STANDARD CHARTERED BANK v. CIVIL JUDGE JUNIOR DIVISION HALDWANI
2006-07-08
B.C.KANDPAL
body2006
DigiLaw.ai
B. C. KANDPAL J. By means of this petition the appli cants, who are the Standard Chartered Bank and its Officers, have challenged the order dated 22-5-2006 passed by the Judicial Magistrate, Haldwani taking cognizance in criminal complaint case No. 444/2006, U/ss 420, 406, 120-B I. P. C. against the applicants. 2. Brief facts of the case are that the applicant No. 1 is the Standard Chartered Bank, a Company incorpo rated in England by Royal Charter, and having its principal office at 1, Aldermanbury Square, London and one of its branch offices in India at Mumbai. The applicants Nos. 2 and 3 are the Officers of the Bank. 3. The respondent Nos. 2 M/s Mega Motors Limited is a partnership firm and an approved dealer of respond ent No. 3 M/s Tata Motors Limited hav ing its office at Tikonia, Nainital Road, Haldwani, Uttaranchal, a criminal com plaint before the court of Judicial Mag istrate, Haldwani U/ss 406,420 and 120-B I. P. C. against the Tata Motors Ltd. and its Officers as well as the peti tioner Bank. 4. The statement of the complain ant was recorded U/s 200 Cr. RC. and thereafter the statement of the witness of the complainant was recorded U/s 202 Cr. RC. The Judicial Magistrate af ter having perused the complaint as well as the statement of the complainant and his witness passed an order on 22-5-2006 taking cognizance in the matter by issuing summons to the petitioners. 5. The petitioners have thus chal lenged the summoning order as well as the proceedings of the criminal com plaint case No. 444/2006, pending in the court of Judicial Magistrate, Haldwani, by way of this petition. 6. The respondent No. 2 has filed the counter affidavit denying the allega tions made in the petition. 7. Heard learned counsel for the parties and perused the record. 8. Learned counsel for the petition ers has submitted that from a bare pe rusal of the complaint no offence is dis closed against the petitioners. It has also been submitted that there has been no entrustment of the property with the Bank as it is an interse dispute between Tata Motors Ltd. and the Mega Motors Ltd. The record reveals that on the re quest of respondent No. 2 the Bank pro vided flexi loan facility under channel fi nance programme upto a maximum amount of Rs.
50 Lakhs for their pur chases of products for domestic sales from Tata Motors Limited. The peti tioner has filed the copy of the loan agreement along with the petition. The record further reveals that the complain ant, who is respondent No. 2 in this case, was in possession of 11 commer cial vehicles and Tata Motors Ltd. issued a letter dated 18-5-2005 to the com plainant in order to take re-possession of the unsold vehicles and it was stated in that letter that the proceeds from the sale of above said vehicles will be ad justed towards the over dues of the Bank. The letter is contained as Annexure-P-2 to this petition. The com plainant thereafter wrote a letter on 13-/-2005 stating therein that M/s Tata Motors had taken back 11 CVs with their invoices and accessories etc. and it was agreed by them that the above said amount would be adjusted against their trade, advance overdue account with the Bank. This letter has been annexed as Annexure- R3 to the petition. Thereaf ter the petitioner No. 3? who is head of Supply Chain Financing in the Bank wrote a letter to Chief Executive Officer of M/s Tata Motors Finance with the request to sell off 11 CVs repossessed by them from the complainant and remit the proceeds of the sale towards part payment of the outstanding dues of the Bank. The copy of the letter is also annexed as Annexure- P-4 to the peti tion. 9. The contention of the Bank is that the respondent No. 2 who is the complainant had deposited post dated cheques with the Bank towards repay ment of the financial facility and since the amount of Rs. 52,15,610=73 R was due against the complainant as on 20-10-2005 and the complainant failed to pay the same, the Bank deposited the aforesaid cheque. The cheque got dis honoured on presentation, therefore the Bank through its counsel issued a legal notice to the complainant M/s Mega Motors Ltd. The Bank again wrote a letter to the complainant on 13-3-2006 thereby stating that the current out standing amount against him was Rs. 37,16,092=81 P. which was to be paid by the complainant, copy of this letter has been annexed as Annexure P-II.
37,16,092=81 P. which was to be paid by the complainant, copy of this letter has been annexed as Annexure P-II. The contention of the petitioners is that the criminal complaint filed by the complain ant/respondent No. 2 is a counterblast to the proceedings initiated by the Bank U/s 138 of the Negotiable Instruments Act. 10. Learned counsel for the re spondent No. 2 has argued that in case if the factual foundation for the offence has been laid in the complaint, then the court should not hasten to quash crimi nal proceedings during investigation stage merely on the premise that one or two ingredients have not been stated in detail. 11. From bare perusal of the com plaint, it is quite clear that there are no specific allegations against the petitioner/ Bank and its Officers as to how the of fence as alleged has been committed by them. Unless the complaint shows that the petitioners had dishonest or fraudu lent intention at the time the complain ant parted with the money, it would not amount an offence U/s 420 I. P. C. and it may only amount to breach of con tract. The guilty intention is an essential ingredient of the offence of cheat ing and therefore to secure conviction "mens rea"on the part of the accused must be established in order to consti tute the offence of cheating, the inten tion to deceive should be in existence at the time when inducement was offered. I, myself, am unable to reach to the conclusion that there is any unlawful gain to the petitioners in the instant case. Mere breach of contract cannot give rise to the criminal prosecution for cheating unless fraudulent or dishonest intention is shown right at the beginning of the prosecution, i. e. the time when the offence is said to have been committed. 12. On the basis of the aforesaid discussion, 1 come to the conclusion that the complaint filed by the respondent No. 2 M/s Mega Motors Ltd. is not maintainable. The order dated 22-5-2006 passed by the Judicial Magistrate, Haldwani, summoning the petitioners for the offences U/ss 406,420,120-B I. P. C. is also liable to be quashed.
12. On the basis of the aforesaid discussion, 1 come to the conclusion that the complaint filed by the respondent No. 2 M/s Mega Motors Ltd. is not maintainable. The order dated 22-5-2006 passed by the Judicial Magistrate, Haldwani, summoning the petitioners for the offences U/ss 406,420,120-B I. P. C. is also liable to be quashed. I am of the view that in case if the proceedings of the criminal case are allowed to con tinue against the petitioners, the same would amount to miscarriage of justice and a sheer abuse of process of court. 13. Accordingly the petitioner is al lowed. The impugned order dated 22-5-2006, as well as the proceedings of criminal complaint case No. 444/2006, M/s Mega Motors Limited Vs. M/s Tata Motors Limited and others U/ss 406,420 and 120-B I. P. C. pending in the Court of Judicial Magistrate, Haldwani, District Nainital are hereby quashed as far as it relates to the petitioners. .