Madan Lal Bajaj Construction v. State of Jharkhand
2011-05-11
DHIRUBHAI NARANBHAI PATEL
body2011
DigiLaw.ai
ORDER D.N. Patel, J. 1. The present writ petition has been preferred mainly for the reason that the Petitioner is one of the bidders for construction of two godowns having capacity of 2500 metric tones, for storage of foodgrains and fertilizers and one more godown having a capacity of 1000 metric tones in the campus of Agricultural Produce Market Committee, Jamtara. The tender notice is at Annexure-1 to the memo of the petition, which is dated 22nd December, 2010. 2. It has been submitted by the counsel for the Petitioner that the Petitioner has offered the price for the construction of the aforesaid godowns at Rs. 1,73,86,860.25p against the estimated cost of the godowns published in the tender, which is at Rs. 2,16,31,400/-. Thus, against the aforesaid estimated cost, the Petitioner is ready and willing to construct the aforesaid godowns with 15% lesser amount in competition with other bidders. The Petitioner was decided to allot the work by the Respondents by a letter dated 27th January, 2011 (Annexure-2 to the memo of the petition), but, to the utter surprise of the Petitioner without cancelling the aforesaid letter of intent Issued in favour of the Petitioner and without assigning any reason to the Petitioner and without giving any notice to the Petitioner, abruptly, arbitrarily and unilaterally the notice inviting tender dated 22nd December, 2010 (Annexure-1) was cancelled and a fresh notice inviting tenders was published on 28th February, 2011, which is at Annexure-4 to the memo of the petition, which is under challenge in this writ petition mainly on the ground that the Petitioner is ready and willing to complete the work against estimated cost of Rs. 2,16.31,400/-for Rs. 1,73,86.860.25p. 3. Counsel for the Respondents-State submitted that there is a breach of Clause-18 of the condition, which reads as under: 18. Tenderers should quote his rate on overall items in percentage above or below Both in figure and words over amount of approved BOQ. Rate quoted 15(fifteen) percent lessor above the BOQ will be rejected. 4. It further appears that the Respondents have No. objection so far as the efficiency of the present Petitioner is concerned. Likewise, the Respondents-State has No. complain about financial capacity of the present Petitioner. Except the aforesaid condition, No. other condition has been violated. 5. Counsel for Respondent Nos. 2 and 3 has submitted that they are abide by the decision taken by the Respondents-State.
Likewise, the Respondents-State has No. complain about financial capacity of the present Petitioner. Except the aforesaid condition, No. other condition has been violated. 5. Counsel for Respondent Nos. 2 and 3 has submitted that they are abide by the decision taken by the Respondents-State. The godowns are belonging to the Government. The finance is coming from the Government and the present Respondent Nos. 2 and 3 have to store the foodgrains and/or fertilizers in the aforesaid godowns. Thus, Respondent Nos. 2 and 3 are the beneficiaries of the construction and they are accepting the arguments, canvassed by the State. 6. Having heard counsel for both the sides and looking to the facts and circumstances of the case, I hereby, quash and set aside Annexure-4 i.e. notice inviting tender No. 4 for the year, 2010-2011 dated 28th February, 2011 issued by Respondent No. 3 so far it relates to the construction of godowns at Jamtara, mainly for the following facts and reasons. (i) It appears that initially, on 22nd December, 2010, notice inviting tenders was published and the following construction work for the Jamtara District, was to be done: Construction of 2 Nos. 2500 M.T. Godown storage for food grain and Fertilizers. and 1 No. godown having the storage capacity of 1000 M.T. with electrification for seed and P.C.C. Road, with parking in the campus of APMC Jamtara. Thus the aforesaid construction work was to be done and the estimated cost of the work was at Rs. 2.16,31,400/-. (ii) The Petitioner alongwith others applied for the construction work to be done by them. Petitioner having one of the bidders offered Rs. 1,73,86,860.25p. and he is ready and willing to complete the work within the aforesaid amount. Petitioner being the lowest bidder and was found otherwise suitable and capable, the work was decided to allot to the present Petitioner. (iii) The aforesaid decision was communicated to the Petitioner by letter dated 27th January, 2011 which is at Annexure-2 to the memo of the present petition. Thus, already a decision to allot the work to the Petitioner was taken. (iv) It appears that some dissatisfied soul must have applied to the Government that there are some irregularities and Government also, without application of mind came to a conclusion that as the Petitioner has quoted lesser amount for the construction work to be done, the Petitioner cannot be given a contract instead of Rs.
(iv) It appears that some dissatisfied soul must have applied to the Government that there are some irregularities and Government also, without application of mind came to a conclusion that as the Petitioner has quoted lesser amount for the construction work to be done, the Petitioner cannot be given a contract instead of Rs. 1,73,86,860.25p. If the Petitioner would have quoted one rupee more, he would have fallen within the criteria of 15% of the estimated cost. (v) Looking to the aforesaid condition and interpretation made by the counsel for the Respondents, it appears that if the estimated cost is Rs. 100/- then the bidders can offer the cost of construction ranging from Rs. 85/- to Rs. 115/- but, if anybody is quoting Rs. 84/- or Rs. 116/- he will be disqualified. This is a gist of the condition. In view of the aforesaid condition and the interpretation made by the Respondents, it appears that if the Petitioner would have quoted one rupee more, he would have given a contract. This reflects non-application of the mind by the Respondents. (vi) Counsel for the Petitioner, in presence of his client, voluntary invites supervision by any of the Committee appointed or constituted by the Respondents and the work of the construction of the godowns will be completed within the aforesaid amount to the satisfaction of the Respondents and/or to the satisfaction of the Committee appointed or constituted by the Respondents over and above, regular supervision by the Committee appointed or constituted by the Respondents so that within the aforesaid amount (which is 15% lesser than estimated cost, published by Respondents) all the three godowns will be completed. This condition, the Petitioner is inviting, over and above, the regular conditions. (vii) Such type of non-application of mind happens only with the governmental contracts. If a Petitioner would have quoted one rupee more the Respondents have No. objection, but, the Government has not appreciated the fact that the Petitioner is completing the work to the satisfaction of the Respondents and/or to the satisfaction of the Committee appointed or constituted by the Respondents within the aforesaid rupees i.e. Rs. 1,73,86,860.25p. 7. As a cumulative effect of the aforesaid facts and reasons, I hereby, quash and set aside Annexure-4 i.e. notice inviting tender No. 1 of the year, 2010-2011 dated 28th February, 2011 so far it relates to Jamtara Distric:.
1,73,86,860.25p. 7. As a cumulative effect of the aforesaid facts and reasons, I hereby, quash and set aside Annexure-4 i.e. notice inviting tender No. 1 of the year, 2010-2011 dated 28th February, 2011 so far it relates to Jamtara Distric:. As the notice inviting tender is quashed and set aside, I hereby, direct the Respondents to issue work order with commencement date so that the work can be completed within the period of eleven months. 8. Accordingly, this writ petition is allowed and disposed of. Petition allowed.