ORDER : 1. We have heard the learned Counsels for the parties. The short and only point that would require an answer from the Court in the present appeals is whether in respect of contracts entered into and fully executed prior to 23rd September, 1992, which is the date of coming into force of the Interest on Delayed Payments to Small Scale and Ancillary Industrial Undertakings Act, 1993 (hereinafter referred to as "the Act of 1993") the provisions of interest as contained in Sections 4 and 5 of the Act of 1993 would have any application. 2. The High Court held that the provisions of the Act of 1993 would apply to such situations and accordingly held the writ Petitioners-Respondents herein to be entitled to receive payments of interest under the Act of 1993. Aggrieved, the State of Arunachal Pradesh is in appeal. 3. Though a number of questions has been raised before the Court, including the correctness of the exercise of power Under Article 226 of the Constitution of India to decree the claims of money for contracts executed, we are of the view that on account of long efflux of time that has taken place we should not deal with any of the said issues and primarily focus on what has been indicated above. 4. The applicability of the Act of 1993 in respect of agreements executed and supplies effected prior to the coming into force of the Act of 1993 is no longer res integra. The question has been answered by this Court in Assam Small Scale Industries Development Corpn. Ltd. and Others vs. J.D. Pharmaceuticals and Another, (2005) 13 SCC 19 : AIR 2006 SC 131 , Para 41, (Para 37) and M/s. Purbanchal Cables & Conductors Pvt. Ltd. vs. Assam State Electricity Board and Another, 2012 (6) SCALE 314 : AIR 2012 SC 3167 . (Paras 39 and 40). 5. On the same question there has been a subsequent conflict of views between the two learned Judges of this Court in the decision in M/s. Shanti Conductors (P) Ltd. and Another vs. Assam State Electricity Board and Others.
(Paras 39 and 40). 5. On the same question there has been a subsequent conflict of views between the two learned Judges of this Court in the decision in M/s. Shanti Conductors (P) Ltd. and Another vs. Assam State Electricity Board and Others. Having gone through the judgment in M/s. Shanti Conductors (P) Ltd. (supra) we find that the difference between the two learned Judges and the consequential reference made in terms thereof would have no application to the facts of the present case when not only the dates of the agreement but even the date of supplies are admittedly prior to the coming into force of the Act of 1993. The only area of disagreement between the two learned Judges in M/s. Shanti Conductors (P) Ltd. (supra) is on the question as to whether for supplies that are effected subsequent to the coming into force of the Act of 1993, the same will have any application. 6. In view of the above, we take the view that the High Court had erred in granting interest under the provisions of the Act of 1993 to the writ Petitioners before it i.e. Respondents in the present appeal. 7. We accordingly set aside the aforesaid part of the order of the High Court. However, the order so far as the principal amount along with interest as applicable under the contract is maintained and the same, if not paid, shall be tendered to the Respondents by the Appellants forthwith and in any case within three months from today. The appeals is disposed of in the above terms.