Research › Search › Judgment

Gauhati High Court · body

2025 DIGILAW 1834 (GAU)

Latala Construction Co. v. Union of India

2025-11-12

DEVASHIS BARUAH

body2025
JUDGMENT AND ORDER : DEVASHIS BARUAH, J. Heard Ms. M. Sharma, the learned counsel appearing on behalf of the Petitioner and Mr. H. Gupta, the learned CGC appearing on behalf of the Respondent Nos. 1 and 2. 2. The present petition is filed challenging the termination notice dated 04/05.09.2025; seeking directions upon the Respondents to refund the Earnest Money Deposit, the Security Deposit as well as the Bank Guarantee. Further to that, the Petitioner also sought for a relief that the Respondents be also directed to permit the Petitioner to resume the balance work after the withdrawal of the mining ban in accordance with the binding directions of the Supreme Court. 3. It is also seen that in the instant writ petition, the Petitioner has sought for the certain interim reliefs. The same being relevant are reproduced herein under: “(i) Stay the operation and implementation of the impugned termination notice dated 04/05.09.2025 issued by the Respondent No.2, i.e., the Senior Divisional Engineer/I, Lumding Division, N.F. Railway, pending conclusion of the arbitration proceedings initiated between the parties; (ii) Restrain the Respondents from taking any coercive or adverse action against the Petitioner, including but not limited to forfeiture of Earnest Money Deposit (EMD), Security Deposit, or encashment of the Performance/Bank Guarantee; (iii) Restrain the Respondents from blacklisting or debarring the Petitioner from participating in the balance work or future contracts related to the subject matter of the present dispute, pending final adjudication of this Writ Petition; and (iv) May pass such other or further interim order(s) or direction(s) as this Hon’ble Court may deem fit and proper in the facts and circumstances of the case.” 4. It is relevant to observe that in the impugned termination notice dated 04/05.09.2025, it was mentioned that the Letter of Acceptance was issued on 20.11.2024 with a completion period of 12 months and the performance was found to be wholly inadequate. It was also mentioned that the Petitioner had supplied only 1535 cum of ballast since the last loading done on 28.02.2025 resulting in issuance of 7 days notice and 48 hours notice on 09.07.2025 and 24.07.2025 respectively. Under such circumstances, in exercise of powers under Clause 62 of the Standard General Conditions of the Contract, the contract with the Petitioner was rescinded with the stipulation that the balance work under the contract would be carried out independently without the participation of the Petitioner. Under such circumstances, in exercise of powers under Clause 62 of the Standard General Conditions of the Contract, the contract with the Petitioner was rescinded with the stipulation that the balance work under the contract would be carried out independently without the participation of the Petitioner. Further to that, the Security Deposit would be forfeited and the Performance Guarantee would also be encashed. 5. It is the case of the Petitioner that the Petitioner was not in a position to make the supply in view of certain orders being passed by the Supreme Court and as such, the said termination was not in accordance with law. 6. At this stage, this Court finds it very pertinent to take note of that the power to rescind the contract is provided in Clause 62((2) of the Standard General Conditions of Contract and the termination order appears to be made in pursuance to the power exercised under Clause 62(2) of the said Standard General Conditions of Contract. 7. This Court further finds it relevant to take note of Clause 64 of the Standard General Conditions of Contract which is an Arbitration Clause. The question therefore arises as to whether this Court should at all exercise the jurisdiction that too when the Petitioner had itself approached for initiation of arbitration proceedings and more particularly when the interim relief so sought for is specific that these interim directions were to be passed during the pendency of the arbitration proceedings. It is the opinion of this Court that Section 9 and Section 17 of the Arbitration and Conciliation Act, 1996 (for short ‘the Act of 1996’) provides adequate safeguards to the Petitioner to approach the appropriate forum if the Petitioner seeks any interim directions pending the arbitration proceedings. 8. Considering the above, this Court therefore is not inclined to entertain the instant writ petition for which the instant writ petition stands dismissed. 9. The dismissal of the instant writ petition however shall not prejudice the Petitioner to approach the Court within the meaning of Section 2 (e) of the Act of 1996 seeking interim directions in terms with Section 9 the Act of 1996 or the Arbitral Tribunal in terms with Section 17 of the Act of 1996. 10. This Court for the sake of clarity observes that this Court had not decided anything on the legality and the validity of the impugned termination notice.