Research › Search › Judgment

Calcutta High Court · body

2023 DIGILAW 810 (CAL)

Sigma Rail Systems Private Limited v. Research Designs & Standards Organization, Ministry of Railways

2023-05-17

MOUSHUMI BHATTACHARYA

body2023
JUDGMENT : (Moushumi Bhattacharya, J.) 1. The petitioner no. 1 is a manufacturer of a signalling device referred to as MSDAC which is installed to detect movement of trains. The petitioners’ signalling equipment is required to be approved by the respondent no. 1 Research Designs and Standards Organisation (RDSO), Ministry of Railways, before the equipment is sold to the Railways. 2. The petitioners claim, through learned counsel, that all the parameters for approval were obtained by the petitioners as per the RDSO Specification prior to the petitioner no. 1 being enlisted as a vendor. It is also the petitioners’ case that the petitioners’ products have been inspected and approved on 69 earlier occasions by the Executive Director of RDSO, Kolkata/respondent no. 3 and no complaint was ever made by the respondents or by any of the Zonal Railways in respect of the said products. 3. The facts relevant to the matter would appear from the following paragraphs. 4. The petitioner no. 1 manufactures the MSDACs once an order is placed by the Railways and thereafter places the equipment for inspection. The respondent no. 3 was the authority who carried out the inspection of the petitioners’ products on all previous occasions, in terms of clause 11.4.1 of the RDSO Specification. The format of inspection is referred to as the Acceptance Test Proforma (ATP) which is part of the records. The records indicate that the Railways have always given a positive feedback with regard to the petitioners’ products. There are no contemporaneous letters to show that the RDSO or any of the Railways made any complaint with regard to the petitioners’ products. 5. The correspondence exchanged between the parties shows that the petitioners’ products were rejected for the first time on 9.11.2022 on the ground that MSDAC does not comply with clause 5.4.3 of the RDSO Specification Version 3.0. This however appears to be a pre-determined rejection since the inspection of the products was actually carried out on 10.11.2022, which is a day after the recorded rejection. Both these documents are part of the records. This was followed by a letter of 14.11.2022, addressed to the respondent no. 1, where the Executive Director, RDSO Kolkata complained that the petitioners’ products were not compliant with clauses 5.4.3 and 5.3.7 of the RDSO Specification. The letter however accepted that the tests were not included in the ATP. 6. Both these documents are part of the records. This was followed by a letter of 14.11.2022, addressed to the respondent no. 1, where the Executive Director, RDSO Kolkata complained that the petitioners’ products were not compliant with clauses 5.4.3 and 5.3.7 of the RDSO Specification. The letter however accepted that the tests were not included in the ATP. 6. Significantly, RDSO replied to this by a letter of 15.11.2022 specifically stating that clause 5.4.3 had been examined in respect of the resetting; that the Specification did not restrict the number of evaluators to be used to achieve the track section-wise resetting preparatory reset/conditional hard reset; compliance of clause 5.3.7 had been submitted by the petitioners at the time of approval and that inspection of material submitted by the petitioners should be carried out as per the RDSO approved Test Format as was being done earlier. A letter of 15.12.2022 from the North East Frontier Railways/respondent no. 4 also stated that clause 5.4.3 of the RDSO Specification does not specify the use of number of evaluators and further stated that the resetting process may involve two evaluators. 7. Notwithstanding the above certifications, the RDSO sent a letter to the petitioners on 2.1.2023 stating that the Vigilance Cell had advised Independent Safety Assessment (ISA) certification and testing of the MSDACs in Indian conditions to ensure passengers safety, and that the product inspection of the petitioners equipment would be withheld till the ISA certification and testing is complete. 8. The petitioners approached the Court at this stage. The petitioners were given interim protection by an order dated 9.2.2023 and the RDSO was directed to file a Report regarding the number of evaluators and the acclimatization of the petitioners’ equipment to Indian condition. The interim order contains certain findings including on the RDSO’s letter of 15.11.2022 stating that the Specification did not restrict the number of evaluators and that the petitioners had conformed with clauses 5.4.3 and 5.3.7 of the Specification and further that the impugned action of withholding product inspection was contrary to the RDSO Vendor Guidelines of 30.12.2022. The RDSO was also directed to continue with the products inspection of the petitioners without prejudice to its rights and subject to the final decision in the Writ Petition in the manner which had been followed by the RDSO before the inspection was stopped. 9. The RDSO was also directed to continue with the products inspection of the petitioners without prejudice to its rights and subject to the final decision in the Writ Petition in the manner which had been followed by the RDSO before the inspection was stopped. 9. The petitioners thereafter filed a contempt proceedings on RDSO’s alleged non-compliance of the direction dated 9.2.2023, which was later agreed to be disposed of in favour of the final hearing of the writ petition. 10. Several documents were produced by the parties before the final hearing of the writ petition which includes an Inspection Report of the petitioners’ products pursuant to inspections held on 29.03.2023 and a final Report in the form of an affidavit was filed by the respondent nos. 1 to 3 in reply to the petitioners’ affidavit-in-reply. It appears from the totality of the documents filed before the Court that the issue is of the petitioners’ alleged non-compliance and violation of clauses 5.4.3, 5.3.7 and 5.0.5 of the RDSO Specification. 11. Clause 5.4.3 relates to track section wise resetting as preparatory reset or conditional hard reset. The Specification does not mention the number of evaluators to be used and the letters from the respondents dated 15.11.2022 and 26.11.2022 clarified that there is no restriction on the number of evaluators to be used for achieving both types of resetting. The letter of 26.11.2022 also stated that the petitioners are in compliance with clause 5.4.3 of the RDSO Specification. The contents of this letter is also reiterated by a letter of the North East Frontier Railways dated 15.12.2022. It is undisputed that the Executive Director of RDSO, Kolkata, respondent no. 3, tested and approved the petitioners’ products using two evaluators on 69 previous occasions spread over a period of 3 years. 12. Since there has been no change in the products manufactured by the petitioners which all along conformed to the ATP, the sudden refusal on the part of the RDSO and respondent no. 3 to inspect the petitioners’ products is untenable and contrary to the conduct expected of a statutory authority. 13. Moreover, the so-called “joint inspection” which took place on 10.11.2022 was done unilaterally by the respondent no. 3. As stated earlier, the alleged non-conformity Report was issued a day earlier on 9.11.2022. 3 to inspect the petitioners’ products is untenable and contrary to the conduct expected of a statutory authority. 13. Moreover, the so-called “joint inspection” which took place on 10.11.2022 was done unilaterally by the respondent no. 3. As stated earlier, the alleged non-conformity Report was issued a day earlier on 9.11.2022. The petitioners’ bona fides would also appear from a letter dated 22.2.2023 whereby the petitioners offered to supply extra evaluators at no additional cost in keeping with the requirements of the Railways. The petitioners have also enclosed a document to show that the signalling equipment produced by the petitioners’ competitors at various places all over the country use two evaluators and that such equipments have been approved by the RDSO. 14. The other area of alleged non-compliance is clause 5.3.7 of the RDSO Specification. The letters of RDSO dated 15.11.2022 and 26.11.2022 have already clarified that the petitioners are in compliance with the clauses of the RDSO Specification including clause 5.3.7. The letter of 26.11.2022 further states that the joint inspection carried out on 11.11.2022 by the Executive Director RDSO is not appropriate considering the Specification clause. It is also significant that the respondent no. 3 admitted in his letter dated 14.11.2022 addressed to the RDSO that the tests conducted to check compliance are not part of the approved ATP. 15. The respondents have further alleged the violation of clause 5.0.5 of the RDSO Specification. This is a new ground taken in the final Report in the form of affidavit filed by the respondent nos. 1-3. The materials placed before the Court show that the testing for clause 5.0.5 of the Specification which requires the push trolley wheels to not be counted by MSDAC is also covered since the tests for compliance of clause 5.0.5 have successfully been conducted in laboratory conditions by the RDSO before giving approval of the petitioners’ equipment. There was a further field testing of the equipment by the RDSO after approval and also by the respondent no. 3 on 69 earlier occasions. The tests were conducted by using standard wheel diameter of 450 mm and the product was passed in accordance with the ATP. There was a further field testing of the equipment by the RDSO after approval and also by the respondent no. 3 on 69 earlier occasions. The tests were conducted by using standard wheel diameter of 450 mm and the product was passed in accordance with the ATP. The documents disclosed subsequently however show that the Executive Director RDSO tested the equipment using a non-standard wheel diameter of 560 mm which is not permitted since the RDSO itself has specified uniform dimensions for trolley wheels used by the Indian Railways. Moreover, the joint testing of the petitioners’ products by the Southern Railways and the South East Central Railway on 6.3.2023 and 10.3.2023 respectively, found the equipment to be satisfactory and the MSDAC units were found to be in compliance with the RDSO Specification including clause 5.0.5. 16. A significant fact which was taken into account by the Court at the time of passing the interim order dated 9.2.2023 was the trigger for the sudden volte face of the RDSO. Records show that the inspection of the petitioners’ products was stopped on a complaint received by a person holding himself out to be an Advocate of Supreme Court. RDSO’s conduct of acting upon this stray compliant is contrary to the Indian Railways Vigilance Manual and the Central Vigilance Commission Guidelines and stopping of the inspection was also contrary to the RDSO Vendor Guidelines in this regard. 17. It may also be pertinent to mention that the petitioner no. 1 sells its equipment directly to the Railways at a cost of Rs. 300000/unit while its competitors sell the same to traders who resell the equipment to the Railways at Rs. 700000/- unit. Hence resulting in an annual loss of approximately Rs. 1100 crores to the Railways for 30,000 units of MSDAC purchased by the Railways every year. The inexplicable refusal of the respondents to inspect the petitioners’ products and in essence render them unviable without due cause, given that the petitioners’ products have passed the tests 69 times previously and by the same authorities, smacks of mala fides. The presumable object of the entire exercise of refusing the inspection of the petitioners’ products is to prevent the petitioners from supplying the equipment directly to the Railways and force the petitioners to route the same through traders at a substantial higher price. 18. The presumable object of the entire exercise of refusing the inspection of the petitioners’ products is to prevent the petitioners from supplying the equipment directly to the Railways and force the petitioners to route the same through traders at a substantial higher price. 18. The arguments made by learned counsel appearing for the Railways on the technical aspects of the matter including deployment of evaluators according to detection points is outside of the pleadings and beyond the RDSO Specification as well as the ATP. 19. WPA 1050 of 2023 is accordingly allowed and disposed of by by cancelling the report dated 9.11.2022 and alleged joint report dated 10.11.2022. The respondent nos. 1, 2 and 3 are accordingly directed to commence the inspection within a period of 7 days from today in accordance with Specification framed by the RDSO and the ATP applying the identical procedure for testing/inspection and with the same frequency as was being done in the 69 prior occasions before the impugned documents dated 9.11.2022 and 10.11.2022 were issued. The petitioners’ equipment shall be inspected by the RDSO and respondent no. 3 within a period of 7 days as directed from the date of this judgment. 20. Learned counsel appearing for the respondent no. 1 prays for stay of the operation of the Judgment. Considering the facts and circumstances discussed in the judgment and the proceedings where contempt initiated by the petitioners was shelved for hearing of the main writ petition, the prayer for stay is considered and refused. Urgent photostat certified copies of this judgment, if applied for, be supplied to the parties upon fulfillment of requisite formalities.