Research › Search › Judgment

Bombay High Court · body

2015 DIGILAW 819 (BOM)

Punj Lloyd Ltd. v. Hindustan Petroleum Corporation Ltd.

2015-03-24

R.D.DHANUKA

body2015
JUDGMENT :. By this petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 (for short “the said Arbitration Act), the petitioner has impugned the arbitral award dated 26th November 2011 passed by the learned arbitrator rejecting the claims made by the petitioner and holding that the respondent was entitled for deduction from the running account bills of the petitioner in line with price reduction clause and accordingly rejected the claims of the petitioner in the sum of Rs.3,28,73,691/-. Some of the relevant facts for the purpose of deciding this petition are as under: 2. The petitioner was the original claimant in the arbitration petition whereas the respondent herein was the original respondent. Some time in the month of April 2005, the respondent no.1 invited bids for laying of pipeline and associated facilities for Pune Solapur Pipeline Project. Pursuant to the said bidding document, the petitioner submitted its offer dated 18th June 2005. On 28th October 2005, the respondent issued a Letter of Intent in favour of the petitioner. The letter of intent was followed by a Purchase Order/Detailed Letter of Acceptance (DLOA) dated 28th October 2005. The scope of work included (a) laying of pipeline of outside diameter 355.6 mm for 182 km (Spread I) and (b) laying of pipeline of outside diameter 323.9 mm for 161 km (Spread II) from the terminal of the respondent at Loni near Pune to the receipt station at Pakni near Solapur. The pipeline was to pass through the existing terminal of respondent at Hazarwadi. The envisaged work also included laying of Optical Fibre Cable (OFC) from Trombay to Loni. 3. The estimated contract value under the said Letter of Intent was Rs.88,60,38,279/-. Time of completion provided was 10 months upto pre-commissioning from the date of issue of Letter of Intent for pipeline of outside diameter 355.6 mm, including Terminal and SV station and 6 months up to pre-commissioning from availability of first pipe at Dumpsite for Pipeline of outside diameter 323.9 mm. Clause 9 of the said Letter of Intent provided for the price reduction in case of works getting delayed. M/s. Engineers India Ltd. was appointed as Engineer-in-Charge for the said project. 4. On 28th October 2005, the petitioner mobilized on the site and commenced the activity of ROW/site grading etc. Clause 9 of the said Letter of Intent provided for the price reduction in case of works getting delayed. M/s. Engineers India Ltd. was appointed as Engineer-in-Charge for the said project. 4. On 28th October 2005, the petitioner mobilized on the site and commenced the activity of ROW/site grading etc. for completion of works contemplated in Spread I. On 15th January 2006, the petitioner mobilized on the site and commenced the activity of ROW/site grading etc. for completion of works contemplated in Spread II. 5. By letter dated 27th July 2006, the respondent alleged delay and serious lapses on the part of the petitioner resulting out of the inexperience of site team. On 24th August 2006, the petitioner submitted a request for extension of time to M/s. Engineers India Ltd., the Engineer-in-Charge of the project (for short “the said EIL”) for extension of time for both Spread I and II on the grounds set out in the said letter. 6. On 8th September 2006, the said EIL sent a letter to the petitioner informing that any works completion getting extended or delayed beyond 29th October 2006 will be dealt with as per the provisions of the contract for price reduction. On 8th September 2006, the said EIL allowed the request of the petitioner for extension of time for both Spread I and II up to 28th October 2006 without any financial implication. On 20th October 2006, OISD report was submitted by the said EIL pointing out the balance scope of work to be completed by the petitioner. 7. On 21st October 2006, the petitioner submitted another request for extension of time in respect of Spread II up to 3rd January 2007. On 24th October 2006, the petitioner submitted a request for extension of time in respect of Spread I. On 26th October 2006, the said EIL rejected the request of the petitioner for further extension of time in respect of Spread I. By letter dated 28th October 2006, the said EIL granted extension of time in respect of Spread II up to 12th December 2006. It is the case of the petitioner that though the respondent had rejected the request of the petitioner for further extension of time in respect of Spread I, the petitioner completed the activities contemplated under clause 3 of the DLOA within the extended completion date of 28th October 2006. 8. It is the case of the petitioner that though the respondent had rejected the request of the petitioner for further extension of time in respect of Spread I, the petitioner completed the activities contemplated under clause 3 of the DLOA within the extended completion date of 28th October 2006. 8. By letter dated 26th October 2006, the said EIL informed the petitioner that the request of the petitioner for exclusion of CPL survey from definition of 'Time Schedule' was out of place and was not at all acceptable. The said EIL had refused to give time beyond 28th October 2006. On 29th October 2006, the said EIL informed the petitioner about the balance works list for Spread I related to pipeline and SV stations I to IV. On 30th October 2006, the said EIL enclosed comments of OISD and forwarded the same to the petitioner with a request to attend the balance points for making the pipeline and SV stations of Spread I ready for commissioning. 9. On 2nd November 2006, the said EIL addressed a letter to the petitioner expressing grave concern about the works of SV stations VI to IX not progressing at all since last one month and stating that the huge quantum of work was still pending. The said EIL enclosed all lists of activities to be completed by the petitioner. On 4th November 2006, the said EIL enclosed another list of balance work for pipeline laying activities to the petitioner as on 28th October 2006. On 4th November 2006, the said EIL enclosed list of balance work at IP and RT stations as on 28th October 2006 to the petitioner. On 12th November 2006, the said EIL addressed a letter to the petitioner pointing out that no spread in-charge was available for Spread I from the petitioner and also enclosed a list of balance work related to the pipeline for Spread I. On 6th November 2006, Test Report for SV-II was prepared. On 3rd December 2006, Test Report for SV-VII and SV-VIII was prepared. On 5th December 2006, the said EIL informed the petitioner about the list of balance activities of pipeline for Spread I. On 6th December 2006, OISD Report was submitted to complete certain works. On 12th December 2006, Test Report for SV-IX was prepared. 10. On 3rd December 2006, Test Report for SV-VII and SV-VIII was prepared. On 5th December 2006, the said EIL informed the petitioner about the list of balance activities of pipeline for Spread I. On 6th December 2006, OISD Report was submitted to complete certain works. On 12th December 2006, Test Report for SV-IX was prepared. 10. It is the case of the petitioner that on 2nd November 2006, the respondent commissioned the pipeline in Spread I i.e. just 4 days after the petitioner had completed the activities falling within its scope in respect of Spread I. The petitioner placed reliance on the Annual Report of the Ministry of Petroleum and Natural Gas in support of this contention. On or about 30th November 2006, the petitioner submitted RA Bill No.12A for Rs.6,28,47,493/- to the respondent. 11. By a letter dated 2nd January 2007, the said EIL informed the petitioner that the progress of job front was sluggish and far from meeting target dates. On 29th January 2007, format IV listing out pending jobs for Spread II and Spread I was submitted. 12. On 6th February 2007, the said EIL addressed a letter to the petitioner expressing its concern regarding liquidation of check list and completion of balance works on pipeline, SV stations, IP/RT stations regarding Pune Solapur pipeline for Spreads I and II. On 6th February 2007, the said EIL enclosed Handing Over Format IV for Spread II by the respondent. 13. On 23rd February 2007, the petitioner forwarded Format III to the said EIL and informed that the same was ready for pre-commissioning certificate for OFC work. It is the case of the respondent that on 27th February, 2007, Format IV for Spread I showing that the work was incomplete. 14. It is the case of the petitioner that on 7th March 2007, the respondent no.1 under RA Bill No.12A paid only Rs.4,97,41,325/- to the petitioner and deducted Rs.1,06,18,358/-. According to the petitioner, the said amount withheld by the respondent was shown as liquidated damages even though there was no provision in the DLOA for such liquidated damages. 15. By letter dated 12th March 2007, the said EIL addressed a letter to the respondent enclosing Format IV for Spread I along with details of minor points to be attended by the petitioner. 15. By letter dated 12th March 2007, the said EIL addressed a letter to the respondent enclosing Format IV for Spread I along with details of minor points to be attended by the petitioner. On 16th March, 2007, the respondent addressed a letter to the petitioner pointing out that the petitioner had assured on 15th February 2007 for completing all balance activities but had not kept the promise. The respondent pointed out that it was not possible to retain the services of the EIL nor the officer of the respondent indefinitely. 16. On 23rd March 2007, the petitioner submitted liquidated check list for pipeline Spread I to the said EIL. On 24th March 2007, the said EIL addressed a letter to the respondent enclosing Format IV for Spread I (OFC work) along with details of minor points to be attended by the petitioner. 17. On 27th March 2007, the said EIL addressed a letter to the respondent to keep bill amount on hold due to non completion of all/total work for Spread I against each item. On 27th March 2007, the said EIL addressed another letter to the respondent recommending to keep bill amount on hold due to non completion of all/total work for Spread I and also levy price reduction on account of delay on the part of the petitioner. 18. On 5th April 2007, the petitioner objected to the deduction made by the respondent and requested to release the amount so withheld against the liquidated damages. 19. On 9th April, 2007, the petitioner enclosed PCP Commissioning Report for Spread II to the said EIL. By letter dated 14th April 2007, the respondent informed the petitioner that since the said EIL had negated the request of the petitioner for time extension for Spread I sought by the petitioner vide letter dated 24th October 2006, the respondent had levied price reduction in line with clause 9 of the DLOA. It is the case of the petitioner that in addition to the amount withheld by the respondent from RA Bill No.12 A of the petitioner, the respondent had also withheld certain amounts from pre-final bills dated 12th January 2007 and 10th March 2007 of the petitioner for Spreads I and II respectively. 20. It is the case of the petitioner that in addition to the amount withheld by the respondent from RA Bill No.12 A of the petitioner, the respondent had also withheld certain amounts from pre-final bills dated 12th January 2007 and 10th March 2007 of the petitioner for Spreads I and II respectively. 20. By an e mail dated 17th April 2007, the said EIL forwarded a draft copy of the recommendations dated 13th April 2007 to the respondent against the request letter submitted by the petitioner for time extension for Spreads I and II. On 27th April 2007, the petitioner gave a reply to the letter dated 27th April 2007 of the said EIL. On 28th April 2007, the respondent addressed a letter to the said EIL pointing out the reason for not sending the approved draft to the petitioner. 21. On 3rd May 2007, the said EIL addressed a letter to the respondent pointing out that activities for CPL and interference survey for Spread I would be completed by mid April 2007 and balance check list point would be completed by 30th June 2007 and for Spread II would be completed by mid April 2007 and balance check list point would be completed by 30th June 2007. In the said letter, the said EIL alleged that it can be seen that all the works up to pre-commissioning except for minor check list points for Spreads I and II work were completed with time extension granted to the petitioner. 22. On 15th May 2007, a meeting between the petitioner, the respondent and the said EIL took place. In the Minutes of meeting, it was recorded that CPL survey for Spread II had been completed on 10th May 2007; OFC reconciliation would be completed on 17th May 2007. Warranty Certificate for DG sets would be submitted by 21st May 2007. Tree cutting in ROU would be completed by 31st May 2007 etc. 23. On 21st May 2007, the said EIL informed the petitioner that the petitioner's claim of extra work or cost of rework for Bhima river was not tenable. 24. On 11th July 2007, a meeting came to be held between the parties along with the said EIL. In the Minutes of meeting, it was confirmed that the petitioner would complete the job for ROU marker on 31st August 2007. 24. On 11th July 2007, a meeting came to be held between the parties along with the said EIL. In the Minutes of meeting, it was confirmed that the petitioner would complete the job for ROU marker on 31st August 2007. All rectification job including obtaining NOC to be completed latest by 31st August 2007. On 27th July 2007, Format III for Spreads I and II came to be submitted. On 20th August 2007, the said EIL submitted a completion certificate. On 29th August 2007, the respondent addressed a letter to the said EIL pointing out that the extension of time completion could only be in accordance with clause 3.1 of the Document No.6545-04/41-TS-02. The respondent further pointed out that the said EIL had issued a completion certificate mentioning the date of completion as 30th June 2007. However, the Cathodic Protection (CP) system had not been handed over till date as the activities were still in progress. Format IV had not been signed by the respondent. The respondent pointed out that major job of coating was in part of the scope of the petitioner. Completion date could only be established after work was completed. The respondent also pointed out that as built document pertaining to CP had not been submitted. CPL survey reports had not been authenticated by the said EIL. The respondent returned the original completion certificate to the said EIL for correction. 25. In the month of August 2007, the petitioner submitted its final bill for Rs.6,58,07,064/- to the said EIL. The said amount was claimed in addition to the amounts withheld by the respondent no.1 from RA Bill No.12A of the petitioner and requested the respondent to pay a total amount of Rs.9,68,19,731/-. 26. On 20th September 2007, the respondent addressed a letter to the said EIL alleging that the statement of the said EIL that activities covered under clause 3.1.1 had been completed for Spread II was absolutely wrong, baseless, far from truth and contradictory. The respondent alleged that the completion date mentioned by the said EIL was out of extraneous reasons without having any relation to the contractual provisions. The dates for completion could only be established by joint inspection of the said EIL and the petitioner or the dates of handing over of any system. The respondent alleged that the completion date mentioned by the said EIL was out of extraneous reasons without having any relation to the contractual provisions. The dates for completion could only be established by joint inspection of the said EIL and the petitioner or the dates of handing over of any system. In the said letter, the respondent further stated that OISD had categorically mentioned that the activities like installation of warning board, direction markers, cathodic protection system, communication which were forming part of clause 3.1.1 had not been completed as on the date of inspection of OISD. The respondent also contended that the said EIL could not point out to the respondent any clause in the contract which provides for post pre-commissioning activity. It was contended that CP during pre-commissioning stage certainly means permanent CP and not limited to temporary CP. 27. It was stated that the view of the said EIL of job completion by 12th December 2006 was not based on any material facts and contractual terms and conditions. The respondent requested the said EIL to include some of the works which were beyond pre-commissioning were still not yet completed. The respondent pointed out that the said EIL had arbitrarily fixed the date of 30th June 2007. The said EIL did not reply to the letters of the respondent dated 21st July 2007, 31st July 2007 and 21st August 2007. The respondent made it clear that CP which was one of most important safety feature of pipeline and current drainage/ coating damages could not be treated as minor check list points and thus the completion certificate was incorrect. The respondent returned the said completion certificate to the said EIL since the same was not in accordance with the terms and conditions according to the respondent. 28. On 10th October 2007, there was a meeting held. In the Minutes of meeting, the petitioner committed that CP related activities would be completed by 31st October 2007. The petitioner requested that the painting job for warning board be deleted from its scope. The petitioner agreed to provide identification marker for SV I, II, III, VII and IX by 25th October 2007 and fencing at SV IV, V and VIII by 30th November 2007. 29. The petitioner requested that the painting job for warning board be deleted from its scope. The petitioner agreed to provide identification marker for SV I, II, III, VII and IX by 25th October 2007 and fencing at SV IV, V and VIII by 30th November 2007. 29. On 1st December 2007, the respondent paid a sum of Rs.5,13,51,759/- under the final bill to the petitioner and made various deductions which were shown as ‘Temporary Hold’ and ‘Permanent Hold.’ 30. On 7th December 2007, the petitioner while acknowledging the receipt of the amount of Rs.5,13,51,759/- objected to various deductions made by the respondent. The petitioner requested the respondent to release all the outstanding payment without any further delay. The petitioner also furnished a detailed break up of the withheld amount. 31. On 8th December 2007, the said EIL forwarded the final bill and revised completion certificate to the respondent. The said EIL, however, informed the respondent that the said EIL had not issued any completion certificate from its end. According to the said revised completion certificate, the activities pertaining to CPL survey attending to current drainage at SV stations were completed on 9th October 2007. 32. It is the case of the petitioner that in response to the request of the petitioner, the said EIL issued a copy of the completion certificate to the petitioner on 1st March 2008. In the said letter, the said EIL recorded that it had sent to the respondent the said certificate along with final bill of the petitioner. According to the petitioner, the said completion certificate dated 1st March 2008 issued by the said EIL would indicate that the petitioner had completed the activities in terms of clause 3 of the DLOA in respect of both Spreads I and II within the respective extended completion dates. 33. On 15th September 2008, the petitioner issued to the respondent a notice under Article 14 of the General Conditions of Contract to commence arbitration. On 14th October 2008, the respondent appointed Shri. R. Krishnan, a retired officer of the respondent as the sole arbitrator. 34. Pursuant to the directions issued by the learned arbitrator, the petitioner filed a statement of claim, inter alia, praying for recovery of Rs.3,28,73,691/- alleged to have been wrongfully recovered by the respondent though the petitioner had alleged to have been completed the activities contemplated under clause 3 of the DLOA. 34. Pursuant to the directions issued by the learned arbitrator, the petitioner filed a statement of claim, inter alia, praying for recovery of Rs.3,28,73,691/- alleged to have been wrongfully recovered by the respondent though the petitioner had alleged to have been completed the activities contemplated under clause 3 of the DLOA. The petitioner had also applied for recovery of extra amount alleged to have been incurred while executing the work of Bhima river crossing and also a sum of Rs.1,13,56,350/- as extra for carrying out re-routing of pipeline alignment pursuant to the alleged instructions by the said EIL/the respondent. The petitioner demanded interest @18% p.a. The said arbitrator Shri. R. Krishnan appointed by the respondent, however, withdrew from the office of the arbitrator. Later on, Shri S.V. Narvekar was appointed by the respondent as the sole arbitrator in the arbitration proceedings from the stage of arguments. 35. By an arbitral award dated 26th November 2011, the learned arbitrator held that the respondent was entitled for deductions from running account bills of the petitioner in line with price reduction clause amounting to Rs.3,28,73,691/- and accordingly, rejected the claim for recovery made by the petitioner and for interest. The learned arbitrator directed both the parties to bear the cost of arbitration equally. The said arbitral award has been impugned by the petitioner in this petition under Section 34 of the Arbitration and Conciliation Act, 1996. 36. Mr. Setalwad, learned senior counsel for the petitioner submits that the time for completion of works was provided as per clause 3 of DLOA. The extended dates for completion of activities in Spreads I and II were 28th October 2006 and 12th December 2006 respectively. The petitioner was obliged to complete pre-commissioning activities within the said extended completion dates. The activities forming part of 'Pre-commissioning' were enumerated in the 'Technical Specifications for Pre-commissioning and Commissioning.’ He submits that all pre-commissioning activities set out in the specifications were completed within the extended completion dates and in support of this contention, he placed reliance on the completion certificate issued by the said EIL. He submits that the said completion certificate issued by the said EIL was final and binding on the parties and could not be questioned about its correctness by the respondent. 37. He submits that the said completion certificate issued by the said EIL was final and binding on the parties and could not be questioned about its correctness by the respondent. 37. Learned senior counsel submits that a final certificate issued by an Engineer/Architect is final and binding on the parties and cannot be challenged except on the ground of fraud, collusion or misconduct and except in the cases where the same had been issued at a time when there were disputes formulated between the parties or referred to arbitration. He submits that finding of the learned arbitrator that such completion certificate issued by the said EIL was not binding on the respondent is contrary to the law. In support of this submission, learned senior counsel placed reliance on the judgment of this Court in the case of Motilal Tajsi & Co. Vs. Ramchandra Gajanan Kherodkar, reported in AIR (29) 1942 Bombay 334 and in particular the following portions thereof which read thus :- “Therefore, even assuming that Clause (4) of the contract amounts to an arbitration clause, it would not ipso facto oust the jurisdiction of the architects to give a certificate under Clause (36) of the conditions of the contract unless Mr. Somjee satisfies me that there were disputes between the parties which were formulated and which were referred to the architects as arbitrators. If there were no disputes or if they were not formulated or if they were not referred to the architects, the jurisdiction of the architects to give a certificate continued unimpaired, and if they did give a certificate, it would be final and binding upon the parties. As I have already stated, in my opinion it was not the intention of the parties to constitute the architects as arbitrators, and any difficulty that one may feel in construing Clause (4) of the contract because of the words "the decision of the architects shall be final and binding on both parties and may be made a rule of the Court" is removed by consideration of the decision in (1909) Hudson's Building Contracts, Vol. II, (4th Edn.), page 411. The clause there which the Court considered was if anything much more favourable to the view advocated by Mr. Somjee than the clause here. II, (4th Edn.), page 411. The clause there which the Court considered was if anything much more favourable to the view advocated by Mr. Somjee than the clause here. The architect was described as the "judge", and with regard to the final certificate he was to issue, it was provided that it was to have the force and effect of an award and may be made a rule of His Majesty's High Court of Justice, or any division thereof, at the instance of either party hereto. In his judgment Lord Justice Buckley says (page 418) :- “It is quite true that the architect is to be an impartial person, no doubt; he is to determine the construction of the contract, and he must not "seek to construe it in favour of the corporation as distinguished from in favour of the contractors; he must act fairly as between the parties. Therefore he owes a duty to the contractors as well as a duty to the corporation, but he, I think, does not hold any judicial duty to one or to the other. Then if you add to that the last words of Section 33, all that you find there is that his certificate as to the work done, the money to be paid and so on, 'shall have the force and effect of an award, and may be made a rule of His Majesty's High Court of Justice, or any division thereof, at the instance of either party hereto'. I do not think that adds anything to it. It is not that this certificate is an award, but it is to be treated as something which it is not, and it is treated as if it were an award. That is the conclusion I come to upon the construction of that clause”. My conclusion on the construction of Clause (4) of the contract is the same. The mere fact that Clause (4) provides for the decision of the architects being made a rule of the Court does not alter their capacity in giving their decision which is not judicial but administrative, and in giving their decision under Clause (4) they do not act as arbitrators at all. If their decision is not an award, the mere fact that the parties provide that it may be made a rule of the Court would not any more make it an award. If their decision is not an award, the mere fact that the parties provide that it may be made a rule of the Court would not any more make it an award. Assuming I am wrong in my construction of Clause (4) and that Clause (4) is an arbitration clause, the next question that arises is whether there were any disputes between the parties before the issuing of the certificate which were referred to the arbitration of the architects within the meaning of Clause (4). Mr. Somjee has tendered four letters which his client wrote to the architects. In the first letter of June 7, 1938, he drew the attention of the architects to certain defects in the sanitary works and he called upon the architects to arrange to remove the present defective fittings and to replace them, with new ones. It is to be noted that in this letter the defendant wanted the architects to act administratively and do certain administrative acts. The decision of the architects was not sought on any dispute between the parties. The next letter of August 11, 1938, makes a grievance of various works which were left incomplete, and these incomplete works are set out seriatim. Here again the request made to the architects is that they should ask the contractors to complete the incomplete works. On January 14, 1939, a reminder was sent, and the architects were again called upon to request the contractors to attend to the defective and incomplete works. A final reminder was sent on June 26, 1939, and there again the grievance was that the architects had not yet got the contractors to complete the incomplete portions of the work and they were further asked to get the contractors to settle the claim of one Thakorlal & Co. in respect of some plumbing and sanitary works. Therefore it would be noted that in all these four letters the defendant was seeking the assistance of the architects to get the contractors to do certain things which he had the power to do under the contract and was making a complaint about various incomplete works which, according to him, the plaintiffs were bound to complete under the terms of the contract. But nowhere do these letters even suggest that there were any disputes between the defendant and the plaintiffs --let alone formulating these disputes, and I fail to understand how these letters can be possibly read as calling upon the architects to take upon themselves the burden of arbitration under Clause (4) of the contract and resolve the disputes between the parties. I therefore hold that assuming Clause (4) of the contract is to be read as an arbitration clause, on the evidence before me there were no formulated disputes between the parties which were referred to arbitration under Clause (4) and, therefore, the jurisdiction of the architects to issue a final certificate under Clause (36) of the conditions of the contract was not in any way ousted.” 38. Learned senior counsel submits that it was not the case of the respondent before the learned arbitrator that the completion certificate was procured by the petitioner either by fraud, collusion or misconduct. The completion certificate issued by the said EIL was binding on the respondent and could not have been ignored by the learned arbitrator. The impugned award is thus contrary to law and also contrary to the terms of the contract. 39. Learned senior counsel placed reliance on the judgment of the Court of Appeal in the case of Arenson Vs. Arenson and Anr., reported in (1973) 2 All E R 235 and would submit that none of the parties could impeach such certificate issued by the said EIL. Under clause 5.1 of the General Conditions of Contract, the said EIL who was authorised to issue such completion certificate and who was appointed as the Engineer-in-Charge had rightly issued such certificate. The respondent could not ignore such completion certificate issued by the said EIL who was appointed by the respondent itself on such flimsy ground. 40. Learned senior counsel submits that the report of the said EIL that the balance works and post commissioning works were not within the scope of the petitioner could not be faulted with by the learned arbitrator. The said opinion of the said EIL was binding on the respondent. The said EIL had also certified that the petitioner had completed all pre-commissioning works. The learned arbitrator while rejecting the said report certified by the said EIL had relied upon the alleged established practice without there being any evidence on record. The said opinion of the said EIL was binding on the respondent. The said EIL had also certified that the petitioner had completed all pre-commissioning works. The learned arbitrator while rejecting the said report certified by the said EIL had relied upon the alleged established practice without there being any evidence on record. The respondent did not lead any oral evidence to prove any established practice before the learned arbitrator. He submits that the established practice is a matter of fact and has to be pleaded and proved. The petitioner had already completed the activity of CP before commissioning. The respondent had not made any deductions for OFC laying works. 41. Learned senior counsel submits that in any event, since no loss was suffered by the respondent even if there was a delay in completion of work, no amount towards liquidated damages could have been recovered from the running account bills of the petitioner without the respondent having proved such loss. In support of this submission, he placed reliance on the judgment of this Court in the case of Smt. Panna Sunit Khatau and Ors. Vs. Dilip Dharmsey Khatau delivered on 12th April 2013 in Arbitration Petition No.4 of 1986 and in particular paragraphs 2 and 27 to 30 thereof which read thus :- “2. Some of the relevant facts for the purposes of deciding this petition are as under: Mr. Sunit Chandrakant Khatau, Kiran Chandrakant Khatau, Dilip Khatau, Abhay Khatau L. Khatau and Kishore Khatau were co-owners of the immovable property known as Khatau Bungalow, Manav Mandir Road, Mumbai 400 006. Under the family arrangement dated 10th August, 1983, the company known as Khatau Company Limited and certain other concerns were allotted to petitioners' group. In respect of the immovable property known as Khatau Bungalow, the Memorandum of Understanding dated 12th July, 1984 (for short "MOU") was executed between Kishore Dharamsey Khatau, Dilip Dharamsey Khatau and Abhay Laxmidas Khatau (hereinafter referred to as "DMK GROUP" and Mr. Sunit Chandrakant Khatau and Kiran Chandrakant Khatau (hereinafter referred to as "CMK GROUP"). The Petitioners in this petition would be referred to as CMK group whereas respondents would be referred to as DMK group. The main object of the said MOU was to implement the desire of the parties i.e. to divide and/or partition of the immovable property by metes and bounds. The Petitioners in this petition would be referred to as CMK group whereas respondents would be referred to as DMK group. The main object of the said MOU was to implement the desire of the parties i.e. to divide and/or partition of the immovable property by metes and bounds. It was agreed that the DMK group should have physical possession and ownership of two thirds of the said immoveable property and CMK group shall have physical possession and ownership of the remaining one-third of the said immoveable property. It was further agreed that in order to effectuate said desire and intention of the parties, two third of the total FSI in respect of the immovable property would be available to and for the beneficial enjoyment of the said two third portion given to DMK group and the one-third of the total FSI would be available to and for the beneficial enjoyment of one third coming to the share of the CMK group. Under clause 3 of the said MOU it was agreed that on the CMK group, their family members and personal servants and others handing over vacant possession to the DMK group of the portion of the said immovable property coming to the share of the DMK group, the DMK group shall pay to the CMK group a sum quantified at Rs. 55,00,000/- (Rupees Fifty Five Lacs) in consideration of the CMK group agreeing to take the portion of the immoveable property coming to their share. Clause 4 of the said MOU provided for the respective FSI for the beneficial enjoyment of the respective portion of the CMK and DMK group. Clause 5 of the said MOU provided that for implementing the said MOU regarding the division of FSI in manner specified in the immediately preceding clause, the party concerned shall demolish any structures or any part or parts thereof on the portion of the said immoveable property coming to such party so that the other party may have the enjoyment and beneficial use of that portion of the FSI allocable to such party's share or portion of the said immoveable property. Clause 6 provided that the DMK group shall ensure that they and the respective members of their families and personal servants are removed from that portion of the said immovable property, shaded yellow on the said plan, within six months from the date of the said MOU and procure in favour of the CMK group a proper performance Guarantee of authorized family members and guaranteeing the payment of Rs. 5,000/- per day. There was similar obligation cast upon CMK group. Clause 6 and 7 of the said MOU which are relevant for the purpose of deciding this petition are extracted below: “6. DMK Group shall ensure that they and the respective members of their families and personal servants are removed from that portion of the said immovable property/shaded yellow on the said plan within six months from the date hereof. The cost of removing all their family members and personal servants shall be borne wholly by the DMK Group and the responsibility will be of the DMK group. The DMK Group shall procure in favour of the CMK group a proper performance Guarantee of Hiten A. Khatau, Mahendra K. Khatau and Anil K. Khatau guaranteeing the performance by the DMK Group of the condition of this clause and guaranteeing the payment of Rs. 5,000/- (Rupees Five Thousand) per day in the event of any willful default or delay on the part of the DMK Group in performance of the said obligation. 7. CMK Group shall ensure that they and the respective members of their families and personal servants are removed from that portion of the property shaded green on the said plan within six months from the date hereof. The cost of removing all their family members and personal servants shall be borne wholly by the CMK Group and the responsibility will be of the CMK Group. The CMK Group shall procure in favour of the DMK Group a proper Performance Guarantee of Shri. Chandrakant M. Khatau guaranteeing the performance by the CMK Group of the condition of this clause and guaranteeing the payment of Rs. 10,000/- (Rupees ten thousand) per day in the event of any willful default or delay on the part of the CMK Group in performance of the said obligation.” 27. 10,000/- (Rupees ten thousand) per day in the event of any willful default or delay on the part of the CMK Group in performance of the said obligation.” 27. In my view on reading this clause as a whole with other obligations of parties and considering the intention and object of the executing of MOU, it reveals that the said clauses provided for payment of Rs. 10,000/- per day is in the nature of penalty. The clause does not indicate that both the parties had agreed that the said amount was correct, genuine pre estimate of damages. The Supreme Court in the case of ONGC Vs. Saw Pipes (supra) has considered a clause by which both the parties had agreed that the purchaser would recover from the contractor as agreed liquidated damages and it was not by way of penalty sum equivalent to 1% of the contract price of the whole unit per week for such delay or part thereof. It was agreed that the said sum was genuine pre-estimate of damages duly agreed by the parties. The Supreme Court construed such clause and held that it would be difficult to prove the exact loss or damage each party had suffered because of breach thereof and in such situation if the parties had pre estimated such loss after clear understanding, it would be unjustified to arrive at the conclusion that the party who had committed breach of the contract is not liable to pay compensation and it would be against the specific provisions of section 73 and 74 of the Indian Contract Act. The Supreme Court held that in the said clause, it was specifically mentioned that it was agreed genuine pre estimate of the damages duly agreed by the parties. It was also mentioned that the liquidated damages was not by way of penalty. With these facts under consideration, the Supreme Court held that there was no reason for the tribunal not to rely upon the clear and unambiguous terms of the agreement stipulating pre estimated damages caused for delay in supply of goods. The Supreme Court also considered that while extending the time for delivery of the goods, the respondent was informed that it would be required to pay stipulated damages. The Supreme Court also considered that while extending the time for delivery of the goods, the respondent was informed that it would be required to pay stipulated damages. In paragraph 68 of the said judgment the Supreme Court it is held that the terms of the contract are required to be taken into consideration before arriving at the conclusion whether the party claiming damages is entitled to the same. If the terms are clear and unambiguous stipulating liquidated damages, unless it is held that such estimate of damages/compensation is unreasonable, or is by way of penalty, party who has committed the breach is required to pay such compensation and that is what is provided under section 73 of the Contract Act. The Supreme Court also held in some cases that it would be impossible for the court to assess the compensation arising from breach and if the compensation contemplated is not by way of penalty or unreasonable, the court can award the same if it is genuine pre-estimate by the parties as the measure of reasonable compensation. The Supreme Court held that the Court is competent to award reasonable compensation in the case of breach even if no actual damage is proved to have been suffered in consequence of the breach of the contract. 28. The Division Bench of this court in the case of Board of Trustees of Port Vs. Pioneer (supra) has interpreted the judgment of the Supreme Court in the case of ONGC Vs. Saw Pipes by holding that the observations made by the Supreme Court will have to be read in the context of the facts of that case. The Division Bench held that the view of the Supreme Court that there was agreed genuine pre-estimate of damage duly agreed by the parties and there was no need to prove then was based on the relevant terms of that contract which stated that in the case of breach of contract purchaser can recover from the contractor as agreed liquidated damages and not by way of penalty sum equivalent to 1% of the contract price or part thereof on which the contractor had failed to deliver within the fixed period. In my view the clause considered by the Supreme Court in the case of ONGC Vs. Saw Pipes is totally different. In my view the clause considered by the Supreme Court in the case of ONGC Vs. Saw Pipes is totally different. It is the case of the respondent themselves that it is not possible to prove the loss suffered by the respondent, if any, in view of the petitioner not handing over the possession of their one third portion to the respondent. Even if the finding of willful default was correct, in my view, the learned arbitrator at the most could have awarded reasonable compensation and not the entire amount as calculated based on clause which is in the nature of penalty. None of the parties led any evidence before the learned arbitrator to prove as to what amount should be reasonable for grant of compensation. On perusal of the impugned award, it is clear that the learned arbitrator has awarded the entire amount of Rs. 10,000/- per day for the alleged willful default not only from 27th January, 1985 to 4th December, 1985 but also from 5th December, 1985 till the petitioners hand over possession to the respondent vacant possession. 29. In my view, award of Rs. 10,000/- per day as claimed which is in nature of penalty shows patent illegality on the face of award. Though the impugned award is a non speaking award, perusal of relief granted clearly reveals that the learned arbitrator had granted the entire relief as claimed by awarding Rs. 10,000/- per day by way of compensation. In my view grant of such relief by way of compensation is contrary to the judgment of the Supreme Court in the case of Fatechand Vs. Balkishandas (supra) AIR 1963 SC 1405 , Maulabux Vs. Union of India (supra), ONGC Vs. Saw Pipes, judgment of Single Judge of this Court in the case of O.N.G.C. Vs. Country Tabular and Jagson Vs. O.N.G.C. (supra) and judgment of Division Bench in the case of Board of Trustees of Part Vs. Pioneer Engineer. 30. Balkishandas (supra) AIR 1963 SC 1405 , Maulabux Vs. Union of India (supra), ONGC Vs. Saw Pipes, judgment of Single Judge of this Court in the case of O.N.G.C. Vs. Country Tabular and Jagson Vs. O.N.G.C. (supra) and judgment of Division Bench in the case of Board of Trustees of Part Vs. Pioneer Engineer. 30. In my view as the error committed by the learned arbitrator in awarding the compensation at the rates as claimed though the said clause was in the nature of penalty, is error apparent on the face of the award, the arbitrator has committed legal misconduct in making the award, the court is empowered to interfere with the said award under section 30 and 33 of the Arbitration Act, 1940 even in the case of non speaking award. Reliance thus placed by Mr. Rustomjee on nine judgments on the scope of section 30 read with section 33 of the Arbitration Act, 1940 is of no assistance to the respondents.” 42. Learned senior counsel submits that since the respondent had not issued any completion certificate, the petitioner had applied for such completion certificate to the said EIL. The said EIL had accordingly issued such completion certificate which is binding on both the parties. 43. In so far as the claim no. II is concerned, the learned senior counsel submits that the petitioner had carried out extra work while carrying out the work of Bhima river crossing. He submits that clause 2.13 of the Job Specific Requirements provided specifications for laying pipelines in the river crossing. The said clause stipulated that 'Pipelines in all river crossings were intended to be installed by open cut method.' However, the petitioner had realised that the depth of water, while working across the river, was possible only when a flow of water had been stopped or sufficiently reduced. This was because the pipelines had to be buried well below the maximum scour depth. He submits that in view of unforeseen problems encountered by the petitioner, the petitioner had to incur additional cost for mobilization and demobilization repeatedly to complete the work and thus the petitioner was entitled to recover a sum of Rs.2,00,80,699/- from the respondent. The learned arbitrator, however, has rejected the said claim without any basis and without any reasons. He submits that the findings rendered by the learned arbitrator are erroneous and are also contrary to the law. 44. The learned arbitrator, however, has rejected the said claim without any basis and without any reasons. He submits that the findings rendered by the learned arbitrator are erroneous and are also contrary to the law. 44. In so far as the claim no. III is concerned, learned senior counsel submits that in view of the instructions given by the respondent and the said EIL while executing the project, the petitioner had to carry out re-routing of pipeline alignment from KP 170 to KP 176 and on account of such instructions, the petitioner had to divert its resources which resulted in the petitioner incurring an additional cost and seeking an extension of time from the respondent. The new route/re-route was longer resulting in additional time and cost. He submits that the respondent had acknowledged the problems faced by the petitioner on account of re-routing while considering the request of the petitioner for extension of time. Reliance is placed on Section 70 of the Indian Contract Act 1872 and it is submitted that the learned arbitrator ought to have allowed the said claim on the principles of Quantum Meriut. In support of this submission, learned senior counsel placed reliance on the judgment of the Supreme Court in the case of Food Corporation of India & Ors. Vs. Vikas Majdoor Kamdar Sahkari Mandli Ltd., reported in 2007 (13) SCALE 126 and in particular paragraph 13 thereof which read thus : “13. If a party to a contract has done additional construction for another not intending to do it gratuitously and such other has obtained benefit, the former is entitled to compensation for the additional work not covered by the contract. If an oral agreement is pleaded, which is not proved, he will be entitled to compensation under Section 70. Payment under this section can also be claimed for work done beyond the terms of the contract, when the benefit of the work has been availed of by the defendant.” 45. Mr. Siodia, learned counsel for the respondent, on the other hand, invited my attention to the relevant correspondence exchanged between the parties as also between the said EIL and also invited my attention to the relevant provisions of the Contract to point out that the scope of work of the Contract awarded to the petitioner. Mr. Siodia, learned counsel for the respondent, on the other hand, invited my attention to the relevant correspondence exchanged between the parties as also between the said EIL and also invited my attention to the relevant provisions of the Contract to point out that the scope of work of the Contract awarded to the petitioner. Learned counsel submits that the work awarded to the petitioner included laying of OFC from Trombay to Loni and also the work of CP. 46. Learned counsel for the respondent placed reliance on clause 2.1 of the General Terms and Conditions of the Works Contract and would submit that the said provision provides for scope of work up to pre-commissioning stage. Learned counsel submits that clause 10 of the Notice Inviting Tender which provided for liquidated damages was subsequently replaced by another clause under which the respondent was permitted for price reduction by ½% (half percent) per week of delay or part thereof subject to ceiling of 5% (five percent) of the contract value of all the works in case of delay in completion of works due to reasons not attributable to the respondent. Learned counsel submits that thus the reduction made by the respondent from running account bills of the petitioner in view of delay in completion of work was not in the nature of the liquidated damages or in the nature of penalty. Learned counsel submits that under clause 5.1, it was provided that the Contractor shall issue a notice to the Site In-charge within thirty days for issuance of Completion Certificate. He submits that such certificate issued by the Site In-charge, however, was not final and binding on the respondent. Under clause 25.1 of the Contract, a notice to rectify defects and for final inspection was required to be issued. 47. Learned counsel submits that the petitioner by its letter dated 21st October 2006 itself had applied for extension of time for Spread I till 27th November 2006 and for Spread II till 3rd January 2007. The petitioner had also requested for exclusion of CPL survey from definition of 'Time Schedule.' The said EIL by its letter dated 26th October 2006 rejected the request for exclusion of CPL survey from definition of 'Time Schedule' on the ground that the said work was a part of pre-commissioning. The petitioner had also requested for exclusion of CPL survey from definition of 'Time Schedule.' The said EIL by its letter dated 26th October 2006 rejected the request for exclusion of CPL survey from definition of 'Time Schedule' on the ground that the said work was a part of pre-commissioning. Even as per the certificate of the EIL, the petitioner had carried out CPL survey only on 9th October 2007 which was beyond the extended period. He submits that the respondent had considered the date of completion as 12th January 2007 for Spread I and 11th February 2007 for Spread II on the basis of completion of OFC though the respondent could have taken the date of completion as 9th October 2007 when CPL survey was completed and could have reduced the contract amount further. 48. Learned counsel placed reliance on the letter of the said EIL dated 28th October 2006 thereby refusing to grant extension of time for Spread II beyond 12th December 2006 and making it clear that the delay would be dealt with as per the provisions of the Contract for price reduction. Even according to the letter of 29th October 2006 from the said EIL to the petitioner, various works for Spread I were pending as on 29th October 2006. The said EIL had also pointed out that by letter dated 2nd November 2006, even the work of the petitioner for Spread II was not complete. The said EIL on 4th November 2006 had also observed that on 28th October 2006, the PCP and OFC work was not completed. The said EIL had noticed the same situation about non-completion of OFC and various other works in its letters dated 12th November 2006, 5th December 2006 and 2nd January 2007. The OFC testing report was signed by both the parties only after completion of work on 12th January 2007. 49. Learned counsel for the respondent submits that only on 23rd March 2007, the petitioner had submitted liquidated check list for pipeline Spread I. On 24th March 2007, the said EIL had informed the respondent that the OFC work was handed over. On 27th March 2007, the said EIL had advised that the work of the petitioner was not completed and various amounts payable to the petitioner should be kept on hold. The said EIL has also recommended for price reduction. 50. On 27th March 2007, the said EIL had advised that the work of the petitioner was not completed and various amounts payable to the petitioner should be kept on hold. The said EIL has also recommended for price reduction. 50. Learned counsel for the respondent invited my attention to the letter dated 27th April 2007 from the said EIL to the petitioner asking the petitioner to forward back up details in the attached format summarizing the pre-commissioning activities. On the same date, the petitioner had purported to have written a letter to the said EIL providing various details in the format suggested by the said EIL. 51. Learned counsel for the respondent invited my attention to the letter dated 3rd May 2007 from the said EIL to the respondent alleging that the pre-commissioning activities were completed by the petitioner within 28th October 2006 except the minor check list points, commissioning of PCP/CPL survey and mitigating measures. In the said letter, the said EIL further alleged that the commissioning of OFC for communication system and providing assistance for commissioning of pipeline were post pre-commissioning activities. The said EIL recommended that the amount of Rs.72,27,229/- in addition to the recoveries to be made by the respondent for material shortage was to be held in the pre final bill against completion of those activities. The said EIL opined that those activities shall be completed by the petitioner as per its final letter i.e. CPL and interference survey for Spread I would be completed by mid April 2007 and balance check list points would be completed by 30th June 2007. The similar recommendation also made for Spread II. Learned counsel submits that even according to the said letter, in so far as Spread I is concerned, CPL and interference survey which were agreed to be completed by the petitioner by mid April 2007 were completed only on 9th October 2007. In so far as the Spread II is concerned, learned counsel for the respondent submits that as against the date of completion, even according to the petitioner, CPL and interference survey would be completed by mid April 2007, however, the same was completed on 9th October 2007. Even in the minutes of meeting dated 15th May 2007, the petitioner had informed that the OFC reconciliation would be completed by 17th May 2007. 52. Even in the minutes of meeting dated 15th May 2007, the petitioner had informed that the OFC reconciliation would be completed by 17th May 2007. 52. Learned counsel submits that the said letter dated 3rd May 2007 addressed by the said EIL was contrary to the provisions of the Contract entered into between the parties and was showing several contradictions in taking a false and inconsistent stand than the stand taken by the said EIL in the earlier correspondence for various issues about the scope and part of the commissioning activities and also the scope of balance work left incomplete. Learned counsel submits that since the petitioner has not even handed over SPI for commissioning, question of the respondent commissioning in the month of November 2006 did not arise. 53. In so far as the reliance placed by the petitioner on the Annual Report of the respondent on the issue of commissioning of the project is concerned, the learned counsel invited my attention to various averments in the written statement and would submit that the respondent had clarified this aspect before the learned arbitrator that the date mentioned in the said Annual Report could not have been considered as conclusive. He submits that even according to the petitioner, the petitioner had not completed the work on the date mentioned in the said Annual Report. 54. Learned counsel invited my attention to the correspondence exchanged between the parties and the said EIL pointing out inconsistent and contradictory stand taken by the said EIL and alleging fraud and collusion between the parties and the said EIL. Learned counsel submits that Mr. V.N. Prasad, the then General Manager of the said EIL had joined the services of the petitioner. Mr. Thakur who had issued the revised certificate on behalf of the said EIL had issued such certificate much after he had left the EIL in the month of December 2007. He invited my attention to some of the paragraphs of the written statement bringing these facts on record. There was no denial to the said averments made by the respondent. He submits that once the respondent had pointed out an objectionable conduct of the said EIL and inconsistencies in its stand for extraneous consideration, the said EIL could not have issued a completion certificate belatedly in favour of the petitioner. There was no denial to the said averments made by the respondent. He submits that once the respondent had pointed out an objectionable conduct of the said EIL and inconsistencies in its stand for extraneous consideration, the said EIL could not have issued a completion certificate belatedly in favour of the petitioner. Learned counsel submits that even in the completion certificate issued by the said EIL to the petitioner as well as to the respondent, date of completion was different. No such reliance thus could be placed on the completion certificate issued by the said EIL. 55. Learned counsel submits that even if the completion certificate issued by the said EIL is considered as correct, even according to the said certificate, the work of CPL survey was completed only on 9th October 2007 which was much beyond the date of extended period of contract. The said EIL itself has stated that the said CPL survey was a part of the pre-commissioning work. The respondent was thus entitled to price reduction under the provisions of the Contract. Learned counsel submits that the respondent had exercised that right and had deducted the price reduction only up to OFC period and not up to 9th October 2007. Learned counsel submits that thus the learned arbitrator has rightly rendered various findings in favour of the respondent. Learned arbitrator after considering the evidence on record and after interpreting the terms of the Contract has justified the deductions made by the respondent from the running account bills of the petitioner as and by way of price reduction. The said price reduction was contractual and was proper. The findings rendered by the learned arbitrator are not perverse and cannot be interfered with under Section 34 of the said Arbitration Act. Learned counsel submits that no case is made out by the petitioner for impugning any part of the award. JUDGMENT :. By this petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 (for short “the said Arbitration Act), the petitioner has impugned the arbitral award dated 26th November 2011 passed by the learned arbitrator rejecting the claims made by the petitioner and holding that the respondent was entitled for deduction from the running account bills of the petitioner in line with price reduction clause and accordingly rejected the claims of the petitioner in the sum of Rs.3,28,73,691/-. Some of the relevant facts for the purpose of deciding this petition are as under: 2. The petitioner was the original claimant in the arbitration petition whereas the respondent herein was the original respondent. Some time in the month of April 2005, the respondent no.1 invited bids for laying of pipeline and associated facilities for Pune Solapur Pipeline Project. Pursuant to the said bidding document, the petitioner submitted its offer dated 18th June 2005. On 28th October 2005, the respondent issued a Letter of Intent in favour of the petitioner. The letter of intent was followed by a Purchase Order/Detailed Letter of Acceptance (DLOA) dated 28th October 2005. The scope of work included (a) laying of pipeline of outside diameter 355.6 mm for 182 km (Spread I) and (b) laying of pipeline of outside diameter 323.9 mm for 161 km (Spread II) from the terminal of the respondent at Loni near Pune to the receipt station at Pakni near Solapur. The pipeline was to pass through the existing terminal of respondent at Hazarwadi. The envisaged work also included laying of Optical Fibre Cable (OFC) from Trombay to Loni. 3. The estimated contract value under the said Letter of Intent was Rs.88,60,38,279/-. Time of completion provided was 10 months upto pre-commissioning from the date of issue of Letter of Intent for pipeline of outside diameter 355.6 mm, including Terminal and SV station and 6 months up to pre-commissioning from availability of first pipe at Dumpsite for Pipeline of outside diameter 323.9 mm. Clause 9 of the said Letter of Intent provided for the price reduction in case of works getting delayed. M/s. Engineers India Ltd. was appointed as Engineer-in-Charge for the said project. 4. On 28th October 2005, the petitioner mobilized on the site and commenced the activity of ROW/site grading etc. for completion of works contemplated in Spread I. On 15th January 2006, the petitioner mobilized on the site and commenced the activity of ROW/site grading etc. for completion of works contemplated in Spread II. 5. By letter dated 27th July 2006, the respondent alleged delay and serious lapses on the part of the petitioner resulting out of the inexperience of site team. for completion of works contemplated in Spread II. 5. By letter dated 27th July 2006, the respondent alleged delay and serious lapses on the part of the petitioner resulting out of the inexperience of site team. On 24th August 2006, the petitioner submitted a request for extension of time to M/s. Engineers India Ltd., the Engineer-in-Charge of the project (for short “the said EIL”) for extension of time for both Spread I and II on the grounds set out in the said letter. 6. On 8th September 2006, the said EIL sent a letter to the petitioner informing that any works completion getting extended or delayed beyond 29th October 2006 will be dealt with as per the provisions of the contract for price reduction. On 8th September 2006, the said EIL allowed the request of the petitioner for extension of time for both Spread I and II up to 28th October 2006 without any financial implication. On 20th October 2006, OISD report was submitted by the said EIL pointing out the balance scope of work to be completed by the petitioner. 7. On 21st October 2006, the petitioner submitted another request for extension of time in respect of Spread II up to 3rd January 2007. On 24th October 2006, the petitioner submitted a request for extension of time in respect of Spread I. On 26th October 2006, the said EIL rejected the request of the petitioner for further extension of time in respect of Spread I. By letter dated 28th October 2006, the said EIL granted extension of time in respect of Spread II up to 12th December 2006. It is the case of the petitioner that though the respondent had rejected the request of the petitioner for further extension of time in respect of Spread I, the petitioner completed the activities contemplated under clause 3 of the DLOA within the extended completion date of 28th October 2006. 8. By letter dated 26th October 2006, the said EIL informed the petitioner that the request of the petitioner for exclusion of CPL survey from definition of 'Time Schedule' was out of place and was not at all acceptable. The said EIL had refused to give time beyond 28th October 2006. On 29th October 2006, the said EIL informed the petitioner about the balance works list for Spread I related to pipeline and SV stations I to IV. The said EIL had refused to give time beyond 28th October 2006. On 29th October 2006, the said EIL informed the petitioner about the balance works list for Spread I related to pipeline and SV stations I to IV. On 30th October 2006, the said EIL enclosed comments of OISD and forwarded the same to the petitioner with a request to attend the balance points for making the pipeline and SV stations of Spread I ready for commissioning. 9. On 2nd November 2006, the said EIL addressed a letter to the petitioner expressing grave concern about the works of SV stations VI to IX not progressing at all since last one month and stating that the huge quantum of work was still pending. The said EIL enclosed all lists of activities to be completed by the petitioner. On 4th November 2006, the said EIL enclosed another list of balance work for pipeline laying activities to the petitioner as on 28th October 2006. On 4th November 2006, the said EIL enclosed list of balance work at IP and RT stations as on 28th October 2006 to the petitioner. On 12th November 2006, the said EIL addressed a letter to the petitioner pointing out that no spread in-charge was available for Spread I from the petitioner and also enclosed a list of balance work related to the pipeline for Spread I. On 6th November 2006, Test Report for SV-II was prepared. On 3rd December 2006, Test Report for SV-VII and SV-VIII was prepared. On 5th December 2006, the said EIL informed the petitioner about the list of balance activities of pipeline for Spread I. On 6th December 2006, OISD Report was submitted to complete certain works. On 12th December 2006, Test Report for SV-IX was prepared. 10. It is the case of the petitioner that on 2nd November 2006, the respondent commissioned the pipeline in Spread I i.e. just 4 days after the petitioner had completed the activities falling within its scope in respect of Spread I. The petitioner placed reliance on the Annual Report of the Ministry of Petroleum and Natural Gas in support of this contention. On or about 30th November 2006, the petitioner submitted RA Bill No.12A for Rs.6,28,47,493/- to the respondent. 11. On or about 30th November 2006, the petitioner submitted RA Bill No.12A for Rs.6,28,47,493/- to the respondent. 11. By a letter dated 2nd January 2007, the said EIL informed the petitioner that the progress of job front was sluggish and far from meeting target dates. On 29th January 2007, format IV listing out pending jobs for Spread II and Spread I was submitted. 12. On 6th February 2007, the said EIL addressed a letter to the petitioner expressing its concern regarding liquidation of check list and completion of balance works on pipeline, SV stations, IP/RT stations regarding Pune Solapur pipeline for Spreads I and II. On 6th February 2007, the said EIL enclosed Handing Over Format IV for Spread II by the respondent. 13. On 23rd February 2007, the petitioner forwarded Format III to the said EIL and informed that the same was ready for pre-commissioning certificate for OFC work. It is the case of the respondent that on 27th February, 2007, Format IV for Spread I showing that the work was incomplete. 14. It is the case of the petitioner that on 7th March 2007, the respondent no.1 under RA Bill No.12A paid only Rs.4,97,41,325/- to the petitioner and deducted Rs.1,06,18,358/-. According to the petitioner, the said amount withheld by the respondent was shown as liquidated damages even though there was no provision in the DLOA for such liquidated damages. 15. By letter dated 12th March 2007, the said EIL addressed a letter to the respondent enclosing Format IV for Spread I along with details of minor points to be attended by the petitioner. On 16th March, 2007, the respondent addressed a letter to the petitioner pointing out that the petitioner had assured on 15th February 2007 for completing all balance activities but had not kept the promise. The respondent pointed out that it was not possible to retain the services of the EIL nor the officer of the respondent indefinitely. 16. On 23rd March 2007, the petitioner submitted liquidated check list for pipeline Spread I to the said EIL. On 24th March 2007, the said EIL addressed a letter to the respondent enclosing Format IV for Spread I (OFC work) along with details of minor points to be attended by the petitioner. 17. 16. On 23rd March 2007, the petitioner submitted liquidated check list for pipeline Spread I to the said EIL. On 24th March 2007, the said EIL addressed a letter to the respondent enclosing Format IV for Spread I (OFC work) along with details of minor points to be attended by the petitioner. 17. On 27th March 2007, the said EIL addressed a letter to the respondent to keep bill amount on hold due to non completion of all/total work for Spread I against each item. On 27th March 2007, the said EIL addressed another letter to the respondent recommending to keep bill amount on hold due to non completion of all/total work for Spread I and also levy price reduction on account of delay on the part of the petitioner. 18. On 5th April 2007, the petitioner objected to the deduction made by the respondent and requested to release the amount so withheld against the liquidated damages. 19. On 9th April, 2007, the petitioner enclosed PCP Commissioning Report for Spread II to the said EIL. By letter dated 14th April 2007, the respondent informed the petitioner that since the said EIL had negated the request of the petitioner for time extension for Spread I sought by the petitioner vide letter dated 24th October 2006, the respondent had levied price reduction in line with clause 9 of the DLOA. It is the case of the petitioner that in addition to the amount withheld by the respondent from RA Bill No.12 A of the petitioner, the respondent had also withheld certain amounts from pre-final bills dated 12th January 2007 and 10th March 2007 of the petitioner for Spreads I and II respectively. 20. By an e mail dated 17th April 2007, the said EIL forwarded a draft copy of the recommendations dated 13th April 2007 to the respondent against the request letter submitted by the petitioner for time extension for Spreads I and II. On 27th April 2007, the petitioner gave a reply to the letter dated 27th April 2007 of the said EIL. On 28th April 2007, the respondent addressed a letter to the said EIL pointing out the reason for not sending the approved draft to the petitioner. 21. On 27th April 2007, the petitioner gave a reply to the letter dated 27th April 2007 of the said EIL. On 28th April 2007, the respondent addressed a letter to the said EIL pointing out the reason for not sending the approved draft to the petitioner. 21. On 3rd May 2007, the said EIL addressed a letter to the respondent pointing out that activities for CPL and interference survey for Spread I would be completed by mid April 2007 and balance check list point would be completed by 30th June 2007 and for Spread II would be completed by mid April 2007 and balance check list point would be completed by 30th June 2007. In the said letter, the said EIL alleged that it can be seen that all the works up to pre-commissioning except for minor check list points for Spreads I and II work were completed with time extension granted to the petitioner. 22. On 15th May 2007, a meeting between the petitioner, the respondent and the said EIL took place. In the Minutes of meeting, it was recorded that CPL survey for Spread II had been completed on 10th May 2007; OFC reconciliation would be completed on 17th May 2007. Warranty Certificate for DG sets would be submitted by 21st May 2007. Tree cutting in ROU would be completed by 31st May 2007 etc. 23. On 21st May 2007, the said EIL informed the petitioner that the petitioner's claim of extra work or cost of rework for Bhima river was not tenable. 24. On 11th July 2007, a meeting came to be held between the parties along with the said EIL. In the Minutes of meeting, it was confirmed that the petitioner would complete the job for ROU marker on 31st August 2007. All rectification job including obtaining NOC to be completed latest by 31st August 2007. On 27th July 2007, Format III for Spreads I and II came to be submitted. On 20th August 2007, the said EIL submitted a completion certificate. On 29th August 2007, the respondent addressed a letter to the said EIL pointing out that the extension of time completion could only be in accordance with clause 3.1 of the Document No.6545-04/41-TS-02. The respondent further pointed out that the said EIL had issued a completion certificate mentioning the date of completion as 30th June 2007. On 29th August 2007, the respondent addressed a letter to the said EIL pointing out that the extension of time completion could only be in accordance with clause 3.1 of the Document No.6545-04/41-TS-02. The respondent further pointed out that the said EIL had issued a completion certificate mentioning the date of completion as 30th June 2007. However, the Cathodic Protection (CP) system had not been handed over till date as the activities were still in progress. Format IV had not been signed by the respondent. The respondent pointed out that major job of coating was in part of the scope of the petitioner. Completion date could only be established after work was completed. The respondent also pointed out that as built document pertaining to CP had not been submitted. CPL survey reports had not been authenticated by the said EIL. The respondent returned the original completion certificate to the said EIL for correction. 25. In the month of August 2007, the petitioner submitted its final bill for Rs.6,58,07,064/- to the said EIL. The said amount was claimed in addition to the amounts withheld by the respondent no.1 from RA Bill No.12A of the petitioner and requested the respondent to pay a total amount of Rs.9,68,19,731/-. 26. On 20th September 2007, the respondent addressed a letter to the said EIL alleging that the statement of the said EIL that activities covered under clause 3.1.1 had been completed for Spread II was absolutely wrong, baseless, far from truth and contradictory. The respondent alleged that the completion date mentioned by the said EIL was out of extraneous reasons without having any relation to the contractual provisions. The dates for completion could only be established by joint inspection of the said EIL and the petitioner or the dates of handing over of any system. In the said letter, the respondent further stated that OISD had categorically mentioned that the activities like installation of warning board, direction markers, cathodic protection system, communication which were forming part of clause 3.1.1 had not been completed as on the date of inspection of OISD. The respondent also contended that the said EIL could not point out to the respondent any clause in the contract which provides for post pre-commissioning activity. It was contended that CP during pre-commissioning stage certainly means permanent CP and not limited to temporary CP. 27. The respondent also contended that the said EIL could not point out to the respondent any clause in the contract which provides for post pre-commissioning activity. It was contended that CP during pre-commissioning stage certainly means permanent CP and not limited to temporary CP. 27. It was stated that the view of the said EIL of job completion by 12th December 2006 was not based on any material facts and contractual terms and conditions. The respondent requested the said EIL to include some of the works which were beyond pre-commissioning were still not yet completed. The respondent pointed out that the said EIL had arbitrarily fixed the date of 30th June 2007. The said EIL did not reply to the letters of the respondent dated 21st July 2007, 31st July 2007 and 21st August 2007. The respondent made it clear that CP which was one of most important safety feature of pipeline and current drainage/ coating damages could not be treated as minor check list points and thus the completion certificate was incorrect. The respondent returned the said completion certificate to the said EIL since the same was not in accordance with the terms and conditions according to the respondent. 28. On 10th October 2007, there was a meeting held. In the Minutes of meeting, the petitioner committed that CP related activities would be completed by 31st October 2007. The petitioner requested that the painting job for warning board be deleted from its scope. The petitioner agreed to provide identification marker for SV I, II, III, VII and IX by 25th October 2007 and fencing at SV IV, V and VIII by 30th November 2007. 29. On 1st December 2007, the respondent paid a sum of Rs.5,13,51,759/- under the final bill to the petitioner and made various deductions which were shown as ‘Temporary Hold’ and ‘Permanent Hold.’ 30. On 7th December 2007, the petitioner while acknowledging the receipt of the amount of Rs.5,13,51,759/- objected to various deductions made by the respondent. The petitioner requested the respondent to release all the outstanding payment without any further delay. The petitioner also furnished a detailed break up of the withheld amount. 31. On 8th December 2007, the said EIL forwarded the final bill and revised completion certificate to the respondent. The said EIL, however, informed the respondent that the said EIL had not issued any completion certificate from its end. The petitioner also furnished a detailed break up of the withheld amount. 31. On 8th December 2007, the said EIL forwarded the final bill and revised completion certificate to the respondent. The said EIL, however, informed the respondent that the said EIL had not issued any completion certificate from its end. According to the said revised completion certificate, the activities pertaining to CPL survey attending to current drainage at SV stations were completed on 9th October 2007. 32. It is the case of the petitioner that in response to the request of the petitioner, the said EIL issued a copy of the completion certificate to the petitioner on 1st March 2008. In the said letter, the said EIL recorded that it had sent to the respondent the said certificate along with final bill of the petitioner. According to the petitioner, the said completion certificate dated 1st March 2008 issued by the said EIL would indicate that the petitioner had completed the activities in terms of clause 3 of the DLOA in respect of both Spreads I and II within the respective extended completion dates. 33. On 15th September 2008, the petitioner issued to the respondent a notice under Article 14 of the General Conditions of Contract to commence arbitration. On 14th October 2008, the respondent appointed Shri. R. Krishnan, a retired officer of the respondent as the sole arbitrator. 34. Pursuant to the directions issued by the learned arbitrator, the petitioner filed a statement of claim, inter alia, praying for recovery of Rs.3,28,73,691/- alleged to have been wrongfully recovered by the respondent though the petitioner had alleged to have been completed the activities contemplated under clause 3 of the DLOA. The petitioner had also applied for recovery of extra amount alleged to have been incurred while executing the work of Bhima river crossing and also a sum of Rs.1,13,56,350/- as extra for carrying out re-routing of pipeline alignment pursuant to the alleged instructions by the said EIL/the respondent. The petitioner demanded interest @18% p.a. The said arbitrator Shri. R. Krishnan appointed by the respondent, however, withdrew from the office of the arbitrator. Later on, Shri S.V. Narvekar was appointed by the respondent as the sole arbitrator in the arbitration proceedings from the stage of arguments. 35. The petitioner demanded interest @18% p.a. The said arbitrator Shri. R. Krishnan appointed by the respondent, however, withdrew from the office of the arbitrator. Later on, Shri S.V. Narvekar was appointed by the respondent as the sole arbitrator in the arbitration proceedings from the stage of arguments. 35. By an arbitral award dated 26th November 2011, the learned arbitrator held that the respondent was entitled for deductions from running account bills of the petitioner in line with price reduction clause amounting to Rs.3,28,73,691/- and accordingly, rejected the claim for recovery made by the petitioner and for interest. The learned arbitrator directed both the parties to bear the cost of arbitration equally. The said arbitral award has been impugned by the petitioner in this petition under Section 34 of the Arbitration and Conciliation Act, 1996. 36. Mr. Setalwad, learned senior counsel for the petitioner submits that the time for completion of works was provided as per clause 3 of DLOA. The extended dates for completion of activities in Spreads I and II were 28th October 2006 and 12th December 2006 respectively. The petitioner was obliged to complete pre-commissioning activities within the said extended completion dates. The activities forming part of 'Pre-commissioning' were enumerated in the 'Technical Specifications for Pre-commissioning and Commissioning.’ He submits that all pre-commissioning activities set out in the specifications were completed within the extended completion dates and in support of this contention, he placed reliance on the completion certificate issued by the said EIL. He submits that the said completion certificate issued by the said EIL was final and binding on the parties and could not be questioned about its correctness by the respondent. 37. Learned senior counsel submits that a final certificate issued by an Engineer/Architect is final and binding on the parties and cannot be challenged except on the ground of fraud, collusion or misconduct and except in the cases where the same had been issued at a time when there were disputes formulated between the parties or referred to arbitration. He submits that finding of the learned arbitrator that such completion certificate issued by the said EIL was not binding on the respondent is contrary to the law. In support of this submission, learned senior counsel placed reliance on the judgment of this Court in the case of Motilal Tajsi & Co. Vs. He submits that finding of the learned arbitrator that such completion certificate issued by the said EIL was not binding on the respondent is contrary to the law. In support of this submission, learned senior counsel placed reliance on the judgment of this Court in the case of Motilal Tajsi & Co. Vs. Ramchandra Gajanan Kherodkar, reported in AIR (29) 1942 Bombay 334 and in particular the following portions thereof which read thus :- “Therefore, even assuming that Clause (4) of the contract amounts to an arbitration clause, it would not ipso facto oust the jurisdiction of the architects to give a certificate under Clause (36) of the conditions of the contract unless Mr. Somjee satisfies me that there were disputes between the parties which were formulated and which were referred to the architects as arbitrators. If there were no disputes or if they were not formulated or if they were not referred to the architects, the jurisdiction of the architects to give a certificate continued unimpaired, and if they did give a certificate, it would be final and binding upon the parties. As I have already stated, in my opinion it was not the intention of the parties to constitute the architects as arbitrators, and any difficulty that one may feel in construing Clause (4) of the contract because of the words "the decision of the architects shall be final and binding on both parties and may be made a rule of the Court" is removed by consideration of the decision in (1909) Hudson's Building Contracts, Vol. II, (4th Edn.), page 411. The clause there which the Court considered was if anything much more favourable to the view advocated by Mr. Somjee than the clause here. The architect was described as the "judge", and with regard to the final certificate he was to issue, it was provided that it was to have the force and effect of an award and may be made a rule of His Majesty's High Court of Justice, or any division thereof, at the instance of either party hereto. The architect was described as the "judge", and with regard to the final certificate he was to issue, it was provided that it was to have the force and effect of an award and may be made a rule of His Majesty's High Court of Justice, or any division thereof, at the instance of either party hereto. In his judgment Lord Justice Buckley says (page 418) :- “It is quite true that the architect is to be an impartial person, no doubt; he is to determine the construction of the contract, and he must not "seek to construe it in favour of the corporation as distinguished from in favour of the contractors; he must act fairly as between the parties. Therefore he owes a duty to the contractors as well as a duty to the corporation, but he, I think, does not hold any judicial duty to one or to the other. Then if you add to that the last words of Section 33, all that you find there is that his certificate as to the work done, the money to be paid and so on, 'shall have the force and effect of an award, and may be made a rule of His Majesty's High Court of Justice, or any division thereof, at the instance of either party hereto'. I do not think that adds anything to it. It is not that this certificate is an award, but it is to be treated as something which it is not, and it is treated as if it were an award. That is the conclusion I come to upon the construction of that clause”. My conclusion on the construction of Clause (4) of the contract is the same. The mere fact that Clause (4) provides for the decision of the architects being made a rule of the Court does not alter their capacity in giving their decision which is not judicial but administrative, and in giving their decision under Clause (4) they do not act as arbitrators at all. If their decision is not an award, the mere fact that the parties provide that it may be made a rule of the Court would not any more make it an award. If their decision is not an award, the mere fact that the parties provide that it may be made a rule of the Court would not any more make it an award. Assuming I am wrong in my construction of Clause (4) and that Clause (4) is an arbitration clause, the next question that arises is whether there were any disputes between the parties before the issuing of the certificate which were referred to the arbitration of the architects within the meaning of Clause (4). Mr. Somjee has tendered four letters which his client wrote to the architects. In the first letter of June 7, 1938, he drew the attention of the architects to certain defects in the sanitary works and he called upon the architects to arrange to remove the present defective fittings and to replace them, with new ones. It is to be noted that in this letter the defendant wanted the architects to act administratively and do certain administrative acts. The decision of the architects was not sought on any dispute between the parties. The next letter of August 11, 1938, makes a grievance of various works which were left incomplete, and these incomplete works are set out seriatim. Here again the request made to the architects is that they should ask the contractors to complete the incomplete works. On January 14, 1939, a reminder was sent, and the architects were again called upon to request the contractors to attend to the defective and incomplete works. A final reminder was sent on June 26, 1939, and there again the grievance was that the architects had not yet got the contractors to complete the incomplete portions of the work and they were further asked to get the contractors to settle the claim of one Thakorlal & Co. in respect of some plumbing and sanitary works. Therefore it would be noted that in all these four letters the defendant was seeking the assistance of the architects to get the contractors to do certain things which he had the power to do under the contract and was making a complaint about various incomplete works which, according to him, the plaintiffs were bound to complete under the terms of the contract. But nowhere do these letters even suggest that there were any disputes between the defendant and the plaintiffs --let alone formulating these disputes, and I fail to understand how these letters can be possibly read as calling upon the architects to take upon themselves the burden of arbitration under Clause (4) of the contract and resolve the disputes between the parties. I therefore hold that assuming Clause (4) of the contract is to be read as an arbitration clause, on the evidence before me there were no formulated disputes between the parties which were referred to arbitration under Clause (4) and, therefore, the jurisdiction of the architects to issue a final certificate under Clause (36) of the conditions of the contract was not in any way ousted.” 38. Learned senior counsel submits that it was not the case of the respondent before the learned arbitrator that the completion certificate was procured by the petitioner either by fraud, collusion or misconduct. The completion certificate issued by the said EIL was binding on the respondent and could not have been ignored by the learned arbitrator. The impugned award is thus contrary to law and also contrary to the terms of the contract. 39. Learned senior counsel placed reliance on the judgment of the Court of Appeal in the case of Arenson Vs. Arenson and Anr., reported in (1973) 2 All E R 235 and would submit that none of the parties could impeach such certificate issued by the said EIL. Under clause 5.1 of the General Conditions of Contract, the said EIL who was authorised to issue such completion certificate and who was appointed as the Engineer-in-Charge had rightly issued such certificate. The respondent could not ignore such completion certificate issued by the said EIL who was appointed by the respondent itself on such flimsy ground. 40. Learned senior counsel submits that the report of the said EIL that the balance works and post commissioning works were not within the scope of the petitioner could not be faulted with by the learned arbitrator. The said opinion of the said EIL was binding on the respondent. The said EIL had also certified that the petitioner had completed all pre-commissioning works. The learned arbitrator while rejecting the said report certified by the said EIL had relied upon the alleged established practice without there being any evidence on record. The said opinion of the said EIL was binding on the respondent. The said EIL had also certified that the petitioner had completed all pre-commissioning works. The learned arbitrator while rejecting the said report certified by the said EIL had relied upon the alleged established practice without there being any evidence on record. The respondent did not lead any oral evidence to prove any established practice before the learned arbitrator. He submits that the established practice is a matter of fact and has to be pleaded and proved. The petitioner had already completed the activity of CP before commissioning. The respondent had not made any deductions for OFC laying works. 41. Learned senior counsel submits that in any event, since no loss was suffered by the respondent even if there was a delay in completion of work, no amount towards liquidated damages could have been recovered from the running account bills of the petitioner without the respondent having proved such loss. In support of this submission, he placed reliance on the judgment of this Court in the case of Smt. Panna Sunit Khatau and Ors. Vs. Dilip Dharmsey Khatau delivered on 12th April 2013 in Arbitration Petition No.4 of 1986 and in particular paragraphs 2 and 27 to 30 thereof which read thus :- “2. Some of the relevant facts for the purposes of deciding this petition are as under: Mr. Sunit Chandrakant Khatau, Kiran Chandrakant Khatau, Dilip Khatau, Abhay Khatau L. Khatau and Kishore Khatau were co-owners of the immovable property known as Khatau Bungalow, Manav Mandir Road, Mumbai 400 006. Under the family arrangement dated 10th August, 1983, the company known as Khatau Company Limited and certain other concerns were allotted to petitioners' group. In respect of the immovable property known as Khatau Bungalow, the Memorandum of Understanding dated 12th July, 1984 (for short "MOU") was executed between Kishore Dharamsey Khatau, Dilip Dharamsey Khatau and Abhay Laxmidas Khatau (hereinafter referred to as "DMK GROUP" and Mr. Sunit Chandrakant Khatau and Kiran Chandrakant Khatau (hereinafter referred to as "CMK GROUP"). The Petitioners in this petition would be referred to as CMK group whereas respondents would be referred to as DMK group. The main object of the said MOU was to implement the desire of the parties i.e. to divide and/or partition of the immovable property by metes and bounds. The Petitioners in this petition would be referred to as CMK group whereas respondents would be referred to as DMK group. The main object of the said MOU was to implement the desire of the parties i.e. to divide and/or partition of the immovable property by metes and bounds. It was agreed that the DMK group should have physical possession and ownership of two thirds of the said immoveable property and CMK group shall have physical possession and ownership of the remaining one-third of the said immoveable property. It was further agreed that in order to effectuate said desire and intention of the parties, two third of the total FSI in respect of the immovable property would be available to and for the beneficial enjoyment of the said two third portion given to DMK group and the one-third of the total FSI would be available to and for the beneficial enjoyment of one third coming to the share of the CMK group. Under clause 3 of the said MOU it was agreed that on the CMK group, their family members and personal servants and others handing over vacant possession to the DMK group of the portion of the said immovable property coming to the share of the DMK group, the DMK group shall pay to the CMK group a sum quantified at Rs. 55,00,000/- (Rupees Fifty Five Lacs) in consideration of the CMK group agreeing to take the portion of the immoveable property coming to their share. Clause 4 of the said MOU provided for the respective FSI for the beneficial enjoyment of the respective portion of the CMK and DMK group. Clause 5 of the said MOU provided that for implementing the said MOU regarding the division of FSI in manner specified in the immediately preceding clause, the party concerned shall demolish any structures or any part or parts thereof on the portion of the said immoveable property coming to such party so that the other party may have the enjoyment and beneficial use of that portion of the FSI allocable to such party's share or portion of the said immoveable property. Clause 6 provided that the DMK group shall ensure that they and the respective members of their families and personal servants are removed from that portion of the said immovable property, shaded yellow on the said plan, within six months from the date of the said MOU and procure in favour of the CMK group a proper performance Guarantee of authorized family members and guaranteeing the payment of Rs. 5,000/- per day. There was similar obligation cast upon CMK group. Clause 6 and 7 of the said MOU which are relevant for the purpose of deciding this petition are extracted below: “6. DMK Group shall ensure that they and the respective members of their families and personal servants are removed from that portion of the said immovable property/shaded yellow on the said plan within six months from the date hereof. The cost of removing all their family members and personal servants shall be borne wholly by the DMK Group and the responsibility will be of the DMK group. The DMK Group shall procure in favour of the CMK group a proper performance Guarantee of Hiten A. Khatau, Mahendra K. Khatau and Anil K. Khatau guaranteeing the performance by the DMK Group of the condition of this clause and guaranteeing the payment of Rs. 5,000/- (Rupees Five Thousand) per day in the event of any willful default or delay on the part of the DMK Group in performance of the said obligation. 7. CMK Group shall ensure that they and the respective members of their families and personal servants are removed from that portion of the property shaded green on the said plan within six months from the date hereof. The cost of removing all their family members and personal servants shall be borne wholly by the CMK Group and the responsibility will be of the CMK Group. The CMK Group shall procure in favour of the DMK Group a proper Performance Guarantee of Shri. Chandrakant M. Khatau guaranteeing the performance by the CMK Group of the condition of this clause and guaranteeing the payment of Rs. 10,000/- (Rupees ten thousand) per day in the event of any willful default or delay on the part of the CMK Group in performance of the said obligation.” 27. 10,000/- (Rupees ten thousand) per day in the event of any willful default or delay on the part of the CMK Group in performance of the said obligation.” 27. In my view on reading this clause as a whole with other obligations of parties and considering the intention and object of the executing of MOU, it reveals that the said clauses provided for payment of Rs. 10,000/- per day is in the nature of penalty. The clause does not indicate that both the parties had agreed that the said amount was correct, genuine pre estimate of damages. The Supreme Court in the case of ONGC Vs. Saw Pipes (supra) has considered a clause by which both the parties had agreed that the purchaser would recover from the contractor as agreed liquidated damages and it was not by way of penalty sum equivalent to 1% of the contract price of the whole unit per week for such delay or part thereof. It was agreed that the said sum was genuine pre-estimate of damages duly agreed by the parties. The Supreme Court construed such clause and held that it would be difficult to prove the exact loss or damage each party had suffered because of breach thereof and in such situation if the parties had pre estimated such loss after clear understanding, it would be unjustified to arrive at the conclusion that the party who had committed breach of the contract is not liable to pay compensation and it would be against the specific provisions of section 73 and 74 of the Indian Contract Act. The Supreme Court held that in the said clause, it was specifically mentioned that it was agreed genuine pre estimate of the damages duly agreed by the parties. It was also mentioned that the liquidated damages was not by way of penalty. With these facts under consideration, the Supreme Court held that there was no reason for the tribunal not to rely upon the clear and unambiguous terms of the agreement stipulating pre estimated damages caused for delay in supply of goods. The Supreme Court also considered that while extending the time for delivery of the goods, the respondent was informed that it would be required to pay stipulated damages. The Supreme Court also considered that while extending the time for delivery of the goods, the respondent was informed that it would be required to pay stipulated damages. In paragraph 68 of the said judgment the Supreme Court it is held that the terms of the contract are required to be taken into consideration before arriving at the conclusion whether the party claiming damages is entitled to the same. If the terms are clear and unambiguous stipulating liquidated damages, unless it is held that such estimate of damages/compensation is unreasonable, or is by way of penalty, party who has committed the breach is required to pay such compensation and that is what is provided under section 73 of the Contract Act. The Supreme Court also held in some cases that it would be impossible for the court to assess the compensation arising from breach and if the compensation contemplated is not by way of penalty or unreasonable, the court can award the same if it is genuine pre-estimate by the parties as the measure of reasonable compensation. The Supreme Court held that the Court is competent to award reasonable compensation in the case of breach even if no actual damage is proved to have been suffered in consequence of the breach of the contract. 28. The Division Bench of this court in the case of Board of Trustees of Port Vs. Pioneer (supra) has interpreted the judgment of the Supreme Court in the case of ONGC Vs. Saw Pipes by holding that the observations made by the Supreme Court will have to be read in the context of the facts of that case. The Division Bench held that the view of the Supreme Court that there was agreed genuine pre-estimate of damage duly agreed by the parties and there was no need to prove then was based on the relevant terms of that contract which stated that in the case of breach of contract purchaser can recover from the contractor as agreed liquidated damages and not by way of penalty sum equivalent to 1% of the contract price or part thereof on which the contractor had failed to deliver within the fixed period. In my view the clause considered by the Supreme Court in the case of ONGC Vs. Saw Pipes is totally different. In my view the clause considered by the Supreme Court in the case of ONGC Vs. Saw Pipes is totally different. It is the case of the respondent themselves that it is not possible to prove the loss suffered by the respondent, if any, in view of the petitioner not handing over the possession of their one third portion to the respondent. Even if the finding of willful default was correct, in my view, the learned arbitrator at the most could have awarded reasonable compensation and not the entire amount as calculated based on clause which is in the nature of penalty. None of the parties led any evidence before the learned arbitrator to prove as to what amount should be reasonable for grant of compensation. On perusal of the impugned award, it is clear that the learned arbitrator has awarded the entire amount of Rs. 10,000/- per day for the alleged willful default not only from 27th January, 1985 to 4th December, 1985 but also from 5th December, 1985 till the petitioners hand over possession to the respondent vacant possession. 29. In my view, award of Rs. 10,000/- per day as claimed which is in nature of penalty shows patent illegality on the face of award. Though the impugned award is a non speaking award, perusal of relief granted clearly reveals that the learned arbitrator had granted the entire relief as claimed by awarding Rs. 10,000/- per day by way of compensation. In my view grant of such relief by way of compensation is contrary to the judgment of the Supreme Court in the case of Fatechand Vs. Balkishandas (supra) AIR 1963 SC 1405 , Maulabux Vs. Union of India (supra), ONGC Vs. Saw Pipes, judgment of Single Judge of this Court in the case of O.N.G.C. Vs. Country Tabular and Jagson Vs. O.N.G.C. (supra) and judgment of Division Bench in the case of Board of Trustees of Part Vs. Pioneer Engineer. 30. Balkishandas (supra) AIR 1963 SC 1405 , Maulabux Vs. Union of India (supra), ONGC Vs. Saw Pipes, judgment of Single Judge of this Court in the case of O.N.G.C. Vs. Country Tabular and Jagson Vs. O.N.G.C. (supra) and judgment of Division Bench in the case of Board of Trustees of Part Vs. Pioneer Engineer. 30. In my view as the error committed by the learned arbitrator in awarding the compensation at the rates as claimed though the said clause was in the nature of penalty, is error apparent on the face of the award, the arbitrator has committed legal misconduct in making the award, the court is empowered to interfere with the said award under section 30 and 33 of the Arbitration Act, 1940 even in the case of non speaking award. Reliance thus placed by Mr. Rustomjee on nine judgments on the scope of section 30 read with section 33 of the Arbitration Act, 1940 is of no assistance to the respondents.” 42. Learned senior counsel submits that since the respondent had not issued any completion certificate, the petitioner had applied for such completion certificate to the said EIL. The said EIL had accordingly issued such completion certificate which is binding on both the parties. 43. In so far as the claim no. II is concerned, the learned senior counsel submits that the petitioner had carried out extra work while carrying out the work of Bhima river crossing. He submits that clause 2.13 of the Job Specific Requirements provided specifications for laying pipelines in the river crossing. The said clause stipulated that 'Pipelines in all river crossings were intended to be installed by open cut method.' However, the petitioner had realised that the depth of water, while working across the river, was possible only when a flow of water had been stopped or sufficiently reduced. This was because the pipelines had to be buried well below the maximum scour depth. He submits that in view of unforeseen problems encountered by the petitioner, the petitioner had to incur additional cost for mobilization and demobilization repeatedly to complete the work and thus the petitioner was entitled to recover a sum of Rs.2,00,80,699/- from the respondent. The learned arbitrator, however, has rejected the said claim without any basis and without any reasons. He submits that the findings rendered by the learned arbitrator are erroneous and are also contrary to the law. 44. The learned arbitrator, however, has rejected the said claim without any basis and without any reasons. He submits that the findings rendered by the learned arbitrator are erroneous and are also contrary to the law. 44. In so far as the claim no. III is concerned, learned senior counsel submits that in view of the instructions given by the respondent and the said EIL while executing the project, the petitioner had to carry out re-routing of pipeline alignment from KP 170 to KP 176 and on account of such instructions, the petitioner had to divert its resources which resulted in the petitioner incurring an additional cost and seeking an extension of time from the respondent. The new route/re-route was longer resulting in additional time and cost. He submits that the respondent had acknowledged the problems faced by the petitioner on account of re-routing while considering the request of the petitioner for extension of time. Reliance is placed on Section 70 of the Indian Contract Act 1872 and it is submitted that the learned arbitrator ought to have allowed the said claim on the principles of Quantum Meriut. In support of this submission, learned senior counsel placed reliance on the judgment of the Supreme Court in the case of Food Corporation of India & Ors. Vs. Vikas Majdoor Kamdar Sahkari Mandli Ltd., reported in 2007 (13) SCALE 126 and in particular paragraph 13 thereof which read thus : “13. If a party to a contract has done additional construction for another not intending to do it gratuitously and such other has obtained benefit, the former is entitled to compensation for the additional work not covered by the contract. If an oral agreement is pleaded, which is not proved, he will be entitled to compensation under Section 70. Payment under this section can also be claimed for work done beyond the terms of the contract, when the benefit of the work has been availed of by the defendant.” 45. Mr. Siodia, learned counsel for the respondent, on the other hand, invited my attention to the relevant correspondence exchanged between the parties as also between the said EIL and also invited my attention to the relevant provisions of the Contract to point out that the scope of work of the Contract awarded to the petitioner. Mr. Siodia, learned counsel for the respondent, on the other hand, invited my attention to the relevant correspondence exchanged between the parties as also between the said EIL and also invited my attention to the relevant provisions of the Contract to point out that the scope of work of the Contract awarded to the petitioner. Learned counsel submits that the work awarded to the petitioner included laying of OFC from Trombay to Loni and also the work of CP. 46. Learned counsel for the respondent placed reliance on clause 2.1 of the General Terms and Conditions of the Works Contract and would submit that the said provision provides for scope of work up to pre-commissioning stage. Learned counsel submits that clause 10 of the Notice Inviting Tender which provided for liquidated damages was subsequently replaced by another clause under which the respondent was permitted for price reduction by ½% (half percent) per week of delay or part thereof subject to ceiling of 5% (five percent) of the contract value of all the works in case of delay in completion of works due to reasons not attributable to the respondent. Learned counsel submits that thus the reduction made by the respondent from running account bills of the petitioner in view of delay in completion of work was not in the nature of the liquidated damages or in the nature of penalty. Learned counsel submits that under clause 5.1, it was provided that the Contractor shall issue a notice to the Site In-charge within thirty days for issuance of Completion Certificate. He submits that such certificate issued by the Site In-charge, however, was not final and binding on the respondent. Under clause 25.1 of the Contract, a notice to rectify defects and for final inspection was required to be issued. 47. Learned counsel submits that the petitioner by its letter dated 21st October 2006 itself had applied for extension of time for Spread I till 27th November 2006 and for Spread II till 3rd January 2007. The petitioner had also requested for exclusion of CPL survey from definition of 'Time Schedule.' The said EIL by its letter dated 26th October 2006 rejected the request for exclusion of CPL survey from definition of 'Time Schedule' on the ground that the said work was a part of pre-commissioning. The petitioner had also requested for exclusion of CPL survey from definition of 'Time Schedule.' The said EIL by its letter dated 26th October 2006 rejected the request for exclusion of CPL survey from definition of 'Time Schedule' on the ground that the said work was a part of pre-commissioning. Even as per the certificate of the EIL, the petitioner had carried out CPL survey only on 9th October 2007 which was beyond the extended period. He submits that the respondent had considered the date of completion as 12th January 2007 for Spread I and 11th February 2007 for Spread II on the basis of completion of OFC though the respondent could have taken the date of completion as 9th October 2007 when CPL survey was completed and could have reduced the contract amount further. 48. Learned counsel placed reliance on the letter of the said EIL dated 28th October 2006 thereby refusing to grant extension of time for Spread II beyond 12th December 2006 and making it clear that the delay would be dealt with as per the provisions of the Contract for price reduction. Even according to the letter of 29th October 2006 from the said EIL to the petitioner, various works for Spread I were pending as on 29th October 2006. The said EIL had also pointed out that by letter dated 2nd November 2006, even the work of the petitioner for Spread II was not complete. The said EIL on 4th November 2006 had also observed that on 28th October 2006, the PCP and OFC work was not completed. The said EIL had noticed the same situation about non-completion of OFC and various other works in its letters dated 12th November 2006, 5th December 2006 and 2nd January 2007. The OFC testing report was signed by both the parties only after completion of work on 12th January 2007. 49. Learned counsel for the respondent submits that only on 23rd March 2007, the petitioner had submitted liquidated check list for pipeline Spread I. On 24th March 2007, the said EIL had informed the respondent that the OFC work was handed over. On 27th March 2007, the said EIL had advised that the work of the petitioner was not completed and various amounts payable to the petitioner should be kept on hold. The said EIL has also recommended for price reduction. 50. On 27th March 2007, the said EIL had advised that the work of the petitioner was not completed and various amounts payable to the petitioner should be kept on hold. The said EIL has also recommended for price reduction. 50. Learned counsel for the respondent invited my attention to the letter dated 27th April 2007 from the said EIL to the petitioner asking the petitioner to forward back up details in the attached format summarizing the pre-commissioning activities. On the same date, the petitioner had purported to have written a letter to the said EIL providing various details in the format suggested by the said EIL. 51. Learned counsel for the respondent invited my attention to the letter dated 3rd May 2007 from the said EIL to the respondent alleging that the pre-commissioning activities were completed by the petitioner within 28th October 2006 except the minor check list points, commissioning of PCP/CPL survey and mitigating measures. In the said letter, the said EIL further alleged that the commissioning of OFC for communication system and providing assistance for commissioning of pipeline were post pre-commissioning activities. The said EIL recommended that the amount of Rs.72,27,229/- in addition to the recoveries to be made by the respondent for material shortage was to be held in the pre final bill against completion of those activities. The said EIL opined that those activities shall be completed by the petitioner as per its final letter i.e. CPL and interference survey for Spread I would be completed by mid April 2007 and balance check list points would be completed by 30th June 2007. The similar recommendation also made for Spread II. Learned counsel submits that even according to the said letter, in so far as Spread I is concerned, CPL and interference survey which were agreed to be completed by the petitioner by mid April 2007 were completed only on 9th October 2007. In so far as the Spread II is concerned, learned counsel for the respondent submits that as against the date of completion, even according to the petitioner, CPL and interference survey would be completed by mid April 2007, however, the same was completed on 9th October 2007. Even in the minutes of meeting dated 15th May 2007, the petitioner had informed that the OFC reconciliation would be completed by 17th May 2007. 52. Even in the minutes of meeting dated 15th May 2007, the petitioner had informed that the OFC reconciliation would be completed by 17th May 2007. 52. Learned counsel submits that the said letter dated 3rd May 2007 addressed by the said EIL was contrary to the provisions of the Contract entered into between the parties and was showing several contradictions in taking a false and inconsistent stand than the stand taken by the said EIL in the earlier correspondence for various issues about the scope and part of the commissioning activities and also the scope of balance work left incomplete. Learned counsel submits that since the petitioner has not even handed over SPI for commissioning, question of the respondent commissioning in the month of November 2006 did not arise. 53. In so far as the reliance placed by the petitioner on the Annual Report of the respondent on the issue of commissioning of the project is concerned, the learned counsel invited my attention to various averments in the written statement and would submit that the respondent had clarified this aspect before the learned arbitrator that the date mentioned in the said Annual Report could not have been considered as conclusive. He submits that even according to the petitioner, the petitioner had not completed the work on the date mentioned in the said Annual Report. 54. Learned counsel invited my attention to the correspondence exchanged between the parties and the said EIL pointing out inconsistent and contradictory stand taken by the said EIL and alleging fraud and collusion between the parties and the said EIL. Learned counsel submits that Mr. V.N. Prasad, the then General Manager of the said EIL had joined the services of the petitioner. Mr. Thakur who had issued the revised certificate on behalf of the said EIL had issued such certificate much after he had left the EIL in the month of December 2007. He invited my attention to some of the paragraphs of the written statement bringing these facts on record. There was no denial to the said averments made by the respondent. He submits that once the respondent had pointed out an objectionable conduct of the said EIL and inconsistencies in its stand for extraneous consideration, the said EIL could not have issued a completion certificate belatedly in favour of the petitioner. There was no denial to the said averments made by the respondent. He submits that once the respondent had pointed out an objectionable conduct of the said EIL and inconsistencies in its stand for extraneous consideration, the said EIL could not have issued a completion certificate belatedly in favour of the petitioner. Learned counsel submits that even in the completion certificate issued by the said EIL to the petitioner as well as to the respondent, date of completion was different. No such reliance thus could be placed on the completion certificate issued by the said EIL. 55. Learned counsel submits that even if the completion certificate issued by the said EIL is considered as correct, even according to the said certificate, the work of CPL survey was completed only on 9th October 2007 which was much beyond the date of extended period of contract. The said EIL itself has stated that the said CPL survey was a part of the pre-commissioning work. The respondent was thus entitled to price reduction under the provisions of the Contract. Learned counsel submits that the respondent had exercised that right and had deducted the price reduction only up to OFC period and not up to 9th October 2007. Learned counsel submits that thus the learned arbitrator has rightly rendered various findings in favour of the respondent. Learned arbitrator after considering the evidence on record and after interpreting the terms of the Contract has justified the deductions made by the respondent from the running account bills of the petitioner as and by way of price reduction. The said price reduction was contractual and was proper. The findings rendered by the learned arbitrator are not perverse and cannot be interfered with under Section 34 of the said Arbitration Act. Learned counsel submits that no case is made out by the petitioner for impugning any part of the award.