Research › Search › Judgment

Gujarat High Court · body

2012 DIGILAW 179 (GUJ)

Amratlal B. Tank v. Surat Municipal Corporation

2012-03-05

RAJESH H.SHUKLA

body2012
Judgment ( 1. ) THE present First Appeals have been filed by the appellant original claimant under Section 39 of the Arbitration Act challenging the judgment and order in Lavad Application No.57/1991 dated 24.10.1997 passed by the Civil Judge (S.D.), Surat dismissing the Lavad Application on the grounds set out in detail in memo of appeals inter alia that the Court below has wrongly come to the conclusion and has failed to appreciate the material evidence on record. It is contended that the Court below has erroneously come to the conclusion that the appellant has committed breach of the contract. It is also contended that the Court below has committed an error in interpreting the provisions of law and has failed to appreciate the judgment reported in 1996 (1) GLH 169. ( 2. ) HEARD learned advocate Mr.K. G. Sukhwani for the appellant and learned senior advocate Mr.Prashant G. Desai with learned advocate Mr.Nilesh Pandya for the respondent. ( 3. ) LEARNED advocate Mr.K. G. Sukhwani for the appellant referred to the papers and tried to submit that the Court below has failed to appreciate the material evidence and has failed to appreciate that the work has been done by the contractor and Thereafter, an agreement was terminated resulting in loss of profit. LEARNED advocate for the appellant submitted that the matter was referred to the arbitrator as per the arbitration clause and, Therefore, this aspect ought to have been considered. LEARNED advocate for the appellant submitted that the Court below has gone into merits of the case and substituted his own view, which is not permissible. In support of his submission, he has referred to and relied upon the decision in the case of M/s.Hindustan Tea Co. Vs. M/s.K. Sashikant and Co., reported in AIR 1987 SC 81 . He has also referred to and relied upon the decision in the case of Puri Construction Pvt. Ltd. Vs. Union of India, reported in AIR 1989 SC 777 and submitted that as provided regarding the scope, the Court cannot examine the correctness of the award. It was submitted that the jurisdiction of the Court is limited, as expressly indicated in the Act, and it has no jurisdiction to sit in appeal and examine the correctness of the award on merits. It was submitted that the jurisdiction of the Court is limited, as expressly indicated in the Act, and it has no jurisdiction to sit in appeal and examine the correctness of the award on merits. He has, Therefore, emphasized and submitted that the Court has entered into the detailed examination as scrutiny of evidence on the basis of the objection raised regarding the claim. He, Therefore, submitted that the Court below has committed an error and There is jurisdictional error in interfering with the award made by the Arbitrator. LEARNED advocate for the appellant has also referred to and relied upon the decision of the Honble Apex Court in the case of M/s.Sudarsan Trading Co. Vs. The Govt. of Kerala and another, reported in AIR 1989 SC 890 and submitted that the reasons for setting aside the award are required to be given. It was submitted that the appreciation of evidence is not required to be re-appreciated and considered by the Court and when the parties have selected their own forum and forum has decided on the basis of evidence, it cannot be substituted or decided on merits. He has also referred to and relied upon the judgment of the Honble Apex Court in the case of Food Corporation of India Vs. Joginderpal Mohinderpal, reported in AIR 1989 SC 1263 and submitted that the scope of interference of the award given by the Arbitrator is limited on the ground of misconduct or misconduct of the proceedings. The Honble Supreme Court has observed that an arbitrators award may be set aside for error of law appearing on the facts of it. Though this jurisdiction is not to be lightly exercised. The award can also be set aside if, inter alia, the arbitrator has misconducting himself or the proceedings. It is difficult to give an exhaustive definition as to what may amount to a misconduct on the part of the arbitrator. It is not misconduct on the part of an arbitrator to come to an erroneous decision, whether or not his findings of face are supported by evidence. LEARNED advocate for the appellant has, Therefore, submitted that if the view taken by the arbitrator is possible then the award cannot be challenged. LEARNED advocate for the appellant has also referred to and relied upon the decision of the Honble Supreme Court in the case of M/s. Associated Construction Vs. LEARNED advocate for the appellant has, Therefore, submitted that if the view taken by the arbitrator is possible then the award cannot be challenged. LEARNED advocate for the appellant has also referred to and relied upon the decision of the Honble Supreme Court in the case of M/s. Associated Construction Vs. Pawanhans Helicopters Pvt Ltd. reported in AIR 2008 SC 2911 , the head note 'A' to emphasis the submissions regarding the scope and power of the Court. He pointedly referred to the head note and submitted that in that case also, There was correspondence between the contractor and the Government with regard to the pending dues and the payment was denied. He has also referred to and relied upon decision of the Honble Supreme Court in the case of M/s.Ravindra Kumar Gupta and Co. Vs. Union of India, reported in AIR 2010 SC 972 and submitted that unless findings recorded by the arbitrator are said to be perverse, same cannot be substituted on appreciation of evidence. ( 4. ) LEARNED senior counsel Mr.Prashant G. Desai with learned advocate Mr.Nilesh Pandya for the respondent has referred to the impugned judgment and order passed by the learned Civil Judge (S.D.), Surat in Lavad Application No.57/1991 filed by the appellant under the provisions of the arbitration. He submitted that the tender was invited with regard to the rain water outlet plan and the tender of the appellant was accepted as per the resolution of the respondent ' Corporation dated 05.02.1988. The work order was given on 17.02.1988 and it was handed over to the contractor on 05.03.1988. LEARNED senior advocate Mr.Desai submitted that the agreement was also executed between the parties and the appellant was required to finish the work within one year i.e. on or before 26.02.1989 as per the terms and conditions of the contract. However, in spite of repeated oral request, the work was not in progress satisfactorily and ultimately, the notice was issued. LEARNED senior advocate Mr.Desai submitted that in spite of such reminder, when no progress report was shown, a show-cause notice was issued on 03.12.1988. The said show-cause notice was replied on 07.12.1988. However, in spite of repeated oral request, the work was not in progress satisfactorily and ultimately, the notice was issued. LEARNED senior advocate Mr.Desai submitted that in spite of such reminder, when no progress report was shown, a show-cause notice was issued on 03.12.1988. The said show-cause notice was replied on 07.12.1988. Therefore, again second show-cause notice dated 11.08.1989 was given and, There was some correspondence between the respondent ' Corporation and the appellant ' contractor and ultimately, the respondent ' Corporation was compelled to terminate the contract of the appellant, as per the resolution of the Standing Committee. LEARNED senior advocate Mr.Desai submitted that even before such termination and the resolution was passed by the Standing Committee, the appellant was called personally and was asked whether he wishes to finish the work and the appellant has provided further opportunity to complete the work. However, as he was not ready and willing to finish the work, the contract was terminated and the work was completed by the respondent ' Corporation. LEARNED senior advocate Mr.Desai from the record pointed out that the Corporation demanded from the appellant in writing that he was not ready and willing to complete the work. LEARNED senior advocate Mr.Desai submitted that in the meantime, he gave notice invoking the arbitration clause and demanded appointment of the arbitrator and Therefore, the arbitrator was appointed. LEARNED senior counsel Mr.Desai referred to the condition No.50 of the contract and submitted that it was not covered in the dispute between the parties. He, Therefore, submitted that the arbitrator had no right to decide of issues between the parties which have not covered by such arbitration clause. He submitted that the appellant has raised some of the disputes regarding condition of the tender which is not permissible. Similarly, some of the documents which were not permissible have been entertained and Thereby has committed error for which the Court has discussed in the impugned judgment. He, Therefore, submitted that the present appeals may not be entertained. LEARNED senior counsel Mr.Desai submitted that before rejecting the claim of the respondent ' Corporation and referring to clause in the contract, an award has been passed. Therefore, clause providing recovery of the damages of breach of the conditions of the contract was not believed and accepted by the arbitrator and the finding was given. LEARNED senior counsel Mr.Desai submitted that before rejecting the claim of the respondent ' Corporation and referring to clause in the contract, an award has been passed. Therefore, clause providing recovery of the damages of breach of the conditions of the contract was not believed and accepted by the arbitrator and the finding was given. LEARNED senior advocate Mr.Desai submitted that in fact, the arbitrator had failed to appreciate the contract and the terms and conditions of the contract which provide for mutual rights and obligations. LEARNED senior advocate Mr.Desai contended that some of the claims were allowed partly and other which were not allowed. Therefore, it is against the said Lavad Application No.57/1991 filed by the appellant for making the award as rule of Court was sought to be stayed by filing Civil Misc. Application No.60/1991 which was allowed and Lavad Application No.57/1991 filed by the appellant was dismissed. On the basis of the entire evidence examined by the Court below, it has been specifically found that the arbitrator has gone beyond the jurisdiction and has proceeded to decide the issue or the claim which has not been referred to under the arbitration clause. LEARNED senior advocate Mr.Desai, Therefore, submitted that the arbitrator had exceeded his jurisdiction and has decided the dispute which were not referred to and has interpreted terms and conditions of the tender which is not permissible. He submitted that while considering that whether the appellant has committed the breach of the contract or not, he has failed to appreciate the material evidence on record. LEARNED senior advocate Mr.Desai has, Therefore, pointedly referred to the testimony of the witnesses including the testimony of the opponent at Ex.68 and Dhirajlal Patel. He has also referred to the correspondence. Referring to the evidence at Ex.73, learned senior advocate Mr.Desai submitted that the date of the award is 31.07.1991 and as per the record at Ex.56, the date is 28.02.1991. He, Therefore, submitted that it reflects in the manner in which the award has been made. ( 5. ) IN view of the rival submissions, the moot question is required to be considered is whether the impugned judgment and award calls for any interference in the present first appeals. ( 6. ) THE main contention which has been raised with regard to the jurisdictional error by the Court. ( 5. ) IN view of the rival submissions, the moot question is required to be considered is whether the impugned judgment and award calls for any interference in the present first appeals. ( 6. ) THE main contention which has been raised with regard to the jurisdictional error by the Court. Though the submissions have made by learned advocate for the appellant that the learned Judge has gone into merits of the case and substituted his own decision and Thereby committed an error is required to be considered. This submission has to be appreciated and considered in the background and evidence and the facts as it is evident from the record and material that in spite of repeated request, the work had not progressed. Even before terminating the contract and passing the resolution by the Standing Committee an opportunity was given to the appellant. There are show-cause notices which have also been issued. Therefore, it is evident that the appellant has failed to carry out the work in compliance with the terms and conditions of the contract. Further when he was asked to give in writing, he sought time and moved an application for appointment of the arbitrator and the arbitrator examined the claims and passed the award in respect of claims which were made by the appellant like loss of profit in respect of the depreciation of the vehicles. THE impugned judgment and order passed by the Court below referred to this aspect in detail and has clearly observed that the contractor had failed to carry out the work as required under the contract. THE Court below has specifically made an observation that the arbitrator has come to conclusion without any basic data. THE specific finding is given that the contractor himself has committed a breach of the conditions and has not finished the work within stipulated period. THE contractor has not submitted the progress report and There is no clause for any extra item and still award has been made for extra item. Further, it has been discussed that for the work which has not done by the contractor, the arbitrator has awarded the compensation. It is specifically observed in the impugned judgment and order that the arbitrator has gone beyond the jurisdiction. Further, it has been discussed that for the work which has not done by the contractor, the arbitrator has awarded the compensation. It is specifically observed in the impugned judgment and order that the arbitrator has gone beyond the jurisdiction. Therefore, if the arbitrator has totally misdirected himself and gone beyond the terms of the reference deciding on issue which has never been referred the dispute never a part of the arbitration, the Court can ascertain and examine such aspect whether it is covered as per the arbitration clause or not. THE view which is taken by the arbitrator should be supported by material and should be falling within the terms of the reference where he has been called upon to decide between the parties. However, if the arbitrator proceeds to decide were never found either in the agreement or in respect of the claims which could have been made even under the terms of the contract. THE arbitrator cannot proceed to examine the terms of the agreement / contract which de hors the material evidence. Therefore, the submissions made by the learned advocate for the appellant referring to the judgments of the Honble Apex Court There can be no quarrel with regard to the scope of the Court that it may not substitute its own decision on merits when the view taken by the arbitrator is plausible. However, it is required to be mentioned that before that it has to be examined whether the arbitrator was within his right and jurisdiction to decide on the issues and whether such issues were referred as per the terms of the agreement / contract between the parties for decision or not. If they are not falling within the terms of the reference or the issues which could be referred to the arbitrator for decision then the arbitrator cannot proceed or decide. It is in these circumstances, it will be open for the Court to examine on the aspects whether the arbitrator has exceeded his jurisdiction or not. Whether the decision is ordered with regard to the claim is based on sound principles, while considering the issues which have been referred to him in the facts of the case. He has proceeded to decide the claims which were not subject matter of the arbitrator. Whether the decision is ordered with regard to the claim is based on sound principles, while considering the issues which have been referred to him in the facts of the case. He has proceeded to decide the claims which were not subject matter of the arbitrator. Similarly, he has considered the issue which were outside his jurisdiction like interpretation of the agreement for the purpose of deciding whether the clause in the agreement would justify a claim or not. When the contractor has not completed the work for which There is no dispute and his contract has been terminated in accordance with law after providing sufficient opportunity, he cannot be permitted to claim like loss of profit in respect of the depreciation of the vehicles or any extra item which has never been found in the agreement. Therefore, when he has decided de-hors such clause in the agreement or material evidence, the Court would examine whether the arbitrator has misdirected himself and decided the proceedings contrary to the material evidence as well as the terms of the agreement. In the facts of the case, when the arbitrator has decided such issues, the Court below has examined which cannot be said to be erroneous. Therefore, the present first appeals cannot be entertained and deserve to be dismissed and accordingly dismissed.