Navajuga Infotech Private Ltd. , Rep. by its Vice President U. B. Raju v. Tamil Nadu Electricity Board
2017-05-26
M.M.SUNDRESH
body2017
DigiLaw.ai
ORDER : By consent W.P.No.8712 of 2017 and O.A.No.268 of 2017 have been called for and a common order is passed. 2. An agreement has been entered into between the petitioner and the respondents on 14.10.2010 for the purpose of digitalising the entire system throughout the State of Tamil Nadu. This agreement was entered into in pursuance to the invitation of bids through tenders made by the 1st respondent followed by the bid of the petitioner having been accepted. This agreement to develop the IT Infrastructure under the Restructured Accelerated Power Programme and Reforms Programme (RPDRP) has been entered into between the parties for the above said purpose. The period mentioned for execution is eighteen months. According to the petitioner, substantial work has been done. However, there is a continued non-cooperation on the part of the respondents. The first respondent is enjoying the completed work of the petitioner, but strangely not releasing the proportionate amount. According to the respondents, as seen from the impugned order under challenge, there is a series of non-compliance on the part of the petitioner, which has got a spiraling effect, including huge delay causing heavy loss. While the petitioner claims an approximately sum of Rs.140 Crores, the 1st respondent claims a sum of Rs.413 Crores. The respective claims are no doubt tentative in nature. The agreement also contains an arbitration clause in Annexure-3: Special Conditions of Contract. Clause GCC 8.2 speaks about the procedures for appointing the Arbitrators which is as under: "GCC 8.2: The formal mechanism for the resolution of disputes shall be: If the parties fail to resolve such a dispute or difference by mutual consultation within twenty-eight (28) days from the commencement of such dispute and difference, either party may require that the dispute be referred for resolution to the formal mechanisms, described below (The date of commencement of the dispute shall be taken from the date when this clause reference is quoted by either party in a formal communication clearly mentioning existence of dispute or as mutually agreed): a) The mechanism for resolution of disputes for bidders shall be in accordance with the Indian Arbitration and Conciliation Act of 1996. The Arbitral Tribunal shall consist of 3 (Three) Arbitrators. Each Party shall nominate an Arbitrator and the two nominated Arbitrators shall mutually agree and nominate a third Presiding Arbitrator.
The Arbitral Tribunal shall consist of 3 (Three) Arbitrators. Each Party shall nominate an Arbitrator and the two nominated Arbitrators shall mutually agree and nominate a third Presiding Arbitrator. b) The Arbitrators shall necessarily be retired High Court Judges and the umpire shall be a retired Chief Justice. c) The place for arbitration shall be Chennai." 3. The petitioner has approached this court by invoking Section 9 of the Arbitration and Conciliation Act, 1996 and incidentally filed two writ petitions. In the meanwhile, the 1st respondent has invoked the arbitration clause and appointed an Arbitrator, namely, Hon'ble Mr. Justice K. Chandru on its behalf. Under those circumstances, this Court has suggested to both sides to thrash all the issues between them before the Arbitration Tribunal. Accordingly the matter stands adjourned to today (26.05.2017). 4. When the matter is taken up for hearing today, both the learned counsels fairly submit that they would ventilate their grievances through the Arbitration Tribunal consisting of three Arbitrators. While the learned counsel for the first respondent has already named Hon'ble Mr. Justice K.Chandru, the learned counsel for the petitioner agrees with the appointment of Hon'ble Mr. Justice K.Venkataraman, as the nominee of the petitioner. Both the parties have also agreed that the Presiding Arbitrator would be Hon'ble Mr. Justice N.Paul Vasanthakumar, Retired Chief Justice of Jammu and Kashmir. 5. Though the clause referred above gives the discretion to the two nominated Arbitrators to nominate the third Presiding Arbitrator, in view of the agreement between the parties, coupled with the fact that it would avoid more delay, this Court is inclined to request Hon'ble Mr. Justice N.Paul Vasanthakumar, Retired Chief Justice of Jammu and Kashmir, to act as the Presiding Arbitrator. The Presiding Arbitrator shall also act as an Umpire as per Sub-Clause GCC 8.2(b), being the Retired Chief Justice. 6. There is an interim order in currency in the Original Application, not to precipitate the matter any further though pending mediation, which appears to have failed. The impugned order under challenge in W.P.No.13520 of 2017 merely states that action is being contemplated. Therefore, this Court is of the view that it is appropriate to protect the interest of the petitioner by ordering Status Quo as on today with specific reference to the proposed order of cancellation that is likely to be passed by the respondents.
The impugned order under challenge in W.P.No.13520 of 2017 merely states that action is being contemplated. Therefore, this Court is of the view that it is appropriate to protect the interest of the petitioner by ordering Status Quo as on today with specific reference to the proposed order of cancellation that is likely to be passed by the respondents. This order would be in currency till the petitioner makes an appropriate application before the Arbitration Tribunal, pending adjudication of the main arbitration. 7. Considering the urgency involved, this court requests the Arbitration Tribunal to convene a sitting at the earliest, preferably, within a period of two weeks from the date of receipt of a copy of this order. The parties are at liberty to file appropriate interim applications before the Arbitration Tribunal, if so advised. The learned Arbitrators are at liberty to fix their own fees. 8. With the above direction, the writ petitions and the original applications stand disposed of. No costs. Consequently, connected miscellaneous petitions and A.No.1238 of 2017 are closed.