ORDER The applicant has approached this Court under Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as 'the Act') for appointment of an Arbitrator to resolve the dispute between the petitioner and the respondent. 2. The petitioner had contracted for three works relating to Ezhimala Naval Academy and they are, Agreement No.7/2005-06 which gives rise to A.R. No. 69 of 2014, Agreement No. 8/2007-08 which gives rise to A.R. No. 67 of 2014 and Agreement No. 9/2005-06 which gives rise to A.R. No. 68 of 2014. Agreement No. 7/2005-06 relates to the work of the main building, Agreement No. 8/2007-08 relates to large scale construction and Agreement No.9/2005-06 relates to residential quarters, each valued at Rs.125 Crores, Rs.32.65 Crores and Rs.62.76 Crores respectively. The time for completion of the work was 24 months with respect to Agreement Nos. 7/2005-06 and 8/2007-08 and 18 months with respect to Agreement No. 9/2005-06. 3. The petitioner would aver that during the work, several deviations and changes were incorporated by the respondent and large number of revisions of drawings had to be made in all these cases. This has caused the work to go beyond the stipulated period and several extensions had to be given. Several other factors intervened and delayed the progress of the work which has been specified in each of the petitions. It is not necessary for the purpose of these applications to narrate them in detail in this order. 4. The petitioner would contend that the economic viability of the agreement would depend upon the completion of the work. The inordinate delay in completing the work, mainly due to the conduct on the part of the respondent, resulted in considerable increase of cost of construction. According to the petitioner, usually in these types of contracts, an escalation clause will be provided. But for reasons best known to the respondent, it was conspicuously absent in the agreements on hand. The petitioner would assert that as per the various decisions of the various High Courts and Apex Court in such cases, the contractor is entitled to enhanced rate especially when the period for completion of work has been extended by the other party. The various communications sent to the respondent are produced in these applications. The petitioner would assert that as per the various decisions of the various High Courts and Apex Court in such cases, the contractor is entitled to enhanced rate especially when the period for completion of work has been extended by the other party. The various communications sent to the respondent are produced in these applications. It is pointed out by the petitioner that as far as Agreement No.7/2005-06 is concerned, there were 1250 revised drawings and Agreement No.8/2007-08 is concerned, there were 75 revised drawings. In Agreement No.9/2005-06, there were 70 revised drawings. With respect to Agreement No.7/2005-06, 92% of the work had been completed and with respect to Agreement No.8/2007-08, the entire work has been completed and with respect to Agreement No.9/2005-06, 84% of the work had been completed. With respect to Agreement No.7/2005-06, Bank Guarantee worth Rs.6.20 Crores was furnished, while in Agreement No.8/2007-08, Bank Guarantee worth Rs.40 Lakhs was furnished and with respect to Agreement No.9/2005-06, Bank Guarantee worth Rs.1.08 Crores was furnished. 5. The complaint of the petitioner is that without justification, Agreement No.7/2005-06 was terminated on 29.11.2014 and on 19.7.2014 Agreement No.9/2005-06 was terminated. 6. Since disputes and differences arose between the parties with regard to each of the work, it had to be resolved through arbitration going by Clause 70 of the General Conditions. The relevant document is produced as Annexure A10 in A.R. No.68 of 2014. But that clause contains several restrictions and qualifications and also provided that the right for arbitration arises only on alternative arrangement being made by the respondent under condition No.54 relating to cancellation of contract. 7. The respondent resorted to take coercive steps against the petitioner arbitrarily. Petitioner is given to understand that the respondent is taking steps to have the Bank Guarantees encashed. 8. The petitioner would point out that on cancellation of the contracts, it is possible to take recourse to arbitration clause on mutual consent. The communication relating to Agreement No.7/2005-06 is Annexure A11 and that relating to Agreement No.9/2005-06 is Annexure A12. In the petitions, the petitioner has narrated the various claims settled through arbitration. Annexure A22 in A.R. 69 of 2014 and Annexure A14 in A.R. 68 of 2014 are the relevant requests made under the Arbitration and Conciliation Act. There was no response from the respondent. 9. In the petitions, the petitioner has narrated the various claims settled through arbitration. Annexure A22 in A.R. 69 of 2014 and Annexure A14 in A.R. 68 of 2014 are the rele