JUDGMENT: 1. This first appeal is preferred by Ambika construction Company . a Contractor with Indian Railways. The appeal is preferred by the said appellant being aggrieved by the modification of award by the District Judge, which was passed by the Arbitrators. 2. The facts are as follows - The appellant is a reputed contractor and it undertakes the Government contracts. In the past, the appellant had successfully completed the various civil construction works of the Indian Railways. The Indian Railways had floated a Tender for the work regarding recapping of bridge No.52 at KM 1064/10-11 between Samnapur and Charegaon Stations on Gondia-Jabalpur Section. The value of the said contract was Rs.5,08,878.95. The time stipulated for completion of work was of eight months commencing from 24/11/1987. There was, therefore, an agreement between the appellant and the South Eastern Railway with regard to this work. The contract consisted of reciprocal promise to be performed by each party. It is the contention of the appellant that in pursuance of the contract, the appellant made all necessary arrangements to see that the contract work is completed within time but the respondent-Railways failed and neglected to perform its part of the contract. The appellant was, in fact, required to mobilise all resources, labour, equipments, machines, tools etc. The respondent-Railway, however, failed to issue the necessary work order immediately. Ultimately, it was issued on 15/3/1988 and the work orders were actually given on 11/4/1988, 6/5/1988 and 10/8/1988. The delay in issue of these orders resulted into infrastructure, men and machines lying idle. The Railways also failed, according to the appellant, to provide work drawings. During the course of the execution of work, substantial changes were made in the quantity of earth work and other work of which joint measurements were taken and recorded in the measurement books. The measurement taken, however, were arbitrarily reduced. The result was, the final bill pertaining to work order was grossly under- billed. Since the dispute arose with regard to the final bill, the matter was referred to the Arbitrators. The Arbitrators passed an award. Being aggrieved by that order passed by the Arbitrators, the Indian Railways i.e. the respondent preferred an application under Section 34 of the Arbitration and Conciliation Act, 1996 before the learned District Judge. Since the dispute arose with regard to the final bill, the matter was referred to the Arbitrators. The Arbitrators passed an award. Being aggrieved by that order passed by the Arbitrators, the Indian Railways i.e. the respondent preferred an application under Section 34 of the Arbitration and Conciliation Act, 1996 before the learned District Judge. The learned District judge modified the Award, in as much as, he disallowed the claim in respect of Claim No.3.2 and he completely set aside the claim Nos.4,5 and 6 awarded by the Arbitrators. Being aggrieved by this order, the Ambika Construction Company . the appellant has preferred this appeal. 3. The respondent justifies order passed by the District Judge. The respondent denies that there was any delay on the part of the respondent in supplying the material, drawings etc. It is the contention of the respondent that in fact the appellant-contractor did not carry out the work in time. 4. I have heard the learned counsel for the appellant and the respondent-Railways. 5. The learned District Judge has set aside the award of the Arbitrators in respect of claim no.3.2, 4,5 and 6 and has confirmed the award in respect of other claims. Section 34 of the Arbitration and Conciliation Act gives out the ground upon which an Arbitrators award can be set aside. Without dilating more on this aspect, it would be worthwhile to mention here that this court in the First Appeal No.601 of 2005 (Union of India .vs. M/s. Ambika Construction) taking a stock of various decisions of the Supreme Court and other High Courts has laid down certain propositions upon which award could be set aside. They are as follows - 15. The propositions that emerge from a survey of these decisions could be summarised as under - 1) Arbitral award can be challenged before a court only on grounds specified in S.34 of the Act and scope of enquiry in appeal under Section 37 cannot extend beyond those grounds. They are as follows - 15. The propositions that emerge from a survey of these decisions could be summarised as under - 1) Arbitral award can be challenged before a court only on grounds specified in S.34 of the Act and scope of enquiry in appeal under Section 37 cannot extend beyond those grounds. 2) Challenge to an award on the ground of being in conflict with public policy of India would be permissible if the award is : a) contrary to fundamental policy of Indian law; or b) c