JUDGMENT : 1. The applicant in the present contempt application has contended that the respondents are liable to be punished for the contempt of non th compliance of the judgment dated 12October, 2017, passed in Writ Petition No. 1562 of 2017 (S/S), Manoj Tripathi Vs. State of Uttarakhand and another, whereby, following direction was issued :- “2. Since the process for selection and appointment of temporary pharmacists has already been initiated, writ petition is disposed with direction to the respondents to complete the selection process as expeditiously as possible and declare the results promptly, unless the Government has meanwhile take a policy decision to cancel the selection.” 2. The language, as used in the said order, says that the respondents were supposed to take a decision and complete the selection process as expeditiously as possible and declare the result promptly. The interpretation of the word “as expeditiously as possible” would always be construed to be derived from the reasonable period which an authority is liable to take an action. The term reasonable time has been interpreted by the Hon’ble Apex Court in the following judgments : 3. In the case of Ram chand and others Vs. Union of India and others reported in (1994) 1 SCC 44 , the Apex Court has held in para 14 and 16 as under : “14. The Parliament has recognised and taken note of the inaction and non-exercise of the statutory power on the part of the authorities, enjoined by the provisions of the Act to complete the acquisition proceedings within a reasonable time and because of that now a time-limit has been fixed for making of the award, failing which the entire proceeding for acquisition shall lapse. But, can it be said that before the introduction of the aforesaid amendment in the Act, the authorities were at liberty to proceed with the acquisition proceedings, irrespective of any schedule or time-frame and to complete the same as and when they desired? It is settled that in a statute where for exercise of power no time-limit is fixed, it has to be exercised within a time which can be held to be reasonable.
It is settled that in a statute where for exercise of power no time-limit is fixed, it has to be exercised within a time which can be held to be reasonable. This aspect of the matter can be examined in the light of second proviso to Article 31-A of the Constitution, which in clear and unambiguous terms prohibits making of any law which does not contain a provision for payment of compensation at a rate, which shall not be less than the market value thereof. The Act is consistent with the second proviso to Article 31-A, because it provides for payment of compensation at the market value of the land acquired. But, whether the constitutional and statutory requirement of the payment of the market value to the persons, whose lands have been compulsorily acquired, is not being circumvented and violated by keeping the land acquisition proceedings pending for more than a decade and half, without making the awards and paying the compensation, which has been pegged to the dates of notifications under sub-section (1) of Section 4 of the Act, which in the present cases had been issued 14 to 21 years before the making of the awards. If a person is paid compensation in the year 1980/1981 at the market rate, prevailing twenty years before, will that be compliance of the constitutional and statutory mandate? Ignoring the escalation of the market value of the lands, especially near the urban agglomeration or metropolitan cities, will amount to ignoring an earthquake and courts can certainly take judicial notice of the said fact. The interest and the solatium, which have to be paid under the provisions of the Act, are linked with the market value of the land with reference to the date of the notification under subsection (1) of Section 4 of the Act. If a decision had been taken as early as in the year 1966, by issuance of declarations under Section 6, that the lands belonging to the different cultivators, who held those lands within the ceiling limit for cultivation, were needed for public purpose, respondents should have taken steps for completion of the acquisition proceedings and payment of compensation at an early date.
In the present cases, unless a justification is furnished on behalf of the respondents, can it be said that the statutory power of making an award under Section 11 has been exercised within a reasonable time from the date of the declaration under Section 6? Due to escalation in prices of land, more so in this area, during the preceding two decades, in reality, the market rate, on the date of the notification under Section 4(1) is a mere fraction, of the rate prevailing at the time of its determination in the Award. 16. On behalf of the respondents, it was pointed out that the petitioners have approached this Court only after making of the awards, or when awards were to be made, having waited for more than fourteen years, without invoking the jurisdiction of the High Court under Article 226 or of this Court under Article 32. It is true that this Court has taken note of delay on the part of the petitioners concerned in invoking the jurisdiction of the High Court or of this Court for quashing the land acquisition proceedings on the ground that the proceedings for acquisition of the lands in question have remained pending for more than a decade, in the cases of Aflatoon v. Lt. Governor of Delhi and Ramjas Foundation v. Union of India According to us, the question of delay in invoking the writ jurisdiction of the High Court under Article 226 or of this Court under Article 32, has to be considered along with the inaction on the part of the authorities, who had to perform their statutory duties. Can the statutory authority take a plea that although it has not performed its duty within a reasonable time, but it is of no consequence because the person, who has been wronged or deprived of his right, has also not invoked the jurisdiction of the High Court or of this Court for a suitable writ or direction to grant the relief considered appropriate in the circumstances? The authorities are enjoined by the statute concerned to perform their duties within a reasonable time, and as such they are answerable to the Court why such duties have not been performed by them, which has caused injury to claimants.
The authorities are enjoined by the statute concerned to perform their duties within a reasonable time, and as such they are answerable to the Court why such duties have not been performed by them, which has caused injury to claimants. By not questioning, the validity of the acquisition proceedings for a long time since the declarations were made under Section 6, the relief of quashing the acquisition proceedings has become inappropriate, because in the meantime, the lands notified have been developed and put to public use. The lands are being utilised to provide shelter to thousands and to implement the scheme of a planned city, which is a must in the present set-up. The outweighing public interest has to be given due weight. That is why this Court has been resisting attempts on the part of the landholders, seeking quashing of the acquisition proceedings on ground of delay in completion of such proceedings. But, can the respondents be not directed to compensate the petitioners, who were small cultivators holding lands within the ceiling limit in and around Delhi, for the injury caused to them, not by the provisions of the Act, but because of the non-exercise of the power by the authorities under the Act within a reasonable time?” 4. In the case of State of Gujrat Vs. Patil Raghav Natha and others reported in 1969 (2) SCC 187 , the Apex Court has held in para 12 as under : “12. It seems to us that Section 65 itself indicates the length of the reasonable time within which the Commissioner must act under Section 211. Under Section 65 of the Code if the Collector does not inform the applicant of his decision on the application within a period of three months the permission applied for shall be deemed to have been granted. This section shows that a period of three months is considered ample for the Collector to make up his mind and beyond that the legislature thinks that the matter is so urgent that permission shall be deemed to have been granted. Reading Sections 211 and 65 together it seems to us that the Commissioner must exercise his revisional powers within a few months of the order of the Collector.
Reading Sections 211 and 65 together it seems to us that the Commissioner must exercise his revisional powers within a few months of the order of the Collector. This is reasonable time because after the grant of the permission for building purposes the occupant is likely to spend money on starting building operations at least within a few months from the date of the permission. In this case the Commissioner set aside the order of the Collector on October 12, 1961 i.e more than a year after the order and it seems to us that this order was passed too late.” 5. Yet again, in the case of Mohamad Kavi Mohamad Amin Vs. Fatmabai Ibrahi reported in (1997) 6 SCC 71 , the Apex Court has held in para 2 as under :- “2. Although Mr Bhasme, learned counsel appearing for the appellant took a stand that under Section 63 of the Act aforesaid, there should not be any discrimination amongst the agriculturists with reference to the State to which such agriculturist belongs. But according to him even without going into that question the impugned order can be set aside on the ground that suo motu power has not been exercised within a reasonable time. Section 84-C of the Act does not prescribe any time for initiation of the proceeding. But in view of the settled position by several judgments of this Court that wherever a power is vested in a statutory authority without prescribing any time-limit, such power should be exercised within a reasonable time. In the present case the transfer took place as early as in the year 1972 and suo motu enquiry was started by the Mamlatdar in September 1973. If sale deeds are declared to be invalid the appellant is likely to suffer irreparable injury, because he has made investments after the aforesaid purchase. In this connection, on behalf of the appellant reliance was placed on a judgment of Justice S.B. Majmudar (as he then was in the High Court of Gujarat) in State of Gujarat v. Jethmal Bhagwandas Shah disposed of on 1-3-1990, where in connection with Section 84-C itself it was said that the power under the aforesaid section should be exercised within a reasonable time.
This Court in connection with other statutory provisions, in the case of State of Gujarat v. Patil Raghav Natha and in the case of Ram Chand v. Union of India has impressed that where no time-limit is prescribed for exercise of a power under a statute it does not mean that it can be exercised at any time; such power has to be exercised within a reasonable time. We are satisfied that in the facts and circumstances of the present case, the suo motu power under Section 84-C of the Act was not exercised by the Mamlatdar within a reasonable time. Accordingly, the appeal is allowed. The impugned orders are set aside. No costs.” 6. Admittedly, the contempt petition has been preferred by the applicant much beyond the period as specified under Section 20 of the Contempt of Courts Act. Section 20 of the Contempt of Courts Act reads as under:- “20. Limitation for actions for contempt.-No court shall initiate any proceedings of contempt, either on its own motion or otherwise, after the expiry of a period of one year from the date on which the contempt is alleged to have been committed." 7. Section 20 of the Act creates a bar that no contempt would be initiated after the expiry of one year period from the date from which the alleged non compliance is said to have been committed. 8. Consequently, this Contempt Petition cannot be entertained by this Court on account of the aforesaid statutory bar created by Section 12 of the Contempt of Courts Act. Hence, the same is dismissed.