful have been listed. It is stated that one Manoj Singh has been appointed as Mukhya Nagar Nigam Adhikari, Agra and a Special Committee has been appointed to look into the matter. 5. We direct the Central Pollution Control Board to send an inspection team to Agra and file report in this respect within 10 days. 6. To come up on December 3, 1996.