Imperial Engineering Company Represented By Its Managing Partner Easo John v. Technopark Park Centre
2021-07-22
T.R.RAVI
body2021
DigiLaw.ai
JUDGMENT : This writ petition is filed challenging Ext.P16 order, whereby the petitioner has been blacklisted from participating in tenders floated by the 1st respondent for a period of one year with effect from 05.01.2017 and the EMD of Rs.50,000/- has been forfeited. 2. Heard Sri M.A.Abdul Hakhim on behalf of the petitioner and Smt.K.V.Rashmi, Standing Counsel for respondents 1 and 2. 3. The petitioner, which is a registered firm, is involved in undertaking electrical works from Governmental and semi-Governmental institutions. The petitioner had undertaken the electrical contract of the building named “Thejaswini” situated in the 1st respondent Techno Park and the same was completed during 2006-2009, as can be seen from Ext.P1. As part of expansion, the respondents wanted to install two additional diesel generators in the said building. The 2nd respondent issued Ext.P6 dated 29.06.2016 inviting tenders for supply, installation, testing and commission of two numbers of diesel generator sets and modification of electrical panel, etc. Ext.P6 shows that the period of completion was three months and earnest money deposit of Rs.50,000/-was to be deposited and Rs.5,000/-plus tax at 5% was to be deposited towards cost of tender documents. The last date for submission of the e-tender was 20.07.2016. A pre-bid meeting was scheduled on 05.07.2016 at Park Centre Building, Technopark. The date of opening of the techno-commercial bid was 25.07.2016 and the tenderers were expected to give a firm period of 120 days for the tender from the date of opening of the bid. The petitioner participated in the tender process. The petitioner who submitted a bid for Rs.1,62,59,440/-was the lowest tenderer. On 17.11.2016, the 1st respondent sent Ext.P9 mail to the petitioner, requesting them to submit an additional bank guarantee for Rs.35,20,000/-(16% of Rs.2.2 crores) within 10 days to enable them to issue the work order. Respondents had relied on clause 4.6 of the instructions to the tenderer. On 18.11.2016, the petitioner sent Ext.P10 reply stating that they had already pointed out during discussions that rates were quoted without taking into account the requirement for additional performance guarantee. It was stated that since the notice inviting tender did not specify the PAC, there was no way in which they could have known whether the offer that they are making was 25 % less than the PAC and that they would be liable to provide an additional performance guarantee.
It was stated that since the notice inviting tender did not specify the PAC, there was no way in which they could have known whether the offer that they are making was 25 % less than the PAC and that they would be liable to provide an additional performance guarantee. On 28.11.2016 the respondents wrote to the petitioner stating that they are yet to receive a response regarding the submission of additional performance guarantee for Rs.35,20,000/-and granting them 10 more days for submission of such guarantee. On 01.12.2016, the petitioner informed that they had already sent a letter on 18.11.2016 explaining their position with regard to performance guarantee. Thereafter the respondents issued Ext.P13, wherein they informed the petitioner that the EMD for Rs.50,000/-submitted along with the e-tender will be forfeited and further action shall be taken regarding the tender, as per the procedure. On 20.12.2016, the petitioners wrote Ext.P14 letter in reply to Ext.P13 objecting to the decision to forfeit the EMD, pointing out that clause 4.4 of tender conditions does not permit such an action. It was also pointed out that the respondents had intimated the PAC as Rs.2.2 Crores only in Ext.P9 e-mail and that prior to the notice inviting tender and at the time of submitting the tender, there was no way in which the petitioner could have known the PAC. It was also pointed out that this vital information regarding the tender was concealed, which is against the CPWD norms. In Ext.P14, the petitioner had also made a suggestion that since the major item of the tender is the DG set, they will construct the necessary foundation and unload the DG set in the site within 15-20 days thereby assuring that the major item is already at site, which is a sufficient guarantee and that the balance value of the work would only be Rs.69,84,580/-. It was pointed out that such a course of action will assure a guaranteed completion. It was again requested that if the above suggestion was not agreeable, the EMD may be refunded. On 03.01.2017, the respondents sent Ext.P15 letter to the petitioner stating that even though the respondents had arranged a pre-bid meeting, the petitioner failed to attend the same and if he had attended, he could have sought clarification regarding the PAC even before the submission of the bid.
On 03.01.2017, the respondents sent Ext.P15 letter to the petitioner stating that even though the respondents had arranged a pre-bid meeting, the petitioner failed to attend the same and if he had attended, he could have sought clarification regarding the PAC even before the submission of the bid. Thereafter, on 10.01.2017, the respondents issued Ext.P16 to the petitioner, whereby the petitioner was informed of the decision to forfeit the EMD and to blacklist the petitioner from participating in the tenders floated by the Technopark, for a period of one year with effect from 05.01.2017. The petitioner challenges Ext.P16 in this writ petition. 4. The Standing Counsel for the respondents has filed a statement wherein it is stated that the petitioner did not choose to attend the pre-bid meeting and that it was his fault that he did not seek any clarification regarding the PAC from the respondents. It is stated that normally respondents do not specify the PAC, since they want to get more competent rates and that no bidder has asked any clarification regarding the PAC during the pre-bid meeting. According to the respondents, the petitioner had quoted the work at the rate of 26% below the estimated value and hence under clause 4.6 of the tender conditions, the petitioner was bound to provide additional performance guarantee. It is stated that the additional performance guarantee is to ensure that a person does not underquote the work and would ensure completion of the work. 5. The petitioner has submitted a reply affidavit producing Ext.P17 tender notice dated 18.01.2017, which was issued within six months after Ext.P6 tender notice, in which the respondents had specified the PAC. Exts.P7 and P8 issued during 2014 are also instances where the respondents had specified the PAC in the notice of tender. The petitioner has thereafter produced Ext.P18 along with I.A.No.1 of 2021, which is the copy of the notice inviting tender for the very same work covered by Ext.P6. It can be seen therefrom that the respondents had specified the PAC. The respondents have produced Annexure R1(A) containing the relevant pages of the conditions of tender, which was notified as per Ext.P6. Reference is made to clauses 4.4 and 4.6, which are extracted below, to justify the actions taken by the respondents. 4.4 EMD/SECURITY DEPOSIT/RETENTION MONEY Earnest Money Deposit prescribed shall be remitted in line with the online payment feature stipulated.
The respondents have produced Annexure R1(A) containing the relevant pages of the conditions of tender, which was notified as per Ext.P6. Reference is made to clauses 4.4 and 4.6, which are extracted below, to justify the actions taken by the respondents. 4.4 EMD/SECURITY DEPOSIT/RETENTION MONEY Earnest Money Deposit prescribed shall be remitted in line with the online payment feature stipulated. EMD of the unsuccessful tenderer will be refunded without any interest on finalisation of contract. E.M.D may be forfeited I. If a bidder withdraws his bid during the period of validity specified. II. If the successful bidder fails within the time limit to sign the contract document or fails to furnish the required security deposit. 4.6 ADDITIONAL PERFORMANCE GUARANTEE Additional performance guarantee will be required to be submitted by the successful contractor if the works are quoted between 11% to 25 % below the estimated rate. This additional performance guarantee shall be equal to the unbalanced price in the estimate PAC and quoted PAC. This will be released only after satisfactory completion of the work without any interest.” 6. A Learned Single Judge of this Court in M/s K.V.Joseph & Sons Private Ltd., Kochi and another vs Principal Secretary to Government, Thiruvananthapuram and others reported in 2017 KHC 170, considered the requirement to provide additional performance guarantee. On the facts of that case, the learned judge held that the bidder was bound to provide additional performance security and that as long as the grievance of the bidder was addressed, he cannot challenge an action for not providing additional performance guarantee on the ground of violation of any principles of natural justice. The counsel for the petitioner pointed out that the facts on which the above judgment was rendered are totally different from the facts involved in the case on hand. It can be seen from paragraph 19 of K.V.Joseph(supra) that there is a specific clause in the contract between the parties, which provided that the failure to provide the additional performance guarantee would result in forfeiture of the EMD as well as an annulment of the award. It is pointed out that there is no such clause available in the contract involved in this case.
It is pointed out that there is no such clause available in the contract involved in this case. It is further pointed out that in K.V.Joseph(supra), the estimate PAC was known to the bidders and hence the bidders knew whether the quoted PAC is falling between the range of 11% and 25%, warranting the provision of additional performance guarantee. Since the estimate PAC was not revealed in the tender document, it is the contention of the Counsel that there is no justification for either blacklisting the petitioner or for forfeiture of EMD. A reading of the above judgment would clearly show that many of the clauses which were available in the contract between the parties, on an interpretation of which the judgment was delivered, are not available in the contract involved in the case on hand. I am hence of the opinion that the judgment in K.V.Joseph (supra) cannot be applied to the facts of this case. 7. The counsel for the petitioner relied on the decision of the Hon'ble Supreme Court in Suresh Kumar Wadhwa v. State of M.P., reported in (2017) 16 SCC 757 and contended that a forfeiture of the EMD could have been resorted to only if there is a specific clause in the agreement between the parties, which permitted the same. The Hon'ble Supreme Court has in the above said judgment held that as per Section 74 of the Contract Act, 1872, if there is no stipulation in the contract for forfeiture, there is no such right available to the party to forfeit the EMD. On the question of publishing the material aspects relating to the contract, the Hon'ble Supreme Court held in the above said judgment that the object behind publishing all material terms is to make the same known to the contracting parties/bidders, so that they can be aware of their rights, obligations and liabilities qua each other and also of the consequences in the event of their non-compliances and also to empower the State to enforce any such term against the bidder in the event of any breach committed by the bidder and to bind the bidder to the express terms in the contract/public notice. A similar view was taken by the Hon'ble Supreme Court in the decision in Union of India v. Vertex Broadcasting Co. (P) Ltd., reported in (2015) 16 SCC 198.
A similar view was taken by the Hon'ble Supreme Court in the decision in Union of India v. Vertex Broadcasting Co. (P) Ltd., reported in (2015) 16 SCC 198. In the absence of disclosure of estimate PAC in the tender document, the demand for additional performance guarantee cannot hence bind the petitioner. The circumstances in which EMD can be forfeited has been specified in clause 4.4 extracted above. Failure to provide Additional performance guarantee is not a reason stipulated in the said clause. Moreover, since the estimate PAC was not revealed in the notice calling for tender, the petitioner cannot be found fault with for not being aware that his bid was 26 % below the estimate PAC. As such, there is no justification whatsoever, to withhold the EMD provided by the petitioner. 8. Coming to the question of blacklisting of the petitioner, the Hon'ble Supreme Court has in Erusian Equipment & Chemicals Ltd. v. State of W.B. Reported in (1975) 1 SCC 70 held that the blacklisting order involves civil consequences and casts a slur and that it creates a barrier between the persons blacklisted and the Government in the matter of transactions. It was held that the blacklists are “instruments of coercion” and it has the effect of preventing a person from the privilege and advantage of entering into lawful relationship with the Government for purposes of gains. The Hon'ble Supreme Court held that fundamentals of fair play require that the person concerned should be given an opportunity to represent his case before he is put on the blacklist. In Patel Engg. Ltd. v. Union of India, reported in (2012) 11 SCC 257 , the Hon'ble Supreme Court held that the authority of the State to blacklist a person is a necessary concomitant to the executive power of the State to carry on the trade or the business and making of contracts for any purpose and that the only legal limitation upon the exercise of such an authority is that the State is to act fairly and rationally without in any way being arbitrary. The Hon'ble Supreme Court further held that the bid document is not a statutory instrument and that the failure to mention blacklisting to be one of the probable actions that could be taken against the delinquent bidder does not, by itself, disable the State from blacklisting a delinquent bidder, if it is otherwise justified.
The Hon'ble Supreme Court further held that the bid document is not a statutory instrument and that the failure to mention blacklisting to be one of the probable actions that could be taken against the delinquent bidder does not, by itself, disable the State from blacklisting a delinquent bidder, if it is otherwise justified. However, Patel (supra) was a case in which the person who was blacklisted was put on notice and given an opportunity of hearing. Admittedly, in the case on hand the petitioner was not put on notice regarding the blacklisting nor was he heard. The period of blacklisting was for one year. This Court had stayed the operation of the order of blacklisting. The period for which the petitioner was blacklisted has expired. It is fairly submitted by the counsel for the respondents that the petitioner had been permitted to enter into contracts with the respondents during the period when this writ petition has been pending consideration of this Court. Even though there is no consequence to follow after the passage of four years, nevertheless, it has to be held that the blacklisting of the petitioner without putting him on notice is bad in law. The Standing Counsel for the respondents submitted that the petitioner was granted sufficient time to comply with the requirement to furnish additional performance guarantee. Since I have already held that the demand for additional performance guarantee cannot bind the petitioner, the fact of granting sufficient time is not relevant. In the result, the Writ petition is allowed. Exhibit P16 order issued by the Respondents is quashed. It is declared that the blacklisting of the petitioner as per Exhibit P16 is not in accordance with law. The Respondents were directed to release the EMD which has been forfeited by the Respondents, within one month from the receipt of a copy of the judgment. The parties shall bear their respective costs.