Abdul Kader Sk. @ Abdul Kader v. The West Bengal State Electricity Distribution Company Ltd.
2011-05-11
JAYANTA KUMAR BISWAS
body2011
DigiLaw.ai
Judgment : The Court: The art.226 petition is disposed of directing the licensee under the Electricity Act, 2003 to decide the petitioner’s application for supply of electricity for operating a pump on the basis of the certificate (at p.21), within three weeks from the date of communication of this order. After making enquiry, recording proceedings and hearing parties, the licensee shall give a reasoned decision that shall be communicated to all at once. If the petitioner is entitled to supply, then supply shall be effected immediately. No costs.