Executive Engineer, Irrigation Department, Lower Vana Project, Wardha v. Maroti Bapurao Auchat
2009-10-09
G.S.SINGHVI, R.V.RAVEENDRAN
body2009
DigiLaw.ai
ORDER : R.V. Raveendran, G.S. Singhvi, JJ. The petitioners counsel seeks four weeks time to produce: (1) the plan showing the original sanctioned alignment; (2) the plan showing the actual alignment; (3) the plan superimposing the actual alignment over the sanctioned alignment to highlight the difference; (4) the photographs of the land; (5) the extent of bifurcated land on either side of canal in Survey No. 174. (6) the protective measures proposed by the petitioner to ensure that the un-acquired portion of the land can be made cultivable by avoiding seepage; 2. It is open to the petitioner to directly make an offer of Rs. 5 lakhs as compensation in lieu of dismantling and fresh construction of canal without prejudice. Adjourned by four weeks.