Research › Search › Judgment

J&K High Court · body

2023 DIGILAW 596 (JK)

M & Co. Engineers & Contractors Pvt. Ltd. v. J&K Power Transmission Corporation Ltd.

2023-10-07

RAJNESH OSWAL

body2023
JUDGMENT : WP(C) No.1560/2023 1) Vide e-NIT/TLMD-VIII/TS/19 of 2022 dated 18.11.2022, the respondent No.1 invited tender for the following works: “Design, Manufacturing, Supply, Erection, Testing & Commissioning of 2 x10 MVA, 132/33 KV Gas insulated sub-station (GIS) at Sumbal, District Ganderbal, including Design, Manufacturing, Supply, laying, Jointing/Termination, Testing & Commissioning of 33 KV 300 sqmm XLPE Power Cable from GIS Sumbal to Gagengeer (Z-Morh Tunnel).” 2) The petitioner-Joint Venture was one of the six respondents to the tender notice. It is stated that during scrutiny of the tenders, certain curable deficiencies were found in all the tenders submitted by six participants. Accordingly, the respective communications were sent to each of the six participants. The petitioner vide communication dated 23.02.2023 was informed by the respondent No.3 that specific construction experience of bidder in respect of GIS and cable package was not submitted by the petitioner and was accordingly instructed to furnish the requisite short fall documents by 01.03.2023 up to 3.00 pm, so as to enable the respondents to proceed further with the evaluation. The petitioner in response to the aforesaid communication, addressed a communication dated 28.02.2023 to the respondent No.3, stating therein that M/S Garima Enterprises, Ghaziabad, was the partner of the Joint Venture and their representatives were present in the pre-bid meeting held on 26.12.2022 in the office of Chief Engineer at Srinagar. It was also stated that the petitioner has also submitted an authorization and performance certificate from OEMs for GIS (M/S Hitachi Energy India Limited) and 33 KV Cable (M/S Universal Cables Limited) for the related works executed by the petitioner and also the undertaking that the OEM’s will make their technical and engineering staff fully available for supervision /erection and commissioning of the project. The petitioner-Joint Venture also enclosed specific and general experience of ‘M/S Garima Enterprises, Ghaziabad’ along with work done certificate and a copy of the Joint Venture Agreement. Thereafter, vide communication dated 20.03.2023 (e-mail), the petitioner-Joint Venture was intimated that it was found to be responsive during technical evaluation. Thereafter vide communication dated 23.03.2023, the petitioner-Joint Venture was informed that its bid has been admitted by the Committee and petitioner was asked to remain in touch with the Tender Inviting Authority. The Contract Committee in its meeting held on 12.05.2023, recommended that the matter be placed before the Board of Directors for approval. Thereafter vide communication dated 23.03.2023, the petitioner-Joint Venture was informed that its bid has been admitted by the Committee and petitioner was asked to remain in touch with the Tender Inviting Authority. The Contract Committee in its meeting held on 12.05.2023, recommended that the matter be placed before the Board of Directors for approval. It is further averred that the petitioner-Joint Venture is unaware as to what transpired thereafter till 09.06.2023 and all of a sudden the Contract Committee, which had previously recommended the case of the petitioner for being placed before the Board of Directors for approval, reversed its decision and recommended that e-NIT dated 18.11.2022 be cancelled. 3) The petitioner has impugned the decision of the Contract Committee-1 bearing No.TLMD-VIII/TS/957-61 dated 09.06.2023, on the grounds that the Contract Committee had no authority to cancel the e-NIT dated 18.11.2022 when the Committee had decided to place the matter before the Board of Directors. It is also submitted that the decision to allot or not to allot the contract or to cancel the tender notice vests exclusively in the Board of Directors, which is the competent authority and no reason has been assigned or disclosed after the first meeting of the Contract Committee as to why the contract was directed to be cancelled by the said Committee, as such, the action of the Contract Committee is arbitrary, unreasonable and discriminatory. It is also urged that if the tender has been cancelled at the instance of some external agency, then in compliance to the principles of natural justice, the petitioner was entitled to be informed about any such interference by a stranger in the tendering process. 4) The response has been filed by the respondents stating therein that the respondents are performing their duties for the benefit of the general public and none of the constitutional as well as fundamental rights of the petitioner have been violated or infringed at the hands of respondents. It is stated that the JKPTCL had issued e-Tender No.TLMD-VIII/TS/19 of 2022 dated 18.11.2022 with an estimated cost of Rs.7730.00 lacs which was later reduced to Rs.6803.00 lacs due to reduction in the underground 33 KV cable Circuits. It is stated that the JKPTCL had issued e-Tender No.TLMD-VIII/TS/19 of 2022 dated 18.11.2022 with an estimated cost of Rs.7730.00 lacs which was later reduced to Rs.6803.00 lacs due to reduction in the underground 33 KV cable Circuits. It is further stated that Techno-Commercial Bids of six bidders were opened online on 11.02.2023 and during preliminary evaluation of the Techno- Commercial Bids, some shortfalls were noticed by the Tender Opening & Evaluation Committee in almost all the bids and the requisite documents in respect of those shortfalls were obtained from the respective bidders. Thereafter, technical bids were opened online wherein the petitioner emerged as first bidder. It is further submitted that the Committee besides discussing other points, agreed that being L-1, the qualification documents, Joint Venture agreement and bid validity of successful bidder (petitioner) may be re-verified before recommending the case to the Board of Directors. The Chief Engineer (Transmission), JKPTCL, Kashmir Srinagar (Member Secretary) apprised the members of the Contract Committee about the urgency of work and as such, the case was recommended for submission to the Board of Directors for approval. After recommendation of the case by the Contract Committee for approval of Board of Directors, certain queries in respect of qualification criteria of the petitioner were raised. The respondent No.3 requested all the members of the Contract Committee-1 to revisit the case by going through the detailed note prepared by JKPTCL in a meeting held on 12.05.2023, the points raised by other bidders in their correspondences and the reply filed by the JKPTCL, Kashmir and take final call as directed by Secretary Technical, JKPDD (Chairman), vide communication dated 02.06.2023. It is also stated that the petitioner had not submitted JV agreement or any agreement or any qualification document of M/S Garima Enterprises Ghaziabad in their initial bid upto the last date of online submission of bids i.e. 10.02.2023 and nor there had been any mention of M/S Garima Enterprises Ghaziabad in the case history, therefore, in the light of Rule 5.4.5, the JV agreement and other qualification documents accepted by the Tender Opening & Evaluation Committee after the opening of the technical bids in hush-hush manner was found in contradiction to the standing norms of tendering/Standard Bid Documents. Moreso, the agreement submitted by the petitioner was a notarized one, not on non-judicial stamp paper of Rs.100/ as stipulated in the Standard Bid Documents. Moreso, the agreement submitted by the petitioner was a notarized one, not on non-judicial stamp paper of Rs.100/ as stipulated in the Standard Bid Documents. It is further stated that in order to avoid further conflicts which may result in delay in execution of this vital project of NHIDCL, it was unanimously decided by all the members of the Contract Committee-I that the recommendation made by the Committee on 12.05.2023 be treated as null and void and the e-NIT No.TLMD-VIII/TS/19 of 2022 dated 18.11.2022 be cancelled. It is also pleaded by the respondents that in the e-NIT as well as SBD, it is also categorically mentioned that the department reserves the right to cancel any or all the e-Bids/the e-Bid process without assigning any reason thereof and further that the decision of the issuing authority will be final and binding. 5) Mr. Z. A. Shah, learned senior counsel, appearing for the petitioner, submitted that no reason has been assigned by the respondents while issuing the communication dated 09.06.2023 whereby the e-NIT dated 18.11.2022 was cancelled, in respect of which the petitioner had emerged as successful bidder. He further submitted that once the petitioner had emerged as successful bidder, the petitioner was required to be heard before cancelling the NIT and that too at the instance of a stranger. 6) Per contra, Mr. Alla-ud-din Ganai, AAG, submitted that it is the prerogative of the Tender Inviting Authority to accept or reject bid of a bidder and the petitioner has no vested right for allotment of the contract. He laid much stress on the point that the writ petition filed by the petitioner has been rendered in-fructuous, as the e-NIT stands cancelled. 7) Heard and perused the record. 8) The perusal of the record reveals that the petitioner submitted its technical bid and projected itself as a Joint-Venture between M/S M & Co and M/S Magpie Hydel Construction Operation Industries Pvt. At serial No.13, it was stated by the petitioner that JV agreement has been submitted and at serial No.14 under the column ‘incorporation’, the particulars of M/S M & Co and M/S Magpie Hydel Construction Operation Industries Pvt Ltd. have been mentioned. The record further depicts that vide communication dated 23.02.2023, the following shortfall was found and intimated to the petitioner-Joint Venture by the respondents and they were directed to furnish the requisite shortfall documents by 01.03.2023 upto 3.00 PM: Specific supply experience of proposed manufacturer MAF for supply of 33Kv cables obtained from M/s KEC international Ltd. Mumbai but their experience of having executed any supply contract not submitted. 9) In reply to the aforesaid communication, the petitioner vide communication dated 28.02.2023 forwarded the specific & general experience of M/s Garima Enterprises, Ghaziabad along with work done certificates and copy of JV agreement to the respondents. 10) From the record it appears that one complaint was filed in respect of the tendering process undertaken by the respondents, pursuant to which the decision arrived at by the Contract Committee on 12.05.2023 was revisited and it was found that the petitioner at the time of submitting its bid had nowhere mentioned in respect of its Joint Venture with M/S Garima Enterprises, Ghaziabad. The Contract Committee in its meeting held on 09.06.2023 took note of Rule 5.4.5 (Clarification of Bids/Shortfall documents) of Manual for Procurement of Works, 2019, Ministry of Finance, Department of Expenditure, and came to the conclusion that no JV agreement or any qualification document of M/S Garima Enterprises, Ghaziabad was submitted/uploaded by the bidder in their initial bid till last date of online submission of bids i.e. 10.02.2023 and also there was no mention of M/S Garima Enterprises, Ghaziabad, in the case history, therefore, the JV agreement and other qualification documents ought not to have been accepted by the Tender Opening & Evaluation Committee after opening of technical bids. The petitioner has not disputed about the relevant Rule as relied upon by the respondents. The Rule 5.4.5 of Manual for Procurement of Works, 2019 besides other limitations in respect of clarification of bids/shortfall documents provides that the shortfall information/documents should be sought only in case of historical documents which pre-existed at the time of tender opening and which have not undergone change since then. It further prescribes that so far as submission of documents is concerned with regard to the qualification criteria, after submission of tender, only shortfall documents should be asked for and considered. It further prescribes that so far as submission of documents is concerned with regard to the qualification criteria, after submission of tender, only shortfall documents should be asked for and considered. 11) In this context, it would also be appropriate to take note of the relevant clause of the e-NIT under reference which is reproduced as under: “The Department reserves the right to cancel any or all the e-Bids/the e-Bid process without assigning any reason thereof. The decision of department will be final and binding.” 12) The action of the respondents in rejecting the bid of the petitioner and cancelling the e-NIT cannot be faulted, particularly when the respondents have demonstrated a sufficient reason for the same as the petitioner had not mentioned in its technical bid about its Joint Venture with M/S Garima Enterprises, Ghaziabad and also did not submit any such Joint Venture agreement with M/S Garima Enterprises, Ghaziabad till 10.02.2023 i.e. the last of online submission of bids. The contract committee in its meeting held on 12.05.2023 erroneously for reasons best known to the committee did not avert to the issue of acceptance of M/S Garima Enterprises Ghaziabad as one of the partners of Joint venture, when M/S Garima Enterprises figured nowhere in the documents submitted by the petitioner and even the joint venture agreement was not submitted till the last date of online submission of bids. The petitioner under the garb of submitting shortfall documents could have never submitted an altogether new JV agreement with new partner which was not submitted by the petitioner till the last date of submission of online bids. The acceptance of a new J-V agreement with M/S Garima Enterprises after the last date of submission of online bids was a serious lapse on the part of the contract committee, as it amounted to acceptance of a bid submitted by an entirely new entity. By revisiting the decision arrived at in the meeting held on 12.05.2023, in its subsequent meeting on 09.06.2023, the wrong committed earlier has been undone by the contract committee. It hardly matters as to who brought to the notice of the respondents, the violation of the Rules by the contract committee. 13) In “Tata Motors Ltd. v. Brihan Mumbai Electric Supply & Transport Undertaking (BEST), 2023 SCC OnLine SC 671”, the Hon’ble Supreme Court has held as under: 48. It hardly matters as to who brought to the notice of the respondents, the violation of the Rules by the contract committee. 13) In “Tata Motors Ltd. v. Brihan Mumbai Electric Supply & Transport Undertaking (BEST), 2023 SCC OnLine SC 671”, the Hon’ble Supreme Court has held as under: 48. This Court being the guardian of fundamental rights is duty-bound to interfere when there is arbitrariness, irrationality, mala fides and bias. However, this Court has cautioned time and again that courts should exercise a lot of restraint while exercising their powers of judicial review in contractual or commercial matters. This Court is normally loathe to interfere in contractual matters unless a clear-cut case of arbitrariness or mala fides or bias or irrationality is made out. One must remember that today many public sector undertakings compete with the private industry. The contracts entered into between private parties are not subject to scrutiny under writ jurisdiction. No doubt, the bodies which are State within the meaning of Article 12 of the Constitution are bound to act fairly and are amenable to the writ jurisdiction of superior courts but this discretionary power must be exercised with a great deal of restraint and caution. The courts must realise their limitations and the havoc which needless interference in commercial matters can cause. In contracts involving technical issues the courts should be even more reluctant because most of us in Judges' robes do not have the necessary expertise to adjudicate upon technical issues beyond our domain. The courts should not use a magnifying glass while scanning the tenders and make every small mistake appear like a big blunder. In fact, the courts must give “fair play in the joints” to the government and public sector undertakings in matters of contract. Courts must also not interfere where such interference will cause unnecessary loss to the public exchequer. (See: Silppi Constructions Contractors v. Union of India, (2020) 16 SCC 489 ) 54. As observed by this Court in Jagdish Mandal v. State of Orissa, reported in (2007) 14 SCC 517 , that while invoking power of judicial review in matters as to tenders or award of contracts, certain special features should be borne in mind that evaluations of tenders and awarding of contracts are essentially commercial functions and principles of equity and natural justice stay at a distance in such matters. If the decision relating to award of contract is bona fide and is in public interest, courts will not interfere by exercising powers of judicial review even if a procedural aberration or error in assessment or prejudice to a tenderer, is made out. Power of judicial review will not be invoked to protect private interest at the cost of public interest, or to decide contractual disputes. (emphasis added) 14) In view of the above, the present petition is found to be misconceived and the same is dismissed accordingly. Interim direction, if any, shall stand vacated. WP(C) No.1705/2023 1) In view of the cancellation of e-NIT dated 10.06.2023 vide letter dated 25.07.2023, this writ petition has been rendered infructuous and is accordingly dismissed. 2) The record be returned to learned counsel for the respondents.