Judgment Valmiki J. Mehta, J. 1. This petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the Act’) is filed by the Delhi Jal Board/petitioner impugning the Award of the Arbitrator dated 10.5.2007, as modified by the Order dated 31.5.2007, whereby, an amount of Rs.13,63,984/- has been awarded in favour of the respondent no.1/Contractor and against the petitioner/objector. Respondent no.1 has also been awarded interest at 9% per annum simple w.e.f 20.8.2002 till realization. 2. The disputes between the parties arose out of a contract for construction of an outfall storm water drain for Tara Apartments, near Tuglakabad Extension and adjoining areas awarded to the respondent no.1 by the petitioner vide Letter of the petitioner dated 16.9.1996. The period of completion of the contract was to be 8 months from the date from which petitioner would ask the respondent no.1 to commence the work under the contract. Before commencement of work in terms of Clauses 11 and 24 of the Contract, the respondent no.1 had to take a Soil Testing Report from a reputed agency and also give approved structural designs and drawings from IIT to the petitioner. Though the Contract was awarded on 16.9.1996, the letter by the petitioner to the contractor to commence the work was given two years later on 1.9.1998 and the respondent no.1 was asked to commence the work from 11.9.1998. From September, 1998, till August, 2002, not much work could be done by the contractor because it has otherwise come on record that there was start and stop and then start and stop and then again start and stop for the work essentially on the ground of either the petitioner not getting the requisite road cutting permission or permission from the police, or these permissions having been expired and not renewed or the police stopping the work or because of monsoon season and so on. Respondent no.1 in the later part of the year 2002 refused to perform the contract on original terms and thus the disputes arose between the parties. 3. Respondent no.1 ultimately invoked the arbitration clause on 20.8.2008 and which has resulted in the impugned Award in favour of the respondent no.1. Respondent no.1 in the later part of the year 2002 refused to perform the contract on original terms and thus the disputes arose between the parties. 3. Respondent no.1 ultimately invoked the arbitration clause on 20.8.2008 and which has resulted in the impugned Award in favour of the respondent no.1. By the subject Award, a counter claim of the petitioner of Rs.4,69,016/- was allowed with respect to steel supplied by the petitioner to the respondent no.1 but not utilized or returned to the petitioner and hence out of the total awarded amount of Rs.18,33,000/-, this amount of Rs.4,69,016/- was reduced resulting in the net amount of Rs.13,63,984/- being awarded in favour of the respondent no.1 and against the petitioner along with interest and costs. 4. Before, I turn to the arguments urged on behalf of the petitioner, it is necessary at this stage, more so in the facts of the present case as are discussed in detail in the Award alongwith the relevant evidences to note the legal position that this Court while hearing the objections under Section 34 of the Act does not sit as an appellate court to re-apprise the findings of facts and conclusions arrived by the award. If two views are possible and the arbitrator takes one possible and plausible view, courts do not interfere under Section 34 of the Act. Courts can only interfere if the award is patently illegal or against the contractual provisions or the findings and conclusions are wholly perverse. The object of stating the aforesaid legal position is that the impugned Award is a detailed Award which refers to the facts of the case along with the respective correspondences between the parties along with the other documents relevant to determine the disputes and has thereafter held the petitioner guilty of delays and breaches with respect to performances of its obligation under the contract. Accordingly, the Arbitrator in the Award has held that the respondent no.1 was justified in rescinding the contract as the petitioner failed to agree to fresh terms. Arbitrator thereafter has gone claim by claim and on each claim has discussed the respective evidences. By discussing respective evidences led by the parties, the Arbitrator in the Award has taken one possible view, which is permissible in law for arriving at the conclusions. Arbitrator thereafter has gone claim by claim and on each claim has discussed the respective evidences. By discussing respective evidences led by the parties, the Arbitrator in the Award has taken one possible view, which is permissible in law for arriving at the conclusions. Once in the arbitration record there exists the requisite evidence, and such evidence leads to the conclusions as arrived at by the Arbitrator for wholly or partially allowing different claims, t