ORDER IAs Nos. 2 and 92, 37 1. We are told that several applications are pending since the National Board for Wild Life (for short "NBWL") has not submitted its latest report/developments in these matters. The learned counsel representing NBWL is not present. We are not in a position to give any further directions as regards these matters. 2. The Member-Secretary of NBWL is directed to be present on the next date of hearing with response for IAs Nos. 2 and 92. 3. List on 11-8-2009. IAs Nos. 52 and 95 4. The respondent, State of Uttarakhand and other respondents in these applications are directed to file their response to the affidavit of MoEF dated 21-7-2008 before the next date of hearing. 5. List on 11-8-2009. IAs Nos. 54, 67 and 76 6. Adjourned to 11-8-2009. IAs Nos. 78, 79 and 109 7. These applications are rejected in view of the rejection of the projects by NBWL. IAs Nos. 83 and 84 8. Report of FAC is awaited. 9. List on 11-8-2009. IA No. 100 10. There was a proposal to send two lion cubs from the State of Gujarat to the State of Madhya Pradesh. The proposal was objected to by the State of Gujarat for various reasons. All these objections were considered by NBWL and it supported the proposal for rejection of objections raised by the State of Gujarat. 11. Now the State of Gujarat has filed a further affidavit in response to the affidavit of MoEF dated 21-7-2008 wherein detailed reasons for objecting the proposal were given. A copy of the further affidavit be furnished to NBWL and NBWL will have a fresh look on the subject and file a report regarding the same. If NBWL feels necessary for filing the report, both the States may be heard. IAs Nos. 104-05 12. Adjourned to 11-8-2009. 13. The State may file its response in the meanwhile. IA No. 106 14. The learned counsel for the State is not present nor has it filed its response to the affidavit of MoEF dated 21-7-2008. 15. The State is directed to submit its response as regards the recommendation of NBWL before the next date of hearing. 16. List on 11-8-2009. IAs Nos. 114-15 17. Pakal Dul Hydroelectric Project of National Hydroelectric Power Corpn. Ltd. was examined by NBWL and it has given a conditional consent to the said project.
15. The State is directed to submit its response as regards the recommendation of NBWL before the next date of hearing. 16. List on 11-8-2009. IAs Nos. 114-15 17. Pakal Dul Hydroelectric Project of National Hydroelectric Power Corpn. Ltd. was examined by NBWL and it has given a conditional consent to the said project. NHPL to execute the work, has to pay Rs.236 crores including Rs.100 crores for the corpus fund for the protected area for the conservation of wildlife by NBWL. NHPL has not deposited the amount. 18. Let the money be deposited. 19. List on 11-8-2009. IAs Nos. 116, 117 and 120 20. Issue notice to the State of Uttarakhand and the Chief Wildlife Warden. The learned counsel appears and accepts notice on behalf of the Chief Wildlife Warden. 21. List on 11-8-2009. IAs Nos. 118, 119 and 121 22. Adjourned to 11-8-2009. IA Nos. 122-23 23. A copy of these applications may be furnished to NBWL. IAs Nos. 126-27 24. Adjourned to 11-8-2009. IAs Nos. 128-29 25. Issue notice. 26. List on 11-8-2009. Court Masters