Research › Search › Judgment

Madhya Pradesh High Court · body

2015 DIGILAW 755 (MP)

Jawaharlal Nehru Krishi Vishwavidyalaya, Jabalpur v. J. H. Kotecha

2015-07-21

ALOK ARADHE

body2015
JUDGMENT 1. These appeals have been filed under section 39(1)(vii) of the Arbitration Act, 1940 (in short ‘the Act’) being aggrieved by the judgments dated 7.3.2001 passed by the Additional District Judge in Arbitration Case No.11-A/2000 and Arbitration Case No.32-A/2000 by which the objections preferred by the appellant against the awards dated 27.9.2000 passed by the sole arbitrator have been rejected. In order to appreciate the appellant’s challenge to the impugned judgments, few facts need mention which are stated infra. 2. The respondent No.1 was appointed as consultant architect for construction of non-residential buildings which were financed by the Indian Council for Agriculture Research, New Delhi and the agreements dated 24.11.1982, 2.12.1983 and 3.12.1983 were executed. Under the aforesaid agreements some of the buildings were constructed whereas some buildings could not be constructed for various technical reasons. As per the version of the appellant, the respondent No.1 was paid the fee which was calculated by it on the basis of cost incurred in construction of the buildings, on the basis of approval accorded by competent authority. The contracts of the respondent No.1 were terminated on 2.5.1988. 3. Being aggrieved, the respondent No.1 filed applications under section 8 of the Act for appointment of an arbitrator. By order dated 17.4.1988, one Mr. Y.R. Khirwadkar was appointed as sole arbitrator to adjudicate the disputes between the parties. In respect of the agreements executed on 24.11.1982 and 2.12.1983, the arbitrator by award dated 27.9.2000 awarded a sum of Rs.8,63,329/- to the respondent No.1 along with interest at the rate of 18% per annum till actual payment is made. The respondent No.1 was also awarded a sum of Rs.25,000/- by way of compensation on account of breach of contract. In respect of agreement executed on 3.12.1983, the arbitrator by award dated 27.9.2000 awarded a sum of Rs.13,972/- along with interest at the rate of 18% per annum w.e.f. 15.9.1987 till actual payment is made to the respondent No.1 and also awarded a sum of Rs.25,000/- by way of compensation on account of breach of contract. 4. Being aggrieved by the aforesaid judgment passed by the Additional District Judge in Arbitration Case No.11-A/2000, the appellant has preferred First Appeal No.247/2001 whereas against the judgment passed in Arbitration Case No.32-A/2000, the appellant has preferred First Appeal No.248/2001. 4. Being aggrieved by the aforesaid judgment passed by the Additional District Judge in Arbitration Case No.11-A/2000, the appellant has preferred First Appeal No.247/2001 whereas against the judgment passed in Arbitration Case No.32-A/2000, the appellant has preferred First Appeal No.248/2001. Since, common questions of law and facts arise in these appeals, they were heard analogously and are decided by this common judgment. 5. Mr. P.N. Dubey, learned counsel for the appellant submitted that clause 9 of the agreement dated 2.12.1983 provides that Arbitral Tribunal shall consist of three members and, therefore, the sole arbitrator could not have been appointed by the Court under section 8 of the Act and the impugned awards are ab initio void. In support of the aforesaid submission, learned counsel has placed reliance on the decision of the Supreme Court in AIR 1994 SC 490 and State of Rajasthan v. Nav Bharat Construction Co. [ (2006)1 SCC 86 ]. 6. It is further submitted that agreement dated 2.12.1983 was executed for non-residential purpose for Jabalpur, Sagar and Sehore however, the sole arbitrator in his award has awarded the claim in respect of other non-residential works also namely, agriculture college, Khandwa and Mandsaur which was not a part of National Agriculture Research Project. In other words, it was not a part of the agreement. Thus, while granting the claim for the works which were not part of the agreement, the arbitrator has misconducted himself. In support of the aforesaid submission, reliance has been placed on the decisions of the Supreme Court in the cases of Food Corporation of India v. Chandu Construction and another [ (2007)4 SCC 697 ], and Union of India v. A.L. Rallia Ram [ AIR 1963 SC 1685 ]. 7. It is also submitted that the arbitrator grossly erred in invoking clauses 3 and 10 of the agreement and erred in holding that the aforesaid clauses give inherent power to include the work not contained in the agreements. It was also pointed out that the claim of the respondent No.1 was barred by limitation, as the claims were due in the year 1985 and the claims were submitted on 28.2.1991 i.e. beyond the period of three years. In support of the aforesaid submission, learned counsel for the petitioner has placed reliance on the decision in the case of S. Rajan v. State of Kerala and Another [ AIR 1992 SC 1918 ]. 8. In support of the aforesaid submission, learned counsel for the petitioner has placed reliance on the decision in the case of S. Rajan v. State of Kerala and Another [ AIR 1992 SC 1918 ]. 8. It was also argued that since the complicated issues of law and fact were involved before the arbitrator, therefore, the same could not have been decided by him and the matter ought to have been referred to the civil Court for adjudication. It was pointed out that even though the appellant preferred the counter claim to the tune of Rs.1.41 lacs before the arbitrator however, while passing the award, the arbitrator, even did not refer to the counter claim filed by the appellant which constitutes misconduct on the part of the arbitrator. It is urged that there was no provision in the agreements for grant of interest with regard to pre-reference period therefore, interest for pre-reference period could not have been granted by the arbitrator. In support of this submission, reliance has been placed in the decision in A.L. Rallia Ram (supra). It is also urged that the work was abandoned by the contractor and the payment of the amount for the work done was already made to the respondent. It is contended that the arbitrator devised his own method for computation of fee payable to the respondent No.1 contrary to the terms and conditions of the agreements. 9. It is also submitted that the respondent No.1 played fraud by manipulating the agreement dated 2.12.1983 and inserted the words (and other stations) with ill intention to seek false claims. However, the arbitrator failed to take note of the aforesaid aspect of the matter and is therefore guilty of misconduct. In this connection, learned counsel for the petitioner has referred to the decision in A. Rangaswamy v. Balasubramania Foundry and others [ AIR 1987 SC 2045 ]. 10. Learned counsel for the petitioner while inviting the attention of this Court to the arbitral proceedings conducted on 5.7.2000, 26.8.2000, 27.8.2000, 9.9.2000, 17.9.2000 and 23.9.2000 submitted that arbitrator refused to grant adjournments and even when valid and cogent reasons were shown before him and proceeded ex parte which constitute misconduct on the part of the arbitrator. 10. Learned counsel for the petitioner while inviting the attention of this Court to the arbitral proceedings conducted on 5.7.2000, 26.8.2000, 27.8.2000, 9.9.2000, 17.9.2000 and 23.9.2000 submitted that arbitrator refused to grant adjournments and even when valid and cogent reasons were shown before him and proceeded ex parte which constitute misconduct on the part of the arbitrator. Lastly, while referring to section 57(2)(C) of the Indira Gandhi Krishi Vishwavidhyalaya Adhiniyam, 1987, it is submitted that the arbitrator grossly erred in granting claim of the aforesaid university in the impugned awards. 11. On the other hand, Mr. Ashok Lalwani, learned counsel for the respondent No.1 while inviting the attention of this Court to the agreement dated 2.12.1983 submitted that Jawaharlal Nehru Krishi Vishwavidyalaya, Jabalpur (In short ‘the JNKVV’) includes successor and assignee as well and include all buildings of the JNKVV. It is further submitted that the agreements were prepared in three copies, one copy was retained by the appellant and other one was retained by the respondent No.1. The respondent No.1 filed the copy in his possession along with the application under section 20 of the Act. While referring to the documents dated 22.12.1983, 24.12.1984 and October, 1985, it was pointed out that the appellant has made payment in respect of other stations including Indore, Ambikapur which shows that the agreement is not forged. While inviting the attention of this Court to paragraph 4 of the reply to the application under section 20 of the Act, it is submitted that the appellant had admitted in aforesaid paragraph that the payment was made to the respondent No.1 in respect of Khandwa and Mandsaur. It was pointed out that by order dated 15.5.2003 a Bench of this Court had directed the appellant to produce original agreement along with affidavit, however, the affidavit was not filed. In the memorandum of the revision, namely, Civil Revision No.139/1990 in paragraph 2 there is reference to other stations. It is also urged that the order appointing arbitrator has attained finality as the same has been upheld by the Supreme Court and, therefore, no challenge can be made to the appointment of the arbitrator. It is contended that last running bill of the respondent No.1 pertains to the year 1987 and the application for appointment of an arbitrator was filed on 29.2.1988 therefore, the claims of the respondent cannot be said to be barred by limitation. It is contended that last running bill of the respondent No.1 pertains to the year 1987 and the application for appointment of an arbitrator was filed on 29.2.1988 therefore, the claims of the respondent cannot be said to be barred by limitation. The appellant did not prefer any cross-objection before the arbitrator therefore, question of adjudication of the same does not arise. It is also argued that the grounds which were not raised before the District Court, cannot be allowed to be raised for the first time in this appeal. In support of the aforesaid submission, learned counsel for the respondent has placed reliance on the decisions in Central Bank of India v. Vrajlal Kapurchand Gandhi [ AIR 2003 SC 3028 ], and Jagvir Singh and others v. State (Delhi Admn.) [ (2007)5 SCC 359 ], and a decision of this Court in Ramjilal Kulshrestha v. State of M.P. and others [ 2012(2) JLJ 321 ], Mehar Singh v. State of Punjab [AIR 1973 Punjab and Haryana 114], and Bihar State Electricity Board v. M/s. Khalsa Brothers [AIR 1988 Patna 304]. It is further submitted that even though there is no provision in the agreements for grant of interest for pre-reference period yet the respondent No.1 is entitled to the interest in view of the provisions of the Interest Act, 1978 and in view of section 4 of the Indian Contract Act, 1872. In support of this submission, reliance has been placed in the decisions of the cases of Secretary, Irrigation Department, Government of Orissa and others v. G.C. Roy [ AIR 1992 SC 732 ], M/s. Saraswati Construction Co. v. Delhi Development Authority [AIR 2004 Delhi 412], and State of Orissa v. B.K. Routrary [ AIR 1999 SC 1101 ]. It was urged that trial Court has grossly erred in reducing the interest awarded by the arbitrator without assigning any reason. Therefore, cross-objections preferred by the respondent No.1 deserves to be allowed. It was stated by learned counsel for the respondent No.1 that he is confining his claim in the counter-claim only to the rate of interest and claim for compensation on account of breach of contract is abandoned. It is also contended that while dealing with the objection to the awards, the trial Court is not supposed to act as Court of appeal and, therefore, cross-objection of the respondent No.1 deserved to be allowed. 12. It is also contended that while dealing with the objection to the awards, the trial Court is not supposed to act as Court of appeal and, therefore, cross-objection of the respondent No.1 deserved to be allowed. 12. By way of rejoinder reply, learned counsel for the appellant submitted that three copies of the agreements were prepared. One was retained by the appellant, other one was retained by the respondent No.1 and the third one was retained by the Chief Engineer (Vice-Chancellor). It is inconceivable that the Vice-Chancellor would make any interpolation in the agreement. While inviting the attention of this Court to the answer given to question No.20 by the respondent No.1 before the arbitrator in his evidence, it is submitted that the respondent has admitted that he himself made interpolation in the agreement. It is also argued that pure question of law can be raised at any stage of the proceeding. 13. I have considered the respective submissions made by learned counsel for the parties and have perused the record. The object of Arbitration is to obtain fair resolution of disputes by an impartial Tribunal without unnecessary delay and expenses and the intervention by the Courts should be restricted. [See : Russell on Arbitration, Twenty-third Edition by David St. John Sutton, Judith Gill and Matthew Gearing] An arbitration in substance ousts the jurisdiction of the Court,except for the purpose of controlling the arbitrators and preventing misconduct and for regulating the procedure after award. The hearing on the merits of the award passed by the arbitrator is not permissible. The Court can interfere with the award only on the grounds set out in section 30 of the Act namely where an arbitrator or an empire has misconducted himself or the proceeding, where and award has been made after the issue of an order by the Court superseding the arbitration or after arbitration proceeding has become invalid and where an award has been improperly procured or is otherwise invalid. It is well settled legal proposition that an award cannot be set aside merely on the ground that in the opinion of the Court award passed by the arbitrator would have been otherwise. It is well settled legal proposition that an award cannot be set aside merely on the ground that in the opinion of the Court award passed by the arbitrator would have been otherwise. In K.P. Poulose v. State of Kerala and another [ AIR 1975 SC 1259 ], it has been held that misconduct under section 30(a) of the Act connotes legal misconduct if the arbitrator on the face of the award arrives at an inconsistent conclusion even on his own finding or arrives at a decision by ignoring very material documents which throw abundant light on the controversy to help a just and fair decision. The aforesaid view was reiterated by the Supreme Court in the decision in the case of Seth Mohanlal Hiralal v. Stat of M.P. [(2003)12 SCC 144]. 14. In G. Ramachandra Reddy and Company v. Union of India and another (2009)6 SCC 414 ], the Supreme Court while setting out legal principles for interfering with the award passed by the arbitrator held that interpretation of a contract may fall within the realm of an arbitrator and the Court while dealing with an award would not reappreciate the evidence. It has further been held that the award containing reasons also, may not be interfered with unless the reasons are found to be perverse or based on a wrong proposition of law and if two views are possible the Court will refrain itself from interfering. It is equally well-settled legal proposition that an arbitrator has to decide the dispute according to the legal right of the parties and not according to what he may consider fair and reasonable and re-appreciation of the evidence by the Court is permissible only when award is erroneous in law and amounts to misconduct by the arbitrator. [See : P. Radhakrishna Murthy v. National Buildings Construction Corporation Ltd. [ (2013)3 SCC 747 ]. 15. In the backdrop of aforesaid well-settled legal position and in view of rival submissions made by learned counsel for the parties, the following issues emerge for consideration in these appeals namely : (1) Whether the appellant can raise the grounds in this appeal which were not raised by it before the District Court. (2) whether in view of clause 9 of the agreement dated 2.12.1983 sole arbitrator could be appointed by the civil Court under section 8 of the Act. (2) whether in view of clause 9 of the agreement dated 2.12.1983 sole arbitrator could be appointed by the civil Court under section 8 of the Act. (3) Whether the respondent No.1 has played fraud by inserting the words and “other stations” in the agreement with ill intention to seek claims. (4) Whether arbitrator committed misconduct in granting claims of the respondent in respect of the works which were not part of the agreements. (5) Whether the arbitrator has wrongly invoked clause (3) and (10) of the agreements while passing the award. (6) Whether the arbitrator has provided reasonable opportunity of hearing to the appellant. (7) Whether non-consideration of the counter claim filed by the appellant by the arbitrator amounts of misconduct. (8) whether the claims of the respondent No.1 are barred by limitation. (9) Whether arbitrator has computed the fee payable to the respondent contrary to the terms and conditions of the agreement. (10) Whether the arbitrator could have awarded interest @ 18% per annum for the per-reference period. (11) Whether the cross-objection filed by the respondent deserves to be allowed. (12) Whether complicated issues of law could have been decided by the arbitrator. (13) Whether arbitrator erred in law in granting claims of Indira Gandhi Krishi Viswavidyalaya in the impugned awards in view section 57(2)(c) of the Indira Gandhi Krishi Viswavidyalaya Adhiniyam 1987. 16. The Supreme Court in the case of State of Maharashtra v. Hindustan Construction Company Limited [ (2010) 4 SCC 518 ], has held that raising a new ground in the memorandum of the appeal for which no foundation was laid down in the application for setting aside the award is not permissible. In view of the aforesaid enunciation of law, it is evident that new ground in the memorandum of appeal for which foundation was not laid in the application for setting aside the award cannot be raised. Accordingly, the issue number (1) is answered. 17. Clause 9 of the agreement dated 2.12.1983 contains arbitration clause, is reproduced below for the facility of reference : “9. Accordingly, the issue number (1) is answered. 17. Clause 9 of the agreement dated 2.12.1983 contains arbitration clause, is reproduced below for the facility of reference : “9. All questions of dispute arising out of or in respect of this agreement except as to any matters the decision on which are expressly provided for, shall be referred to a tribunal of Arbitration consisting of one member to be nominated by the employer, one member nominated by the architect and an umpire to be appointed by the Indian Council of Agriculture Research (ICAR). The decision of the arbitration shall be final and binding on both the parties to the agreement, within the meaning of Indian Arbitration Act 1940 and the Rules thereunder or any statutory modification or re-enactment thereof.” 18. The respondent No.1 filed an application for appointment of an arbitrator on 29.2.1988 in First Appeal No.247/2001 whereas the same was filed on 4.5.1989 in First Appeal 248/2001. The sole arbitrator was appointed vide order dated 17.4.1998 by the Additional District Judge. An application for modification of the order was filed which was dismissed vide order dated 16.10.1998. The said order was upheld in Civil Revision No.1185/1999 vide order dated 1.10.1999 passed by the High Court. The aforesaid order was subject-matter of challenge in SLP (C) No.18450-18451/1999 which was dismissed vide order dated 17.12.1999. Thereafter, miscellaneous judicial case was filed for removal of the sole arbitrator, namely, MJC No.2/1999 which was also dismissed vide order dated 18.3.1999. The order passed by the Additional District Judge was upheld by the High Court in Civil Revision No.903/1999 which was dismissed vide order dated 1.10.1999. From the above narration of the facts, it is evident that the order of appointment of the arbitrator dated 17.4.1998 was challenged up to the Supreme Court and was upheld. Thus, the order by which the sole arbitrator was appointed to adjudicate the disputes between the parties attained finality and binds the parties. [See: State of Kerala v. M.K. Kunhikannan Nambiar [ (1996)1 SCC 435 ]. Therefore, reliance placed by the appellant on the decisions in Government of Andhra Pradesh v. K. Mastan Rao [ AIR 1994 SC 490 ], and Nav Bharat Construction Co. (supra), is of no assistance to them in the facts of the case. Thus, issue number (2) is answered in the affirmative and against the appellant. 19. Therefore, reliance placed by the appellant on the decisions in Government of Andhra Pradesh v. K. Mastan Rao [ AIR 1994 SC 490 ], and Nav Bharat Construction Co. (supra), is of no assistance to them in the facts of the case. Thus, issue number (2) is answered in the affirmative and against the appellant. 19. Consequent upon launching of National Agriculture Research Project Scheme as a part of five year plan, the Indian Council for Agriculture Research, New Delhi entrusted the subprojects for their implementation including the civil works for execution to Jawaharlal Nehru Krishi Vishwavidyalaya, Jabalpur. As per the manual published by the National Agriculture Research Project Scheme, it was mandatory for the University to appoint an architect for planning and designing of these subproject buildings in consultation with the National Agriculture Research Project and to get them approved before their execution. As per the norms laid down by the National Agriculture Research Project, the applications were invited from the reputed firms of the architects along with the terms and conditions for planning and designing of the non-residential buildings of the University under the subprojects of the National Agriculture Research Project. The Executive Engineer vide letter dated 13.7.1982 informed that the respondent No.1 was selected by the Vice Chancellor and his selection was notified by the Executive Engineer vide letter dated 23.11.1982. Subsequently, two agreements were executed on 24.11.1982 for non-residential building of the University. Under the Agreement one building each was to be constructed at Morena, Tikamgarh andAmbikapur whereas under the Agreement dated 2.12.1983, the non-residential buildings at Jabalpur, Sihore and Sagar were to be constructed. Thereafter the work orders were issued to the respondent No.1. Clause 3 of the Agreements stipulated that the architect would be paid stage wise fee by the employer in accordance with the schedule given thereto. Clause 10 of the agreements reads as under : “10. Notwithstanding what is mentioned in para 3 above, the parties above named shall be free to negotiate and agree upon different rates and different mode of payment for other works taking into consideration the nature of the work etc.” 20. Admittedly, the respondent No.1 made a claim before the arbitrator for works executed by him in respect of Chhindwara, Khandwa, Mandsaur, Jhabua, Tikamgarh, Sihore, Jabalpur, Ambikapur and Jagdalpur. Admittedly, the respondent No.1 made a claim before the arbitrator for works executed by him in respect of Chhindwara, Khandwa, Mandsaur, Jhabua, Tikamgarh, Sihore, Jabalpur, Ambikapur and Jagdalpur. Out of the aforesaid places, four places, namely, Tikamgarh, Sagar, Sihore and Ambikapur are expressly mentioned in the agreements executed between the parties. In exercise of power conferred under clause 10 of the Agreement the Vice-Chancellor approved the same rates in respect of other works as that of the non-residential buildings for all divisions which was intimated to the respondent No.1 by Executive Engineer vide communication dated 12.4.1984. The Executive Engineer vide letter dated 24.12.1984, informed the respondent No.1 that the suitable remuneration shall be paid for the KVK building Jhabua and the payment shall be made as per the Scheme. Subsequently, with the approval of the Vice-Chancellor, the Executive Engineer at Jabalpur informed the Executive Engineer, Raipur for payment of construction of KVK building at Bilaspur. Thus, from perusal of the communications dated 24.12.1984 and 15.10.1985, it is evident that the respondent No.1 was asked to prepare and design buildings at Jhabua and Bilaspur and it was agreed that the payment shall be made to him as per the rate prescribed under the agreement. From perusal of the communication dated 12.5.1987, it is evident that the Executive Engineer, requested the respondent No.1 to prepare sketch planning for construction of college building at Khandwa and Mandsaur. From perusal of the communication dated 22.12.1983, it is evident that the respondent was asked to commence the work for Jabalpur, Sagar, Sihore and other centres also and the payments were also made in respect of the other centres. Thus, it is evident that subsequently, the respondent No.1 was asked to execute the works in respect of the other centres and it was agreed between the parties that the fee shall be payable in respect of the other centres as per the rate prescribed in the Agreement which was done with the approval of the Vice-Chancellor. 21. From perusal of paragraph 2 of the memorandum of Civil Revision No.139/1990 filed by the appellant against the order dated 5.1.1990 passed by the Additional District Judge, it is evident that the appellant had admitted execution of agreement dated 2.12.1983 and work orders were issued on 22.12.1983 for carrying out the work at Jabalpur, Sagar, Sihore and other centres as well. Similarly, paragraph 4 of the application under section 20 reveals that payments to respondent No.1 were made in respect of other stations as well. In case the agreement was not executed in respect of other stations, the appellant should not have made payments to the respondent No.1 and should have taken objection at the first available opportunity. However, neither such explanation is on record as to why payment was made to respondent No.1 in respect of other projects nor any explanation has been offered as to whay such objection was not taken. It is pertinent to mention here that clause 10 enable the parties to negotiate and agree upon different rates and different mode of payment for other works taking into consideration the nature of the work etc. In his statement before the arbitrator, in reply to question number 15, the respondent No.1 has stated that agreement was in respect of works throughout Madhya Pradesh. In reply to question number 20, it has been stated by respondent No.1 in duplicate copy he has carried out corrections himself, which were done in the original by the Executive Engineer. Thus, there is no admission on the part of the respondent No.1 that he has tampered with the original agreement. A Bench of this Court vide order dated 15.5.2003 had directed the appellant to file an affidavit of the concerned person in support of the allegations made by the appellant in the memorandum of the appeal, for the first time that there is tampering of the original documents. However, no such affidavit has been filed. From perusal of the award, it is graphically clear that before the arbitrator, the appellant has not raised any such contention that the respondent No.1 played fraud by inserting words “other stations” with ill-intention to seek the claims. The aforesaid contention has also not been made before the trial Court. The appellant has failed to file the affidavit as directed by a Bench of this Court vide order dated 15.5.2003. Therefore, the issue number (3) is answered in the negative. For the reasons assigned supra, the arbitrator has rightly invoked the clauses 3 and 10 of the agreement while passing the award and has rightly awarded the claims in respect of the works which were part of the agreements and thus not committed any misconduct. Therefore, the issue number (3) is answered in the negative. For the reasons assigned supra, the arbitrator has rightly invoked the clauses 3 and 10 of the agreement while passing the award and has rightly awarded the claims in respect of the works which were part of the agreements and thus not committed any misconduct. For the aforementioned reasons decisions relied on behalf of the appellant in Chandu Construction (supra), and Union of India v. A.L. Rallia Ram [ AIR 1963 SC 1685 ], and A. Rangaswamy (supra), are not applicable to the facts of the case. Accordingly, the issue number (4) is answered. 22. The proceeding before the arbitrator commenced on 29.11.1998. On that day, letter was sent by the counsel for the appellant that staff of the appellant has been assigned election duties and they will be busy till the counting of the votes and therefore, the proceeding be adjourned. The arbitrator thereupon adjourned the proceeding to 2.1.1999. On 2.1.1999, the counsel for the appellant by a letter dated 23.12.1998 informed the arbitrator that the appellant has moved an application before the trial Court for removal of the arbitrator and, therefore, the proceeding before the arbitrator should be deferred for a period of twenty-five days. Accordingly, the proceeding of the arbitration was adjourned till 5.1.1999. On 5.1.1999, the arbitrator received a telegram from the Executive Engineer of the appellant university stating that the proceeding before the arbitrator has been stayed by the Additional District Judge. Accordingly, the proceeding was adjourned. On 22.3.1999, the arbitrator received the order of the Court vacating the order of stay and dismissing the miscellaneous judicial case filed by the appellant. The Court had directed the arbitrator to pass an award within a period of four months from the date of receipt of copy of the order. Accordingly, the proceeding was taken up on 17.4.1999. 23. On 17.4.1999, the arbitrator received an intimation through telegram that High Court has stayed the proceeding before the arbitrator by an order dated 16.4.1999. The arbitrator thereupon adjourned the proceeding sine die on 16.10.1999, the counsel for the respondent No.1 produced certified copy of the order passed by the High Court dismissing the civil revision preferred by the appellant. Thereupon, the proceedings were adjourned to 25.10.1999. The arbitrator thereupon adjourned the proceeding sine die on 16.10.1999, the counsel for the respondent No.1 produced certified copy of the order passed by the High Court dismissing the civil revision preferred by the appellant. Thereupon, the proceedings were adjourned to 25.10.1999. On 25.10.1999, the Registrar of the appellant sent an application by registered post acknowledgement due praying for staying the proceeding for a period of one month, till the matter regarding appointment of arbitrator is adjudicated by the Supreme Court. Accordingly the case was adjourned to 19.11.1999. On 19.11.1999, the arbitrator received a memo from the Additional District Judge, directing him to submit the award within a period of four months. Thereafter the proceeding was adjourned to 12.12.1999. On the said day, the Executive Engineer of the appellant was present who filed an application for adjournment on the ground that special leave petition has been filed before the Supreme Court. Thereupon the arbitrator adjourned the case and directed that no further extension of time shall be granted to the appellant to file the reply. On 28.12.1999, the appellant sent the reply and vakalatnama through the counsel which was incomplete. The proceeding was adjourned to 8.1.2000. On 8.1.2000, the vakalatnama and reply were taken on record and the proceeding was adjourned for 29.1.2000. On 29.1.2000 the arbitrator directed that both the parties should separate the claims and replies for the claims which arose out of different agreements and the proceeding was adjourned to 21.2.2000. 24. On 21.2.2000, certain additional documents as well as applications for amendment of the replies were filed which were allowed and the proceeding was adjourned to 11.3.2000. On 11.3.2000, the additional documents were filed by the appellant and the proceeding was fixed on 5.7.2000. On 5.7.2000, the counsel for the appellant sent a telegram for deferring the proceeding till 22.7.2000 on the ground that the officer incharge of the appellant is on medical leave. It was further submitted in the application that counsel himself is unable to attend the proceeding because of his personal engagement. Thereupon, the arbitrator recorded the following observations : “It is a serious matter that the respondent has taken this Court for a “Joy Ride”. They have not taken the matter seriously and acted accordingly. It was further submitted in the application that counsel himself is unable to attend the proceeding because of his personal engagement. Thereupon, the arbitrator recorded the following observations : “It is a serious matter that the respondent has taken this Court for a “Joy Ride”. They have not taken the matter seriously and acted accordingly. On the basis of past record, I record over here that the respondents have spared no pains to delay the proceedings and stall them on some pretext which is totally against the letter and spirit of Arbitration Act, itself. As such they do not deserve extension of time.” Accordingly, in view of availability of limited time to conclude the proceeding of the arbitration, fixed by the Court, the proceeding was fixed on 15.7.2000 and the appellant was directed to remain present failing which the ex parte decision could be taken against him. It was directed that hearing which may commence on 15.7.2000, shall continue on subsequent dates also. 25. On 15.7.2000, the parties agreed to adduce evidence by way of affidavits. The next date of hearing was fixed for 22.7.2000. On 22.7.2000, the respondent No.1 adduced the evidence in the form of affidavit and the copies were supplied to appellant and the proceeding was fixed for 5.8.2000. On 5.8.2000, an application was sent by the appellant by Speed Post for taking the documents on record which was allowed with the consent of the parties and the case was fixed for 11.8.2000. On 11.8.2000, the issues were framed and the case was fixed for 26.8.2000. On 26.8.2000, a telegram was sent by the appellant stating that the appellant has filed an application under section 33 of the Act before the Additional District Judge about the jurisdiction of the arbitrator, about the agreement dated 2.12.1983. Thus, the proceeding was again adjourned to 27.8.2000. On 27.8.2000, the respondent No.1 was directed to submit estimate and extracts of bill duly signed by the competent authority. The parties agreed to adduce evidence finally by next date of hearing which was fixed on 9.9.2000. It was directed by the arbitrator that parties shall finally adduce evidence on 9.9.2000 and on 10.9.2000, the arguments shall be heard in the afternoon session. On 9.9.2000 the parties informed that the Court has extended the time for submission of the award till 30.9.2000. It was directed by the arbitrator that parties shall finally adduce evidence on 9.9.2000 and on 10.9.2000, the arguments shall be heard in the afternoon session. On 9.9.2000 the parties informed that the Court has extended the time for submission of the award till 30.9.2000. the next date of hearing was fixed on 16.9.2000 at guest house of the university. On 16.9.2000, the counsel for the appellant cross-examined the respondent No.1 and the proceeding was adjourned to 23.9.2000 for examination of witnesses of the appellant. On 23.9.2000, a letter sent by the Fax was received by the arbitrator by which a request was made that hearing may be deferred to after Navratri on the ground that witness namely, J.N. Pandey is ill and is not in a position to attend the proceeding and both the counsel for the appellant also expressed their inability to attend the proceeding. Thereupon the arbitrator recorded the following observations : “It is surprising that this extension of time was given at the instance of the respondents. Further in last two hearings it was made very clear that since the award is to be made by 30.9.2000 it is not possible to allow any postponement of hearing here after. This was categorically made clear to the respondents. Inspite of that they have not attended today.” 26. The arbitrator thereafter heard the arguments and closed the case for award. Thus, from scrutiny of the ordersheets of the proceeding before the arbitrator, it is evident that the appellant had adopted all possible tactics to linger on the proceeding before the arbitrator and on several occasions neither any officer of the appellant nor the counsel had appeared before the arbitrator. At the instance of the appellant, extension of time was granted several times. The appellant took the proceeding before the arbitrator very casually. Thus, it cannot be said that the arbitrator has not provided reasonable opportunity of hearing to the appellant. The trial Court has held that the appellant himself committed default for appearing before the arbitrator on 23.9.2000 without showing sufficient cause. Therefore, the action of the arbitrator in closing the right of the appellant to adduce evidence by taking into account the time limit fixed by the Court for delivery of the award, was justified. For the aforementioned reasons, it cannot be said that the arbitrator has not provided reasonable opportunity of hearing to the appellant. Therefore, the action of the arbitrator in closing the right of the appellant to adduce evidence by taking into account the time limit fixed by the Court for delivery of the award, was justified. For the aforementioned reasons, it cannot be said that the arbitrator has not provided reasonable opportunity of hearing to the appellant. Accordingly issue number 6 is answered in the affirmative and against the appellant. 27. From perusal of the record of arbitration proceeding, it is evident that the appellant had not filed any counter-claim. Therefore, the question of its consideration does not arise. The contention raised on behalf of the appellant regarding non-consideration of the counter-claim filed by the appellant before the arbitrator amounts to misconduct, is based on incorrect factual premises. Accordingly, issue number 7 is answered. 28. From perusal of the order passed by the Additional District Judge, it appears that the appellant had not raised any objection before the trial Court that the claims of the respondent No.1 are barred by limitation. The aforesaid objection appears to have been raised before this Court for the first time. The said objection was neither raised before the arbitrator nor before the trial Court. The question whether or not the claims of the respondent No.1 are barred by limitation is a mixed question of law and fact in the fact situation of the case, which cannot be permitted to be raised first time in these appeals in view of the law laid down by the Supreme Court in Hindustan Construction Company Ltd. (supra). Even otherwise the last running bills of the respondent No.1 were of the year 1987 and the application for appointment of an arbitrator was filed on 29.2.1988 in First Appeal No.247/2001 whereas the same was filed on 4.5.1989 in First Appeal 248/2001. Therefore, it appears that the claims of the respondent No.1 are not barred by limitation. The decision relied on by the appellant in the case of S. Rajan (supra), deals with the period of limitation for filing of an application under section 20 of the Act before the Court, therefore, the same is of no assistance to the appellant. Accordingly, the aforesaid issue is answered. 29. The decision relied on by the appellant in the case of S. Rajan (supra), deals with the period of limitation for filing of an application under section 20 of the Act before the Court, therefore, the same is of no assistance to the appellant. Accordingly, the aforesaid issue is answered. 29. From close scrutiny of the award passed by the arbitrator, it is apparent that the arbitrator has computed the fee payable to the respondent No.1 as per the terms and conditions of the agreement and as per the rates approved by the Vice-Chancellor. Therefore, the contention raised by the learned counsel for the appellant that the fee of the respondent No.1 has been computed contrary to the terms and conditions of the agreement, cannot be accepted and the same is hereby repelled. Accordingly, the issue number 9 is answered. 30. The agreements executed between the parties do not contain any express prohibition for grant of interest for ante lite period i.e. pre-reference period. The interest on the sum awarded by an arbitrator can be granted under the provisions of the agreement or under the Interest Act, 1978. The Supreme Court in the case of P. Radhakrishna Murthy (supra), while referring to Constitution Bench decision of the Supreme Court in Department of Irrigation v. Abhaduta Jena [ (1988)1 SCC 418 ], and Secretary Irrigation, Department, Government of Orissa and others v. G.C. Roy [ AIR 1992 SC 732 ], has held that where the agreement between the parties does not prohibit grant of interest, the arbitrator shall have power to grant interest. The award has been passed by the arbitrator after coming into force of Interest Act, 1978, therefore, the arbitrator had the authority to award interest for pre-reference period under the provisions of Interest Act, 1978. The rate of interest at 18% per annum has already been reduced to 10% by the Additional District Judge. The Supreme Court in the case of Krishn Bhagya Jala Nigam Ltd. v. G. Harischandra Reddy and Another [ (2007)2 SCC 720 ], while taking into account the economic reforms in the country in respect of an agreement pertaining to 1993 has reduced the rate of interest from 18% to 9%. The Supreme Court in the case of Krishn Bhagya Jala Nigam Ltd. v. G. Harischandra Reddy and Another [ (2007)2 SCC 720 ], while taking into account the economic reforms in the country in respect of an agreement pertaining to 1993 has reduced the rate of interest from 18% to 9%. Similarly in P. Radhakrishna Murti (supra), in respect of an agreement executed in the year 1988, the Supreme Court has upheld the order of the High Court reducing the rate of interest from 16.5% to 12%. Thus, the trial Court has already reduced the rate of interest from 18% to 10%. Accordingly, the issue numbers 10 and 11 are answered. 31. From perusal of the award, it is evident that no complicated issues of law and fact had arisen for consideration before the arbitrator. The objection raised by learned counsel for the appellant in this regard is vague as it has not specified as to which complicated questions of law and fact had arisen before the arbitrator which could not have been dealt with by him. Therefore, the contention raised by the appellant that the complicated issues of law and fact could not have been decided by the arbitrator, is repelled. Accordingly, the issue number (12) is answered. 32. So far as, the issue number (13) is concerned, from perusal of the objections filed by the appellant under section 30 of the Act as well as memorandum of the appeal, it is evident that the appellant has not raised any objection that the arbitrator has committed an error of law in granting claim in respect of the Indira Gandhi Krishi Viswavidyalaya in the impugned awards in view section 57(2)(c) of the Indira Gandhi Krishi Vishwavidyalaya Adhiniyam 1987. The aforesaid contention has been raised first time before this Court which cannot be entertained in view of the law laid down by the Supreme Court in Hindustan Construction Company Ltd. (supra). 33. In view of the preceding analysis, the appeals filed by the appellant and cross-objections preferred by the respondent No.1, are dismissed. However, in the facts of the case, the appellant shall bear the costs of the proceedings. ...........